Land and Environment Court
of New South Wales
CITATION: Wollongong City Council v. Masood Falamaki [1998] NSWLEC 130 PARTIES: APPLICANT
RESPONDENT
Wollongong City Council
Masood FalamakiFILE NUMBER(S): 40091 of 1997 CORAM: Talbot J KEY ISSUES: :- LEGISLATION CITED: CASES CITED: Ziade v Woollahra Council & Anor unreported CA40457/93 28 April 1994 at p 6 DATES OF HEARING: 1-5/06/98 DATE OF JUDGMENT:
06/19/1998LEGAL REPRESENTATIVES: RESPONDENT
APPLICANT
Mr C W McEwen (Barrister)
Peedom Brodie & Ward Solicitors
In Person
JUDGMENT:
The respondent is the owner of a property known as 12 Arter Avenue, Fig Tree within the area of the applicant council. Dr Falamaki is an engineer by profession and he appeared without legal representation.
The council is the statutory authority responsible for administration of the Local Government Act 1993 within its area.
On 8 December 1995 the council issued an approval to the erection of a three storey dwelling house on the respondent's land subject to conditions. The application for approval was supported by a report by Coffey Partners dated 30 October 1995.
Conditions 6 and 7 of the building approval are in the following terms:-
6 All proposed building works must comply with the recommendations of the geotechnical engineer's report No SCL 5000/1-65 dated 30 October 1995.
7 Before construction is commenced, plans and specifications prepared and endorsed by a suitably qualified and approved structural engineer shall be submitted to, and approved by Council for all reinforced concrete floor slabs, the footings of the proposed structure, the proposed retaining walls, the proposed works required to stabilise the rock and excavation and all structural steelwork.
Plans described as structural plans were presented to the council on 22 October 1996 and approved by a council Health and Building Surveyor the following day, 23 October 1996.
Work commenced on the site during December 1996 with an excavation down to bedrock at a depth of between seven and eight metres at the deepest point of the cut. Subject to resolution of an evidentiary issue in favour of the respondent, the council concedes that the excavation was, for present purposes, carried out sufficiently in accordance with the structural plans approved on 23 October.
Amended foundation plans were presented to council on 14 February 1997 and approved, following which council officers carried out an inspection of pad footings on 20 February 1997.
In a letter dated 21 February 1997, the council requested the respondent to provide engineer's certification of the footings and retaining walls and requested that he advise council on completion of the work.
After receipt of the letter dated 21 February 1997, the respondent completed twenty one pad footings and most of the foundation beams. Erection of the structural columns had commenced by April 1997 when the council wrote to the respondent, on 17 April 1997, referring to an inspection which indicated the development works "are not in accordance with the building consent". The letter continued:-
Council has serious concerns as to the extent of excavation on the site which is clearly…
Keep reading for free
Create a free CaseChat account to read Wollongong City Council v Masood Falamaki and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [1998] NSWLEC 130
- Decision Date
CaseChat Overview and Summary
The court found that Falamaki had breached Condition 6 of the building approval, as he had not complied with the recommendations of the geotechnical engineer's report. The court found that Falamaki had excavated the site to a greater depth than was approved, and that the excavation was not in accordance with the approved plans. The court found that Falamaki had not properly understood the definition of rock and the categorisation of material identified by the geotechnical report as being suitable as a bed for foundation. The court found that although Falamaki's actions had created a critical situation, they were done in good faith.
The court found that the council had been careless in the way it had approved the plans in October 1996, and had delayed in demanding a stop to work. The court found that the council had failed to provide answers to questions raised by Falamaki or to furnish essential particulars of the modelling undertaken on council's behalf. The court found that the council had also failed to obtain competent advice.
The court exercised its discretion not to make a declaration or order for Falamaki to carry out remedial works, provided that Falamaki provided certification of the engineering specification for the structure. The court found that the structure could be completed in a way which ensured the appropriate loads were supported and the site was made safe from landslip. The court found that the excavation could not be left in its present condition for an extended period.
The court dismissed the council's application for a declaration and order for Falamaki to carry out remedial works, but reserved the question of costs. The court made an order that the matter be adjourned to allow Falamaki the opportunity to obtain acceptable certification. The court made an order that either party had liberty to apply on two days notice.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi