Blackbear (NT) Pty Ltd v Want & Anor [2013] NTSC 55
PARTIES:Blackbear (NT) Pty Ltd
ACN 116 222 005
v
Want, Gary John
and
Want, Geraldine Elizabeth
TITLE OF COURT: SUPREME COURT OF THE NORTHERN TERRITORY
JURISDICTION: SUPREME COURT OF THE TERRITORY EXERCISING TERRITORY JURISDICTION
FILE NO:18 of 2012 (21207410)
DELIVERED: 27 AUGUST 2013
HEARING DATES: 29 APRIL 2013
JUDGMENT OF: KELLY J
CATCHWORDS:
CONTRACTS—Construction contract—Due diligence—Whether failure to proceed with “due diligence” a defect capable of remedy—Whether gives rise to right to terminate—Held that lack of due diligence capable of remedy—No right to terminate contract
CONTRACTS—Construction contract—Notice of default—Notice required under contract—Whether form of notice was adequate—Held that correspondence was not sufficient to put builder on notice that contract would be terminated—No right to terminate contract
BUILDING AND CONSTRUCTION—Due diligence—Requirement to perform work with due diligence—Whether failure to proceed with due diligence a defect capable of remedy—Held that failure is a breach capable of being remediedRe Stewardson Stubbs & Collett v Bankstown Municipal Council [1965] NSWR 1671; Batson v De Carvalho (1948) 48 SR (NSW) 417, applied
Hooker Constructions Pty Ltd v Chris’s Engineering Contracting Co [1970] ALR 821, followed
REPRESENTATION:
Counsel:
Plaintiff:T Liveris
Defendant:K Sibley
Solicitors:
Plaintiff:Paul Maher
Defendant:De Silva Hebron
Judgment category classification: B
Judgment ID Number: KEL13011
Number of pages: 22
IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWINBlackbear (NT) Pty Ltd v Want & Anor [2013] NTSC 55
No. 18 of 2012 (21207410)
BETWEEN:
BLACKBEAR (NT) PTY LTD
ACN 116 222 005
Plaintiff
AND:
GARY JOHN WANT
First Defendant
AND:
GERALDINE ELIZABETH WANT
Second Defendant
CORAM: KELLY J
REASONS FOR JUDGMENT
(Delivered 27 August 2013)
The plaintiff Blackbear (NT) Pty Ltd is a building company owned by Michael Beare which trades under the name “Beare Homes”.
In April 2009 the defendants, Mr and Mrs Want, entered into negotiations with Beare Homes for the construction of a new home. Beare Homes was advertising “house and land packages” and Mr and Mrs Want had visited their display home. They signed a contract with a third party to purchase a block of land at Humpty Doo and negotiated a price with Beare Homes for the construction of a three bedroom house on that land.
Eventually Mr and Mrs Want entered into a contract with Beare Homes to construct a house on that land. The contract was dated 3 June 2009, but Mr Want deposed that it was not signed until 19 August 2009, the date that they completed the purchase of the block of land. Nothing turns on the date of the contract.
The contract price was $399,620.00 inclusive of GST to be paid in accordance with a progress payment schedule annexed to the contract. The appendix to the contract specified the date of commencement of the works to be “approx 2 weeks after building permit issued” and the due date for practical completion[1] was specified as “approx 24 weeks after main slab complete”.
Work was slow in starting. Plans and drawings…
Keep reading for free
Create a free CaseChat account to read Blackbear (NT) Pty Ltd v Want and Anor and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2013] NTSC 55
- Decision Date
CaseChat Overview and Summary
The central legal issues before the court were whether the builder's lack of due diligence constituted a defect capable of remedy and, if so, whether it provided a right to terminate the contract. Additionally, the court had to determine if the notice provided to the builder was adequate under the terms of the contract. The court was tasked with interpreting the contract and assessing the sufficiency of the notice given in relation to the termination clause.
In its decision, the court held that while the builder's failure to proceed with due diligence constituted a breach, it was a defect capable of being remedied. The court found that such a breach did not provide a right to terminate the contract. Furthermore, the court examined the form of the notice given to the builder and concluded that it was insufficient to put the builder on notice that the contract would be terminated. Consequently, the plaintiff's claims were dismissed, and no right to terminate the contract was established.
No specific orders were made beyond the dismissal of the plaintiff's claims, leaving the construction contract in place.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi