FEDERAL COURT OF AUSTRALIA
Direct Factory Outlets Pty Ltd v Westfield Management Ltd
[2005] FCA 34
AVIATION – airport development – land uses – leases and sub-leases – development of Brisbane Airport – aeronautical and non-aeronautical facilities – whether permitted use under the Airports Act 1996 (Cth) – challenge by retail competitor
Airports Act 1996 (Cth)
Airports (Building Control) Regulations 1996 (Cth)
Airports Bill 1996
Evidence Act 1995 (Cth)
Federal Airports Corporation Act 1986 (Cth)
Airports (Transitional) Act 1996 (Cth)
Aviation Legislation Amendment Act (No 1) 1997 (Cth)
Acts Interpretation Act 1901 (Cth)City Area Leases Ordinance 1936-64 (ACT)
Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355
American Dairy Queen (Qld) Pty Ltd v Blue Rio Pty Ltd (1981) 147 CLR 677
NSW Associated Blue-Metal Quarries Ltd v Federal Commissioner of Taxation (1956) 94 CLR 509
Collector of Customs v Agfa-Gevaert (1996) 186 CLR 389
Maunsell v Olins [1975] AC 373
PMT Partners Pty Ltd (in liq) v Australian National Parks and Wildlife Service (1995) 184 CLR 301
O’Grady v Northern Queensland Co Ltd (1990) 169 CLR 356
Broken Hill Proprietary Company Ltd v Commissioner of Taxation (1968) 41 ALJR 377
University of Western Australia v City of Subiaco (1980) 52 LGRA 360
Owendale Pty Limited v Anthony and Another (1967) 117 CLR 539
Marks & Spencer Ltd v London County Council [1952] Ch 549DIRECT FACTORY OUTLETS PTY LTD v WESTFIELD MANAGEMENT LTD, CPT MANAGER LTD and BRISBANE AIRPORT CORPORATION LTD
Q92 OF 2003COOPER J
BRISBANE
3 FEBRUARY 2005
IN THE FEDERAL COURT OF AUSTRALIA
DISTRICT REGISTRY
Q92 OF 2003
BETWEEN:
DIRECT FACTORY OUTLETS PTY LTD
ACN 087 112 301
APPLICANTAND:
WESTFIELD MANAGEMENT LTD
ACN 001 670 579
FIRST RESPONDENTCPT MANAGER LTD
ACN 054 494 307
SECOND RESPONDENTBRISBANE AIRPORT CORPORATION LTD
ACN 076 870 650
THIRD RESPONDENT
JUDGE:
COOPER J
DATE OF ORDER:
3 FEBRUARY 2005
WHERE MADE:
BRISBANE
THE COURT DECLARES THAT:
1.The final Master Plan for the Brisbane Airport approved by the Minister for Transport and Regional Services on 7 May 2004 is a valid and effective final Master Plan for the purposes of the Airports Act 1996 (Cth).
2.The Major Development Plan for the Outlet Centre approved by the Minister for Transport and Regional Services on 25 June 2004 is a valid and effective Major Development Plan for the purposes of the Airports Act 1996 (Cth).
3.The works permits issued by the Building Controller for the Brisbane Airport on 24 September 2001 and 12 September 2002 under the Airports (Building Control) Regulations 1996 (Cth) are valid and effective works permits for the purposes of those Regulations and the Airports Act 1996 (Cth).
4.The entry into the written agreements to lease by Brisbane Airport Corporation Limited and Direct Factory Outlets Pty Ltd, dated 28 July 2003 (as varied by Deed of Variation dated 30 July 2004) and 30 July 2004 respectively, and the carrying of the terms of such agreements into effect are:
(a)not conduct by Brisbane Airport Corporation…
Keep reading for free
Create a free CaseChat account to read We Two Pty Ltd v Shorrock (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2005] FCA 34
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the Major Development Plan, works permits, and agreements between BAC and DFO were valid and enforceable, and if BAC had the authority to grant the necessary permits. The court had to examine the statutory framework governing airport development, the Airports Act 1996, and the Airports (Building Control) Regulations 1996, to determine the extent of BAC's powers and the legality of its actions.
In its reasoning, the court found that the Major Development Plan and associated permits were valid and effective, as they had been duly approved by the Minister for Transport and Regional Services. The court dismissed the contentions of the respondents that the Building Controller lacked the authority to issue the permits. The court also held that the agreements between BAC and DFO were lawful and did not contravene the Airports Act or the regulations. The declarations sought by DFO were largely denied, as the court found that the development plans were still conceptual and it was premature to make the declarations. However, the court did make specific declarations affirming the validity of the final Master Plan, the Major Development Plan, the works permits, and the lease agreements.
The final orders of the court were that the application by Westfield and Centro would be dismissed, and specific declarations regarding the validity of the Major Development Plan, works permits, and lease agreements were made in favour of BAC and DFO. The court reserved the question of costs for further hearing.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Established by: COOPER J
Full text does not contain this section.