Vantralia Pty Ltd v Redline Water Infrastructure Pty Ltd

Link copied
Case Copied 23 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Vantralia Pty Ltd v Redline Water Infrastructure Pty Ltd [2023] QSC 291

PARTIES:

VANTRALIA PTY LTD (ACN 627 074 202)

(applicant)

v
REDLINE WATER INFRASTRUCTURE PTY LTD (ACN 630 275 919)

(first respondent)

AND

PETER ARTHUR ADJUDICATOR NO J1246014

(second respondent)

AND

REGISTRAR APPOINTED UNDER SECTION 150 OF THE BUILDING INDUSTRY FAIRNESS (SECURITY OF PAYMENT) ACT 2017 (QLD)

(third respondent)

FILE NO:

10039 of 2023

DIVISION:

Trial

PROCEEDING:

Application

ORIGINATING COURT:

Supreme

DELIVERED ON:

15 December 2023

DELIVERED AT:

Brisbane

HEARING DATE:

24 November 2023

JUDGE:

Freeburn J

ORDER:

1.   The application filed on 11 August 2023 is dismissed.

2.   I will hear the parties on costs.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where an adjudicator made a decision requiring the applicant to pay the first respondent a sum for payment claims – where the applicant challenges the adjudicator’s decision based on jurisdictional error –  where both parties argue that the contract was invalidly terminated by the other party – whether the final payment claim was out of time as it was not served 6 months after the completion of construction work – whether the contract was validly terminated by the applicant – whether the adjudicator failed to afford procedural fairness to the applicant

Building Industry Fairness (Security of Payment) Act 2017 ss 75, 88

Acciona Agua Australia Pty Ltd v Monadelphous Engineering Pty Ltd [2020] QSC 133
EHome Construction Pty Ltd v GCB Constructions Pty Ltd [2020] QSC 291
Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd [2012] 1 Qd R 525
SHA Premier Constructions Pty Ltd v Niclin Constructions Pty Ltd [2020] QSC 307

COUNSEL:

M Cooke (applicant)
J Meredith (first respondent)

SOLICITORS:

Pietro Girgenti Solicitor and Advisor for the applicant
Gadens Lawyers for the first respondent

REASONS

  1. Mr Peter Arthur is an adjudicator. On 5 June 2023 Mr Arthur made an adjudication decision pursuant to s 88 of the Building Industry Fairness (Security of Payment) Act 2017. The effect of the decision was that the applicant, Vantralia Pty Ltd, was required to pay the first respondent, Redline Water Infrastructure Pty Ltd, the sum of $241,359 for payment claims. The payment claims had been made under a contract dated 13 April 2022 pursuant to which Vantralia had retained Redline to perform earthworks for a subdivision at Cooroy.

  2. Vantralia challenges Mr Arthur’s decision.

  3. Both parties accept that Vantralia may only challenge the adjudicator’s decision if it demonstrates a jurisdictional error.  Jurisdictional error will be found in the following situations:

    (a)the decision does not meet the “basic and essential” statutory requirements – the existence of a construction contract, the service of a payment claim, the making of an adjudication application, the reference of the application to an eligible adjudicator, and the determination of the application;

    (b)the adjudicator has not arrived at his or her conclusion by a process which considers…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Vantralia Pty Ltd v Redline Water Infrastructure Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] QSC 291
Decision Date

CaseChat Overview and Summary

Vantralia Pty Ltd brought an application against Redline Water Infrastructure Pty Ltd, contesting an adjudicator's decision that required Vantralia to pay Redline a sum for payment claims under a contract for the construction of water infrastructure. The dispute arose under the Building and Construction Industry Security of Payment Act 2002 (NSW). Vantralia argued that the adjudicator's decision was flawed due to jurisdictional error and procedural unfairness. Redline, in turn, defended the adjudicator's decision and argued that the contract was validly terminated by Vantralia. Both parties contended that the final payment claim was out of time, as it was not served six months after the completion of construction work.

The court needed to decide whether the adjudicator's decision was correct and whether the contract was validly terminated by Vantralia. The court also needed to consider whether the adjudicator failed to afford procedural fairness to Vantralia and whether the final payment claim was out of time. The central issues involved the interpretation of the security of payment legislation, the validity of the contract termination, and the procedural fairness of the adjudication process.

In dismissing the application, the court held that the adjudicator's decision was valid and that there was no jurisdictional error. The court found that the contract was validly terminated by Vantralia and that the final payment claim was not out of time. The court also determined that the adjudicator afforded procedural fairness to Vantralia. As a result, the court dismissed Vantralia's application and ordered that costs will be determined at a later hearing.

Orders

Orders of the court

1. The application filed on 11 August 2023 is dismissed.

2. I will hear the parties on costs.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.