CITATION: Watpac Constructions v Austin Group [2010] NSWSC 347 HEARING DATE(S): 16/4/10 JURISDICTION: Equity Division
Technology & Construction ListJUDGMENT OF: McDougall J at 1 EX TEMPORE JUDGMENT DATE: 16 April 2010 DECISION: 1. I make orders in accordance with paragraphs 1 to 4 of the short minutes of order initialled by me and dated today's date.
2. I stay order 4 for 28 days from today's date.CATCHWORDS: BUILDING AND CONSTRUCTION – where adjudication determination based on payment claim that included impermissibly re-agitated claims – consequences of issue estoppel and abuse process – whether determination void or whether enforcement of rights may be restrained to extent of invalidity – where adjudication determination involved substantial denial of natural justice – consequences of denial of natural justice – whether determination void – whether determination wholly void or void to extent of denial – Building and Construction Industry Security of Payment Act 1999 (NSW). - COSTS – whether partial success and partial failure – costs to follow event. LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999 (NSW) CATEGORY: Separate question CASES CITED: Brodyn Pty Limited v Davenport (2004) 61 NSWLR 41
Holmwood Holdings Pty Ltd v Halkat Electrical Contractors Pty Ltd [2005] NSWSC 1129
John Holland Pty Ltd v Roads & Traffic Authority of New South Wales (2007) 23 BCL 205
Reiby Street Apartments Pty Limited v Winterton Constructions Pty Limited [2006] NSWSC 375
Robson Civil Projects Pty Limited v Walter Mining Pty Limited [2009] NSWSC 1071
Trysans Pty Ltd v Club Constructions (NSW) Pty Limited [2007] NSWSC 1298
Transgrid v Siemens Ltd (2004) 61 NSWLR 521
Urban Traders v Paul Michael [2009] NSWSC 1072PARTIES: Watpac Construction (NSW) Pty Limited (Plaintiff)
Austin Corp Pty Limited (Defendant)FILE NUMBER(S): SC 2010/41832 COUNSEL: N J Kidd (Plaintiff)
F C Corsaro SC (Defendant)SOLICITORS: Maddocks Lawyers (Plaintiff)
Crisp Legal (Defendant)
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY & CONSTRUCTION LIST
McDOUGALL J
16 April 2010 (ex tempore – revised 21 April 2010)
2010/41832 WATPAC CONSTRUCTIONS (NSW) PTY LIMITED v AUSTIN CORP PTY LIMITED (No.2)
JUDGMENT (On form of orders and costs)
1 HIS HONOUR: The question for decision today is: what orders should be made to give effect to my reasons for judgment delivered on 19 March 2010 ([2010] NSWSC 168)? That question arises against the following background.
Background
2 The plaintiff (Watpac) and the first defendant (Austin) were parties to a subcontract whereby Austin undertook to perform air conditioning and mechanical services work for Watpac. It was common ground that this subcontract was a construction contract for the purposes of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act).
3 Austin served a number of payment claims under the Act. They included the "December" payment claim that was ultimately the subject of the "February" adjudication determination made by the second defendant (the second adjudicator). It was that determination which gave rise to the disputes dealt with in my earlier reasons…
Continue reading Watpac Constructions v Austin Group
Sign in free to access the full text
- AGLC
- Watpac Constructions v Austin Group [2010] NSWSC 347
- Case
- [2010] NSWSC 347
- Decision Date
CaseChat Overview and Summary
The court was required to decide whether the adjudication determination was void because it was based on a payment claim that included impermissibly re-agitated claims. The court also had to determine whether the adjudication determination was void because it involved a substantial denial of natural justice. Additionally, the court had to consider whether the determination was void in its entirety or only to the extent of the denial of natural justice. The court had to weigh the consequences of issue estoppel and abuse of process against the need for finality in adjudication determinations.
The court found that the adjudication determination was not void because it was based on a payment claim that included impermissibly re-agitated claims. The court held that the issue estoppel doctrine did not apply in this case because the determination was not based on the re-agitated claims. The court also found that there was no abuse of process because the Austin Group had not acted improperly in presenting the payment claim. However, the court found that the adjudication determination was void because it involved a substantial denial of natural justice. The court held that the denial of natural justice was so significant that it rendered the determination invalid. The court found that the determination was void in its entirety because the invalidity affected the entire determination.
The court ordered that the adjudication determination was void and could not be enforced. The court also ordered that costs were to follow the event, with the Austin Group to pay Watpac Constructions' costs of the proceedings.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.