DISTRICT COURT OF QUEENSLAND
CITATION:
PARTIES:
LEONARD and VERA WALKER
Appellants
v
PETER KORDONSKY
Respondent
FILE NO/S:
Appeal No D3552/2002
DIVISION:
PROCEEDING:
Appeal
ORIGINATING COURT:
Queensland Building Tribunal
DELIVERED ON:
17 March 2004
DELIVERED AT:
Brisbane
HEARING DATE:
7 November 2003
JUDGE:
McGill DCJ
ORDER:
Appeal dismissed.
CATCHWORDS:
BUILDING AND ENGINEERING CONTRACTS – Construction – contract to complete partly built home – no warranty of work done by other builder.
APPEAL AND NEW TRIAL – Appeal from Queensland Building Tribunal – whether additional evidence to be admitted – factual issues not raised before Tribunal – whether findings open on evidence.
COUNSEL:
Both parties appeared in person.
SOLICITORS:
Neither party was represented at the time of hearing.
This is an appeal from a decision of the Queensland Building Tribunal which on 26 July 2002 ordered the appellants[1] to pay the respondent[2] $10,886.75, being part of the amount the respondent had claimed as applicant in the proceeding in the tribunal, together with the reimbursement of his filing fee of $200. On 9 August 2002 the appellants applied to have the decision reconsidered under the Queensland Building Tribunal Act 2000 (“the Act”). On 19 August 2002 the chair of the tribunal refused their request, on the ground that the circumstances permitting a reopening under s 88 of the Act did not apply. The notice of appeal to this court was filed on 23 August 2002. The appeal is by way of rehearing in the usual sense: Pointon v Redcliffe Demolitions Pty Ltd (2002) 23 Qld Lawyer R 103.
[1]I shall refer to Mr and Mrs Walker as the appellants; they were the respondents in the proceeding in the tribunal.
[2]I shall refer to Mr Kordonsky as the respondent; he was the applicant in the proceeding in the tribunal.
The proceeding arose out of the construction of a house for the appellants. They had originally entered into a contract with a builder, Davlyn Homes Pty Ltd, to construct the house, but at about the completion of the frame stage a dispute between the parties resulted in each party purporting to terminate. Proceedings were commenced in the tribunal, which ultimately decided that the company was entitled to recover some payment from the appellants. The appellants counter-claimed for defective workmanship, in respect of which the sum of $500 was allowed by the tribunal. The appellants appealed to the District Court from that decision, which appeal was dismissed: [2003] QDC 292. The appellants applied for leave to appeal from that decision to the Court of Appeal. After the present appeal was argued before me, the Court of Appeal refused that application: [2003] QCA 565. The judgment of the Court of Appeal contained a number of important statements of principle as to the correct approach to appeals from the tribunal to this court under the Act. I am of course bound to apply the approach laid down by the Court of Appeal.
After the relationship between the appellants and that…
Continue reading Walker v Kordonsky
Sign in free to access the full text
- AGLC
- Walker v Kordonsky [2004] QDC 32
- Case
- [2004] QDC 32
- Decision Date
CaseChat Overview and Summary
The central legal issues addressed by the court involved the interpretation of the contract between the parties, the admissibility of new evidence not presented at the Tribunal, and whether the findings of the Tribunal were supported by the evidence. The appellant argued that the Tribunal should have allowed additional evidence which would have demonstrated that the respondent was aware of the deficiencies in the work of the previous builder. Additionally, the appellant contended that certain factual issues were not properly raised before the Tribunal, and thus, the Tribunal's findings were not open to them based on the evidence presented.
The court found that the contract clearly excluded any warranty concerning the work done by the previous builder. It was determined that the appellant had not demonstrated that the additional evidence was necessary or that it would have altered the outcome of the Tribunal's decision. The court held that the findings of the Tribunal were well-supported by the evidence and that the appellant had not shown that the Tribunal's conclusions were not open on the evidence. Consequently, the appeal was dismissed, and the decision of the Queensland Building Tribunal was upheld.
Orders
Orders of the court
Appeal dismissed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.