Supreme Court at BrisbaneDELIVERED ON:
21 August 2020
DELIVERED AT:
Brisbane
HEARING DATE:
10 to 14 February and 1 May 2020
Further written submissions received on 8 May 2020JUDGE:
Bradley J
ORDER:
The Order of the Court is that:
1. The first defendant pay to the first plaintiff the sum of $329,034.48.
2. The first defendant pay the first plaintiff’s costs of the claim on the standard basis.
3. The counterclaim against plaintiffs is dismissed.
4. The first defendant pay the plaintiffs’ costs of the counterclaim on the standard basis.
CATCHWORDS:
GUARANTEE AND INDEMNITY – CONTRACT OF GUARANTEE – OTHER MATTERS – where the defendants held shares in a company that was indebted to the first plaintiff – where each defendant guaranteed the company’s performance of its obligations to the first plaintiff – where the company was in monetary and non-monetary default under facilities the first plaintiff had extended to it – where the first plaintiff appointed the second plaintiff as receiver and manager of certain property of the company – where the first plaintiff demanded payment from each defendant pursuant to the guarantees they executed – where the first plaintiff obtained default judgment against the second defendant – where the first defendant filed a defence and counterclaim, in which he alleged various breaches of codes of conduct by each plaintiff – where the first defendant denies he is liable to the first plaintiff under the guarantee on which he is sued on account of the alleged breaches – whether either plaintiff committed any of the alleged breaches so that the guarantee on which the first defendant is sued is unenforceable
Equititrust Ltd v Gamp Developments Pty Ltd & Ors [2009] QSC 115, applied
Jones v Dunkel (1959) 101 CLR 298, applied
National Australia Bank Ltd v Troiani [2002] QCA 196, appliedCOUNSEL:
G Handran for the plaintiffs
The first defendant appeared on his own behalf
SOLICITORS:
Gadens for the plaintiffs
The first defendant appeared on his own behalf
The first plaintiff (Westpac) claims $329,034.48 from the first defendant (Mr Heslop). Westpac says Mr Heslop is the guarantor of a debt in this amount owed by Lonrae Pty Ltd (Lonrae) pursuant to a written guarantee and indemnity Mr Heslop executed on 24 June 2004 (the Guarantee).
Lonrae is a company in which Mr Heslop and the second defendant (Ms Harper) held shares as trustees. Westpac obtained default judgment against Ms Harper on 16 December 2016 pursuant to a separate guarantee of Lonrae’s debt and personal covenants in a mortgage. These reasons do not deal with her personal…
Keep reading for free
Create a free CaseChat account to read Westpac Banking Corporation v Heslop (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] QSC 256
- Decision Date
CaseChat Overview and Summary
The central legal issues before the court were whether Westpac had breached its obligations under various banking codes of practice and whether the receiver had breached her obligations under receivers' codes of professional practice. The court had to assess these allegations in light of the evidence presented and determine their impact, if any, on the enforceability of the guarantee. The court also had to consider the defendant's failure to give evidence, which could potentially affect the outcome of the case.
The court found that the defendant failed to provide any evidence of the alleged breaches by Westpac or the receiver. Despite the defendant's initial intention to testify, he ultimately chose not to do so, which the court inferred meant that his evidence would not have helped his case. Consequently, the court rejected the defence based on alleged breaches of the codes of conduct. Additionally, the court dismissed the defendant's counterclaim against the plaintiffs. The court held that the defendant's obligation under the guarantee was to ensure the company met its obligations to Westpac, and this obligation remained unaffected by any alleged breaches by the plaintiffs.
The court ordered that the defendant pay Westpac the sum of $329,034.48, along with the costs of the claim on the standard basis. The counterclaim against the plaintiffs was dismissed, and the defendant was ordered to pay the plaintiffs' costs of the counterclaim on the standard basis. The court did not find any basis for awarding costs on an indemnity basis, as the contractual agreements between the parties did not provide for such an award.
Orders
Orders of the court
The Order of the Court is that:
1. The first defendant pay to the first plaintiff the sum of $329,034.48.
2. The first defendant pay the first plaintiff’s costs of the claim on the standard basis.
3. The counterclaim against plaintiffs is dismissed.
4. The first defendant pay the plaintiffs’ costs of the counterclaim on the standard basis.
Background
Background to the litigation
The matter came before the court for trial following a default judgment against the second defendant and a defence and counterclaim filed by the first defendant, Mr. Heslop. The case involved several stages of pre-trial directions hearings, where Mr. Heslop indicated he would give evidence. However, on the scheduled day, he did not appear and subsequently advised the court that he would not be calling himself to give evidence. The trial resumed weeks later, and Mr. Heslop did not provide any written evidence or appear. The court considered the evidence presented and the arguments from both sides before delivering its judgment.
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
It follows that Mr Heslop has failed to make out any part of his defence or counterclaim that the Receiver failed to comply with the ARITA Code. Consideration of the other matters pleaded in the defence and counterclaim At the trial, Mr Heslop informed the Court he only wished to pursue his allegations of breaches of the Banking Code by Westpac and of the ARITA Code by the Receiver. For completeness’ sake, these reasons deal briefly with some of the other allegations pleaded by Mr Heslop. National Consumer Credit Protection Act allegations In his defence, Mr Heslop pleaded that Westpac breached ss 128, 129, 130, 131 and 132 of the National Consumer Credit Protection Act 2009 (Cth) (the NCCPA) in respect of the loans made to Lonrae in 2004, 2007, 2008 and 2012. He made no oral or written submissions about these allegations. In short, these provisions prohibit a credit provider from entering into a credit contract with a consumer (or increasing the consumer’s credit limit) unless the credit provider has made an assessment of whether the credit contract will be unsuitable for the consumer if it is entered into or if the credit limit is increased. The assessment must have been made within 90 days of the contract or the increase. The credit provider must make reasonable enquiries and take reasonable and prescribed steps before making the assessment. Mr Heslop’s allegations must be rejected. The operative provisions of the NCCPA, including the National Credit Code, commenced on 1 April 2010. They did not apply in June 2004, when Westpac and Lonrae entered into the Burke BFA, in July 2007, when they entered into the IPL and the Gabba BFA, in November 2008, when they entered into the Parc BFA and varied the IPL, or in March 2010, when Westpac offered the investment property loans for the Boambillee Drive property. The NCCPA was in force in December 2010 when the BBBL was first drawn, in September 2011 when the Hub BFA was signed, and in December 2012 when the BBBL facility was changed. These NCCPA provisions apply to credit contracts where the debtor is a natural person or a strata corporation and where the credit is wholly or predominantly for personal, domestic or household purposes or to purchase, renovate or improve residential property for investment purposes.[28] A debtor is the person liable to pay or repay the credit, but does not include a guarantor like Mr Heslop. In each of these Westpac loans, the debtor was Lonrae. It was not a natural person or a strata corporation. The credit was provided for commercial purposes, to acquire and to provide working capital for MLR businesses, and not wholly or predominantly for purposes that would bring the lending within the scope of these provisions. [28]National Credit Code (Cth), ss 4, 5. Human Rights allegations Mr Heslop pleaded that Westpac and the Receiver: “breached Article 12 of the Human Rights Act by engineering the default and subsequent events which led to assault and unlawful detention of [Mr Heslop] and the sequential loss to both [Mr Heslop] and [Ms Harper] by forcefully and unlawfully taking possession of [the Parc MLR business]. This breach resulted in the loss of dignity by both [Mr Heslop] and [Ms Harper].”