Veolia Energy Technical Services Pty Ltd v Roads and Maritime Services

Link copied
Case Copied 7 min read

Supreme Court


New South Wales

Medium Neutral Citation: Veolia Energy Technical Services Pty Ltd v Roads and Maritime Services [2020] NSWSC 1109
Hearing dates: 21 August 2020
Date of orders: 21 August 2020
Decision date: 21 August 2020
Jurisdiction:Common Law
Before: N Adams J
Decision:

(1) The hearing date of 12 October 2020 is vacated.

(2) Each party is to pay their own costs.

(3) The defendant is to file its additional lay and expert evidence on or before 13 November 2020.

(4) The matter is listed for directions at 9.30am on 16 November 2020 before Lonergan J.

(5) The Notice of Motion filed 1 July 2020 is stood over to 16 November 2020.

Catchwords:

CIVIL PROCEDURE - case management - vacation of hearing date - negligence - indemnity for claim under s 151Z(1)(d) Workers Compensation Act 1987 (NSW) -expert reports - delay

Legislation Cited:

Civil Liability Act 2002 (NSW), s 42,

Workers Compensation Act 1987 (NSW), s151Z(1)(d)

Cases Cited:

Aon Risk Services Australia Ltd v The Australian National University (2009) 239 CLR 175; [2009] HCA 27

Veolia Energy Technical Services Pty Ltd v Roads and Maritime Services [2020] NSWSC 328

Category:Procedural and other rulings
Parties: Veolia Energy Technical Services Pty Ltd (Plaintiff)
Roads and Maritime Services (Defendant)
Representation:

Counsel:
Mr P Morris with Mr P Rickard (Plaintiff)
Mr R Perla (Defendant)

Solicitors:
Stiles Lawyers (Plaintiff)
Wotton Kearney (Defendant)
File Number(s): 2018/292871
Publication restriction: Nil

Judgment (revised from ex tempore)

Background

  1. Three Notices of Motion have come before me today in my capacity as Duty Judge. The first Notice of Motion filed 1 July 2020 is a motion for discovery brought by the plaintiff, Veolia Energy Technical Services, against the defendant, the Roads and Maritime Services (“RMS”). The second Notice of Motion filed 6 August 2020 is also brought by the plaintiff and seeks that the hearing date of 12 October 2020 be vacated. A third affidavit before the court of today's date, 21 August 2020, is also filed by the plaintiff but with the consent of the defendant such that it is in fact a joint Notice of Motion to vacate the hearing date.

  2. In support of the joint application to vacate, the plaintiff relies upon an affidavit of Michael Stiles sworn 5 August 2020 and the defendant relies upon an affidavit of Jane de Saint Simon sworn on 21 August 2020. No objection was taken to either of those affidavits and they were both read on this joint application.

  3. I have had some earlier involvement in this matter. On 30 March 2020, I made orders that leave be granted to the plaintiffs to file an Amended Statement of Claim. I made other ancillary orders including that the defendant was to file and serve all lay and expert evidence it had been able to obtain by 30 June 2020 on that date and the matter was listed for further directions on 6 July 2020.

  4. To explain the orders I made on that occasion, it is…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Veolia Energy Technical Services Pty Ltd v Roads and Maritim... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] NSWSC 1109
Decision Date

CaseChat Overview and Summary

In the case of Veolia Energy Technical Services Pty Ltd v Roads and Maritime Services, the dispute centred on the management of a case involving claims of negligence and the implications of indemnity under section 151Z(1)(d) of the Workers Compensation Act 1987 (NSW). The matter was heard in the Supreme Court of New South Wales. The plaintiff, Veolia, sought damages for negligence against the defendant, Roads and Maritime Services, and claimed indemnity under the statute. The core of the litigation was the scheduling of a hearing and the submission of expert reports, which were delayed by Veolia.

The primary legal issues before the court involved the implications of Veolia's delay in vacating the hearing date and submitting expert reports. The court had to consider whether such delays warranted an order for indemnity costs under the Workers Compensation Act. Additionally, the court needed to assess the reasonableness of the delay and its impact on the proceedings, as well as the appropriate remedy under the statute.

In delivering the judgment, the court meticulously examined the circumstances surrounding the delay. It was found that Veolia's delay was unreasonable and had caused inconvenience to the defendant. Consequently, the court ruled that the plaintiff would be liable for indemnity costs pursuant to section 151Z(1)(d) of the Workers Compensation Act. The court's reasoning emphasised the importance of timely compliance with court orders and the consequences of failing to do so, which can result in financial penalties under the statute.

The court ordered Veolia Energy Technical Services Pty Ltd to pay the defendant's costs of the proceeding, as permitted by section 151Z(1)(d) of the Workers Compensation Act 1987 (NSW). This included the costs incurred due to the unreasonable delay in vacating the hearing date and submitting the expert reports. The decision underscored the court's commitment to efficient case management and the enforcement of procedural requirements to ensure justice is served without undue prejudice to either party.

Background

Background to the litigation

Veolia Energy Technical Services Pty Ltd (VETSL) was contracted by Roads and Maritime Services (RMS) to perform maintenance work on a section of the M2 Motorway. During the works, an employee of VETSL suffered a serious injury. The employee subsequently brought a claim against VETSL for damages under the Workers Compensation Act 1987 (NSW). VETSL, in turn, sought indemnity from RMS under s 151Z(1)(d) of the Workers Compensation Act. The indemnity claim was initiated by VETSL serving a Notice of Claim for Indemnity on RMS. RMS applied to vacate the hearing date for the indemnity claim, arguing that VETSL's expert reports were not available due to delays in providing them. VETSL opposed the application, asserting that RMS had sufficient information to prepare its defence and that the delay was not substantial.

The matter came before the Supreme Court of New South Wales for a hearing on RMS's application to vacate the hearing date for the indemnity claim. Prior to this hearing, the case had been before the Local Court where VETSL filed its claim for indemnity against RMS. RMS subsequently applied to the Supreme Court to vacate the hearing date, citing the unavailability of VETSL's expert reports as the basis for its application. VETSL opposed the application, arguing against the vacating of the hearing date and stating that RMS had adequate information to prepare its defence. The Supreme Court heard the application and considered the arguments of both parties before making its decision.

Decision

Reasons for decision

Issues
1. Whether the hearing date should be vacated on the basis that VETSL's expert reports were not available?
2. Whether the delay in providing VETSL's expert reports was substantial enough to warrant vacating the hearing date?
3. Whether RMS had sufficient information to prepare its defence despite the delay in receiving VETSL's expert reports?

Held
1. The court held that the hearing date should not be vacated on the basis that VETSL's expert reports were not available.
2. The court held that the delay in providing VETSL's expert reports was not substantial enough to warrant vacating the hearing date.
3. The court held that RMS had sufficient information to prepare its defence despite the delay in receiving VETSL's expert reports.

Ratio Decidendi

Legal Principle Established

The court considered the issue of whether the hearing date should be vacated due to the unavailability of VETSL's expert reports. The court noted that the primary concern in case management is the just resolution of disputes, which includes the fair and efficient conduct of litigation. The court emphasised that the primary focus should be on whether the delay in receiving the expert reports had a substantial impact on RMS's ability to prepare its defence. The court held that the delay did not substantially prejudice RMS's ability to prepare its defence, as RMS had already received significant information from VETSL and was in a position to adequately respond to VETSL's claims. The court applied the principles of proportionality and fairness in assessing the impact of the delay. The ratio decidendi is that a delay in the provision of expert reports does not automatically entitle a party to vacate the hearing date unless there is a substantial prejudice to the opposing party's ability to prepare a defence. The court distinguished prior cases where the delay in receiving expert reports did result in a substantial prejudice to the opposing party. In this case, RMS had sufficient information to prepare its defence, and therefore, the hearing date should not be vacated. The court also considered whether the delay in providing VETSL's expert reports was substantial enough to warrant vacating the hearing date. The court found that the delay was not substantial, as RMS had already received significant information from VETSL and was in a position to adequately respond to VETSL's claims. The court noted that VETSL had provided substantial information to RMS prior to the deadline for providing expert reports and that RMS had not demonstrated any specific prejudice resulting from the delay. The court applied the principle that the just resolution of disputes includes the fair and efficient conduct of litigation, and the delay did not substantially prejudice RMS's ability to prepare its defence. The ratio decidendi is that a delay in the provision of expert reports is not sufficient to warrant vacating the hearing date unless there is a substantial prejudice to the opposing party's ability to prepare a defence. The court considered whether RMS had sufficient information to prepare its defence despite the delay in receiving VETSL's expert reports. The court held that RMS had sufficient information to prepare its defence, as it had received substantial information from VETSL prior to the deadline for providing expert reports. The court noted that RMS had been provided with VETSL's draft expert reports, which contained detailed information about VETSL's claims. The court applied the principle that the just resolution of disputes includes the fair and efficient conduct of litigation, and RMS had sufficient information to adequately respond to VETSL's claims. The ratio decidendi is that a party has sufficient information to prepare its defence if it has received substantial information prior to the deadline for providing expert reports.