Waterford PPG Pty Ltd v Civil Constructors (Aust) Pty Ltd

Link copied
Case Copied 11 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Waterford PPG Pty Ltd v Civil Constructors (Aust) Pty Ltd [2020] QSC 8

PARTIES:

WATERFORD PPG PTY LTD (ABN 73 615 440 081)

(applicant)

v
CIVIL CONSTRUCTORS (AUST) PTY LTD (ABN 56 169 588 194)

(first respondent)

and

HELEN DURHAM (ADJUDICATOR NO J1105410)
(second respondent)

FILE NO/S:

No 12705 of 2019

DIVISION:

Trial Division

PROCEEDING:

Application

ORIGINATING COURT:

Supreme Court of Queensland

DELIVERED ON:

12 February 2020

DELIVERED AT:

Brisbane

HEARING DATE:

12 December 2019

JUDGE:

Boddice J

ORDER:

1.     The originating application filed 14 November 2019 be dismissed.

2.     I will hear the parties as to costs and any other orders.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where the applicant and first respondent entered into a contract for the construction of roadworks, drainage, sewerage reticulation, water supply, conduits and stormwater quality in respect of a development – where the works undertaken pursuant to the contract included the installation of waste tanks and the installation of a boundary kit and lateral to connect to the proposed development lots – where the first respondent served a payment claim on the applicant for works undertaken – where the applicant disputed the payment claim – where an adjudication application was lodged in respect to the disputed payment claim – where the second respondent decided the amount outstanding in respect of the payment claim was $603,767.27 – where the applicant contends the work is building work – where the applicant contends the first respondent contravened s 42(1) of the Queensland Building and Construction Commission Act 1991 (Qld) by undertaking to carry out the works – where the applicant seeks declaratory relief that the adjudication decision is void by reason of jurisdictional error – whether the first respondent breached s 42(1) of the Queensland Building and Construction Commission Act 1991 (Qld) – whether the adjudication decision should be void


Building and Construction Industry Payments Act 2004 (Qld)
Queensland Building and Construction Commission Act 1991 (Qld), s 42, Schedule 2
Queensland Building and Construction Commission Regulation 2018 (Qld), Schedule 1

Low v MCC Pty Ltd & Ors [2018] QSC 6
Northbuild Constructions Pty Ltd v Central Interior Linings Pty Ltd
[2012] 1 Qd R 525
Ooralea Developments Pty Ltd v Civil Contractors (Australia) Pty Ltd [2015] 1 Qd R 311
Theiss Pty Ltd v Warren Brother Earthmoving Pty Ltd
[2013] 2 Qd R 75
The Trustee for Hardev Property (Dev 10) Unit Trust v Palmgrove Holdings Pty Ltd & Ors [2019] QSC 208
Watkins Contracting Pty Ltd v Hyatt Ground Engineering Pty Ltd [2018] QSC 65

COUNSEL:

P Hastie QC with SB Whitten for the Applicant

M O Jones for the First Respondent

SOLICITORS:

CDI Lawyers for the Applicant

HWL Ebsworth for the First Respondent

  1. On 11 April 2019, the second respondent delivered a decision in respect of an adjudication application made under the Building and Construction Industry Payments Act

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Waterford PPG Pty Ltd v Civil Constructors (Aust) Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] QSC 8
Decision Date

CaseChat Overview and Summary

In the case of Waterford PPG Pty Ltd v Civil Constructors (Aust) Pty Ltd, the applicant, Waterford PPG, and the first respondent, Civil Constructors (Aust) Pty Ltd, were involved in a dispute over the construction of roadworks, drainage, sewerage reticulation, water supply, conduits, and stormwater quality for a development. The dispute centred on a payment claim issued by Civil Constructors for the work undertaken, which Waterford PPG disputed. The matter was referred to adjudication, resulting in a decision that the amount outstanding was $603,767.27. Waterford PPG sought declaratory relief, arguing that the adjudication decision was void due to jurisdictional error, alleging that Civil Constructors contravened section 42(1) of the Queensland Building and Construction Commission Act 1991 (Qld) by undertaking the works.

The legal issues before the court were whether Civil Constructors breached section 42(1) of the QBCC Act by undertaking the works and whether the adjudication decision should be void. The court examined the definitions and exceptions set out in the QBCC Act and the Building and Construction Commission Regulation 2008 (Qld). The court found that the work undertaken by Civil Constructors fell within the exception in clause 11 of Schedule 1 of the Regulations, which excludes works for water reticulation systems, sewerage systems, or stormwater drains from the definition of building work. The court concluded that Civil Constructors did not contravene section 42(1) of the QBCC Act by undertaking the works and that the adjudication application was properly made and the second respondent had jurisdiction to make the adjudication decision. Consequently, the court dismissed the originating application.

The court's reasoning was based on the legislative intent to exclude certain works from the definition of building work and the specific wording of the exception in clause 11 of Schedule 1 of the Regulations. The court held that to find the work undertaken by Civil Constructors constituted "building work" would defeat the express wording of the exception. The court also considered the definition of "building work" and "carry out" under the QBCC Act and concluded that the works undertaken by Civil Constructors were not "building work" within the meaning of the Act.

The final orders of the court were that the originating application filed on 14 November 2019 be dismissed. The court also indicated that it would hear the parties regarding costs and any other orders.

Orders

Orders of the court

1. The originating application filed 14 November 2019 be dismissed.

2. I will hear the parties as to costs and any other orders.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Third, clause 11 of Schedule 1 to the Regulations evidences a legislative intent to exclude particular works from the definition of building work. To hold that the undertaking of work associated with a proposed subdivision involving the construction of a sewerage system, including the installation of waste tanks and connections to pressure mains, constitutes “building work” within the meaning of the QBCC Act would specifically defeat the express wording of the exception in clause 11 of Schedule 1.Conclusions In undertaking the relevant work pursuant to the contract, the first respondent did not contravene section 42(1) of the QBCC Act. The works undertaken by the first respondent were undertaken pursuant to the contract and the first respondent was entitled to issue the disputed payment claim. The adjudication application was properly made and the second respondent had jurisdiction to make the adjudication decision. The originating application is dismissed. I shall hear the parties as to costs and any other orders.

Ratio Decidendi

Legal Principle Established

The first respondent submits the decision of Hardev is not distinguishable. The decision of Ooralea is distinguishable. That decision pertained to a provision which was subsequently amended. Further, Ooralea predated the introduction of the exception in clause 11 of Schedule 1 of the Regulations.Consideration Section 42(1) of the QBCC Act prohibits a person from undertaking to carry out and from carrying out “building work” unless that person holds a contractor’s licence of the appropriate class under the Act at the time when the building work is carried out. Schedule 2 of the QBCC Act defines “carry out” for building work to include directly or indirectly causing the work to be carried out or providing the building work services for the work, as well as carrying out the work personally. That same schedule defines “undertake to carry out” to mean entering into a contract, submitting a tender or making an offer to carry out that work. “Building work” is defined in the QBCC Act to include the erection or construction of a building. Schedule 2 of the Act defines “building” as including any fixed structure. The schedule provides examples of a fixed structure, including “a water tank connected to the stormwater system for a building”. The definition of building works under the QBCC Act includes “the provision of … sewerage or drainage in connection with a building; and any site work (including construction of retaining structures) related to work of that kind”. The requirement for a licence in respect of building work is, however, subject to exceptions. Schedule 1 of the Regulations sets out work that is not building work. Relevantly, clause 11 of Schedule 1 provides:-“11Work for water reticulation systems, sewerage systems or stormwater drains(1)Construction, extension, repair or replacement of a water reticulation system, sewerage system or stormwater drain, other than works connecting a particular building to a main of the system or drain.(2)In this section – building includes a proposed building.” The work the first respondent undertook pursuant to the contract, the performance of which was the subject of the disputed payment claim and the adjudication decision, involved, relevantly, the installation and connection of waste tanks to the pressure sewer mains in proposed streets within the proposed subdivision. Those works included the installation of the pressure sewer mains and the installation of a boundary kit, valve box and lateral to connect the proposed lot to the pressure main in the proposed street. Whilst an appropriate inference in respect of a development project involving the creation of lots in a subdivision is that those lots will ultimately contain buildings, the works undertaken by the first respondent pursuant to the contract fell within the exception contained in clause 11 of Schedule 1 of the Regulations. The work undertaken by the first respondent in respect of the sewerage system involved the construction of the sewerage system, but did not involve works connecting a particular building or proposed building to a main of that system.