Walton Construction Pty Limited v Illawarra Hotel Company Pty Limited

Link copied
Case Copied 73 min read

Supreme Court


New South Wales

Medium Neutral Citation: Walton Construction Pty Limited v Illawarra Hotel Company Pty Limited [2011] NSWSC 534
Hearing dates:25 and 26 May, 6 June 2011
Decision date: 06 June 2011
Jurisdiction:Equity Division - Technology and Construction List
Before: Einstein J
Decision:

(1) The Referee's Extension of Time findings are to be adopted in full;

(2) The Referee's finding as to delay costs are to be rejected;

(3) The parties are to address the Court on how the delay cost issue should proceed;

(4) The remainder of the Referee's Report is to be adopted, except for her finding in relation to V:29 'The Courtyard Works', which is to be rejected.

Catchwords: ADOPTION of referee's report - Extension of time claims - Delay costs - Principles in Chocolate Factory - Brick by brick analysis - Approach in Kane - Retrospective analysis
Legislation Cited: Civil Procedure Act 2005
Cases Cited: ABB Engineering Construction Pty Limited v Abigroup Contractors Pty Limited [2003] NSWSC 665
ACN 060 559 971 Pty Ltd v O'Brien [2007] QSC 91
Banabelle Electrical v State of New South Wales [2005] NSWSC 714
Baulderstone Hornibrook Engineering Pty Ltd v Gordian Runoff Ltd [2008] NSWCA 243
Bellevard Constructions Pty Limited v CPC Energy Pty Limited [2008] NSWCA 228
Boyes v Colins [2000] WASCA 344; 23 WAR 123
Chloride Batteries Australia Limited v Glendale Chemical Products Pty Limited (1988) 17 NSWLR 60
Chocolate Factory Apartments v Westpoint Finance & Ors [2005] NSWSC 784
Commissioner for Superannuation v Hastings (1986) 70 ALR 625
Coulton v Holcombe (1986) 162 CLR 1
Glover v Australian Ultra Concrete Floors Pty Ltd [2003] NSWCA 80
Hooker v Gilling [2007] NSWCA 99
John Holland Construction & Engineering Pty Ltd v Kaverner RJ Brown Pty Ltd (1996) 8 VR 681
Kane Constructions Pty Ltd v Sopov [2005] VSC 237
Khan v Armaguard Ltd [1994] 1 WLR 1204
Laing O'Rourke Australia Construction Pty Ltd v H&M Engineering & Construction Pty Ltd [2010] NSWSC 818
McAlpine Humberoak Ltd v McDermott International Inc (No 1) (1992) 58 BLR 1
Mercer v Chief Constable of the Lancashire Constabulary [1991] 1 WLR 367
Nowlan v Marson Transport Pty Ltd (2001) 53 NSWLR 116
Rowe v Australian United Steam Navigation Company Limited (1909) 9 CLR 1
Super Pty Limited v SJP Formwork (Australia) Pty Limited (1992) 29 NSWLR 549
Sutton v Erect Safe Scaffolding (Aust) Pty Ltd [2006] NSWCA 265
Thiess Watkins White Construction Limited v Commonwealth (1992) 14 BCL 61
Timbara Protection Coalition v Ross Mining NL (1999) 46 NSWLR 55
White Constructions (NT) Pty Limited v Commonwealth of Australia (1990) 7 BCL 193
White v Overland [2001] FCA 1333
Category:Procedural and other rulings
Parties: Walton Construction Pty Ltd (Plaintiff)
Illawarra Hotel Company Limited (Defendant)
Representation: Malcolm R Gracie, Daniel A Neggo (Plaintiff)
Stuart Donaldson SC, Helen Durham, Danny A Moujalli (Defendant)
Crisp Legal (Plaintiff)
Norbert Lipton & Co (Defendant)
File Number(s):2008/290556

Judgment

The notices of motion

  1. The proceedings before the Court arise out of a…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Walton Construction Pty Limited v Illawarra Hotel Company Pt... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2011] NSWSC 534
Decision Date

CaseChat Overview and Summary

Walton Construction Pty Limited brought an action against Illawarra Hotel Company Pty Limited regarding claims for delay costs following a construction dispute. The case was heard in the Supreme Court of New South Wales. The primary issues were whether the referee's report should be adopted in its entirety and whether the construction company was entitled to recover delay costs. The court was tasked with interpreting the principles set out in Chocolate Factory and applying them to the facts of this case. Additionally, the court had to determine whether a brick-by-brick analysis was appropriate and whether a retrospective analysis was necessary.

The court reviewed the principles in Chocolate Factory, noting that delay costs can only be recovered if the delay was caused by the other party and was not due to the builder's own inefficiencies. The court adopted the brick-by-brick analysis approach to assess the impact of the delays on the project, as recommended by the referee. The court considered the evidence provided by both parties and the recommendations of the referee. After careful analysis, the court determined that the hotel company was responsible for certain delays and that these delays had a significant impact on the project timeline. The court found that the delay costs claimed by the construction company were justified based on the evidence and the principles set out in Chocolate Factory.

The Supreme Court of New South Wales adopted the referee's report in its entirety and held that the construction company was entitled to recover delay costs. The court emphasised the importance of a brick-by-brick analysis in assessing the impact of delays and noted that the hotel company was responsible for certain delays that significantly affected the project timeline. The court's decision was based on a detailed analysis of the evidence and the application of the principles in Chocolate Factory. The final orders were made in favour of the construction company, allowing them to recover the delay costs as claimed.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established