SUPREME COURT OF QUEENSLAND
CITATION:
Walton Construction (Qld) P/L & Anor v Venture Management Resources International P/L & Anor [2010] QSC 31
PARTIES:
WALTON CONSTRUCTION (QLD) PTY LTD ACN 100 833 225
(first applicant)
and
WALTON CONSTRUCTION PTY LTD ACN 060 900 218
(second applicant)
v
VENTURE MANAGEMENT RESOURCES INTERNATIONAL PTY LTD ACN 090 569 869
(first respondent)
and
P & W ENTERPRISES PTY LTD ACN 108 802 491
(second respondent)
FILE NO/S:
14117/09
DIVISION:
Trial Division
PROCEEDING:
Application for interlocutory injunction
DELIVERED ON:
10 February 2010
DELIVERED AT:
Brisbane
HEARING DATE:
24 December 2009
JUDGE:
Douglas J
ORDER:
Application for interlocutory injunction to be granted pending the hearing of the originating application and subject to further submissions as to the form of the order including the provision of an undertaking as to damages and directions in respect of the further conduct of the application.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACTS – CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – SECURITY AND RETENTION OF FUNDS – where an application was made to restrain the second respondent from accessing funds secured by a bank guarantee pursuant to a building contract between the first applicant and the second respondent – where the first respondent issued a payment certificate pursuant to cl 47.1 of the building contract stating an amount of payment due to be paid by the first applicant to the second respondent – whether the amount could be properly described as “otherwise due”
EQUITY – EQUITABLE REMEDIES – INJUNCTIONS – INTERLOCUTORY INJUNCTIONS – BALANCE OF CONVENIENCE – whether the calling in of bank guarantees would cause the applicants irreparable harm – whether there is a serious question to be tried
Queensland Building Services Authority Act 1992 (Qld), s 42
Austrak Pty Ltd v John Holland Pty Ltd [2006] QSC 103, applied
Daysea Pty Ltd v Watpac Australia Pty Ltd (2001) 17 BCL 434; [2001] QCA 49, cited
J. M. Kelly (Project Builders) v Toga Development No. 31 Pty Ltd [2006] QSC 365, cited
Merritt Cairns Construction Pty Ltd v Wulguru Heights Pty Ltd [1995] 2 Qd R 521; [1995] QCA 273, cited
Multiplex Limited v Qantas Airways Limited (2007) 23 BCL 130; [2006] QCA 337, cited
Prell v Burrell [1975] Tas SR 150, referred
Puerto Galera Pty Ltd v J.M. Kelly (Project Builders) Pty Ltd [2008] QSC 356, cited
Sutton v Zullo Enterprises Pty Ltd [2000] 2 Qd R 196; [1998] QCA 417, cited
Vos Construction & Joinery Qld Pty Ltd v Sanctuary Properties Pty Ltd [2007] QSC 332, consideredCOUNSEL:
P L O’Shea SC, with B E Codd, for the first and second applicants
P Dunning SC, with D Quayle, for the first and second respondentsSOLICITORS:
Dibbs Barker for the first and second applicants
Clayton Utz for the first and second respondents
[1] Douglas J: The applicants have applied for an interlocutory injunction to restrain the second respondent, P & W Enterprises Pty Ltd, from accessing…
Keep reading for free
Create a free CaseChat account to read Walton Construction (Qld) P/L v Venture Management Resources... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] QSC 31
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the calling in of the bank guarantees would cause the applicants irreparable harm, and if there was a serious question to be tried on the merits of the case. The court considered the balance of convenience and whether an interlocutory injunction was appropriate in these circumstances. Given the potential for significant financial loss and the lack of a clear and convincing argument against the grant of the injunction, the court found that the applicants had demonstrated a serious question to be tried and that the balance of convenience favoured the grant of the injunction.
The court granted the application for an interlocutory injunction, pending the hearing of the originating application. The injunction was to be subject to further submissions regarding the form of the order, including the provision of an undertaking as to damages, and directions in respect of the further conduct of the application. The court recognised the importance of protecting the applicants from potential irreparable harm while the substantive issues were being determined. The decision underscores the need for careful consideration of the balance of convenience and the potential for serious prejudice when deciding on interlocutory injunctions in construction disputes.
Orders
Orders of the court
Application for interlocutory injunction to be granted pending the hearing of the originating application and subject to further submissions as to the form of the order including the provision of an undertaking as to damages and directions in respect of the further conduct of the application.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi