Want & Anor v Blackbear (NT) Pty Ltd [2014] NTCA 3
PARTIES: WANT, Gary John
AND:
WANT, Geraldine Elizabeth
v
BLACKBEAR (NT) PTY LTD
A.C.N. 116 222 005
TITLE OF COURT: COURT OF APPEAL OF THE NORTHERN TERRITORY
JURISDICTION: CIVIL APPEAL FROM THE SUPREME COURT EXERCISING TERRITORY JURISDICTION
FILE NO:AP 9 of 2013 (21207410)
DELIVERED: 27 March 2014
HEARING DATES: 4 February 2014
JUDGMENT OF: RILEY CJ, SOUTHWOOD
and BARR JJ
APPEALED FROM: KELLY J
CATCHWORDS:
CONTRACTS – building contract – contract termination – termination notice – intention to determine the contract – unequivocal statement of intention required – unequivocal if a commercial person clearly understands that notice is given – surrounding circumstances relevant – intention to determine contract at later stage insufficient.
CONTRACTS – building contract – contract termination – valid ground for termination – breach of contract – failure to proceed with due diligence – breach capable of remedy – not required to produce the same condition of affairs as if the breach had never occurred – substantial seizure of suspension or proceeding with the contract with reasonable diligence and competence adequate.
Batson v Carvalho (1948) 48 SR (NSW) 417; Brenmar Building Company Pty Ltd v University of Newcastle (1999) 15 BCL 467; Diploma Construction Pty Ltd v Marula Pty Ltd [2009] WASCA 229; Fountain Select Meats (Sales) Pty Ltd v International Produce Merchants Pty Ltd (1988) 81 ALR 397; FPM Constructions [2005] NSWCA 340; Hooper Constructions Pty Ltd v Chris’s Engineering Contracting Co [1970] ALR 821; Re Stewardson Stubbs & Collett Pty Ltd and Bankstown Municipal Council [1965] NSWR 1671; Shepherd v Felt and Textiles of Australia Ltd [1931] 45 CLR 359, referred to.
Spadaccini v Grice [2012] NTSC 41, distinguished.
REPRESENTATION:
Counsel:
Appellant:Self Represented
Respondent: L McCrimmon
Solicitors:
Appellant:Self Represented
Respondent: P Maher
Judgment category classification: B
Judgment ID Number: Ril1405
Number of pages: 31
IN THE COURT OF APPEAL
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWINWant & Anor v Blackbear (NT) Pty Ltd [2014] NTCA 3
No AP 9 of 2013 (21207410)
BETWEEN:
GARY JOHN WANT
First Appellant
GERALDINE ELIZABETH WANT
Second Appellant
AND:
BLACKBEAR (NT) PTY LTD
A.C.N. 116 222 005
Respondent
CORAM: RILEY CJ, SOUTHWOOD and BARR JJ
REASONS FOR JUDGMENT
(Delivered 27 March 2014)
RILEY CJ and BARR J:
Introduction
In 2009 the appellants entered into a building contract with the respondent to construct a house on land the appellants were purchasing in Humpty Doo. The appellants were dissatisfied with the progress of the works and on 8 July 2010 gave notice to the respondent that the “contract is terminated effective immediately”. Thereafter, the appellants denied the respondent access to the site and the respondent was unable to complete the works. The respondent disputed the right of the appellants to terminate the contract and, by letter dated 3 August 2010, the respondent purported to accept the repudiation of the contract and terminated the contract. The respondent then brought proceedings in the Supreme Court and eventually…
Keep reading for free
Create a free CaseChat account to read Want v Blackbear (NT) Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2014] NTCA 3
- Decision Date
CaseChat Overview and Summary
The court examined whether the defendant's notice of termination was unequivocal and clearly communicated the intention to terminate the contract. The court held that for a termination notice to be effective, it must be an unequivocal statement of intention that is understood by a commercial person. The court also considered the surrounding circumstances in determining whether the defendant's intention to terminate the contract was unequivocal. The court found that the defendant's intention to terminate the contract at a later stage was not sufficient to constitute a valid termination notice.
Additionally, the court considered whether the plaintiff's breach of contract provided a valid ground for termination. The court held that a breach of contract that is capable of remedy provides a valid ground for termination, even if it is not possible to produce the same condition of affairs as if the breach had never occurred. The court found that the plaintiff's failure to proceed with due diligence was a breach capable of remedy, and the defendant's substantial seizure or suspension of proceeding with the contract with reasonable diligence and competence was adequate. The court ultimately determined that the defendant's termination of the contract was valid.
The court ordered that the defendant's termination of the contract was valid and that the defendant was entitled to recover any damages suffered as a result of the plaintiff's breach of contract. The court also ordered that the plaintiff pay the defendant's costs of the proceedings.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
Established by: RILEY CJ