SUPREME COURT OF QUEENSLAND
CITATION: EHome Construction Pty Ltd v GCB Constructions Pty Ltd
[2020] QSC 291PARTIES: EHOME CONSTRUCTION PTY LTD
ABN 72 607 445 009
(applicant)
v
GCB CONSTRUCTIONS PTY LTD
ABN 26 151 244 254
(first respondent)
RANJIT KHOSLA J1077622
(second respondent)
THE ADJUDICATION REGISTRAR, QUEENSLAND
BUILDING AND CONSTRUCTION COMMISSION
(third respondent)FILE NO/S: BS 6386 of 2020 DIVISION: Trial Division PROCEEDING: Originating Application DELIVERED EX 18 September 2020 TEMPORE ON: DELIVERED AT: Brisbane HEARING DATE: 18 September 2020 JUDGE: Bond J ORDER:
1. The originating application is dismissed. 2. The question of the order which should be made as to costs will be determined on the papers and in this regard the parties are directed to file and serve submissions on that question within seven days of today, such submissions to be limited to three pages. 3. The sum of $668,342.58 together with any accretions thereto which has been paid into Court by the applicant must be paid out to the first respondent. 4. Order 3 is stayed until 4 pm on 25 September 2020. CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where a payment claim was made for work carried out up to termination of a construction contract – where the payment claim was made, and the adjudication determined, on the basis
that the claim was a final payment claim – whether the payment claim was made within time – where the payment claim included an amount for retention monies – whether the payment claim was a valid payment claim – whether the adjudication decision was affected by jurisdictional error
Building Industry Fairness (Security of Payment) Act 2017 (Qld), s 75
Acciona Agua Australia Pty Ltd v Monadelphous Engineering Pty
Ltd [2020] QSC 133, applied
COUNSEL: R A Perry QC, with I Erskine, for the applicant
J Baartz for the first respondent
No appearance for the second and third respondentsSOLICITORS: Anthony Delaney Lawyers for the applicant
Mills Oakley for the first respondent
No appearance for the second and third respondents
HIS HONOUR: This is an application for declarations that a payment claim served by the first respondent on the applicant is void because it did not comply with the requirements of the Building Industry Fairness (Security of Payment) Act 2017 (BIFA). The application further seeks a declaration that the adjudication in respect of that payment claim, namely, a decision by the second respondent dated 5 June 2020, is not a valid adjudication pursuant to BIFA and is void. The second respondent and the third respondent have not participated in the proceeding. Accordingly it is convenient to refer to the first respondent simply as the respondent and the second respondent as the adjudicator.
There is no significant dispute in relation to the factual background. The applicant provides domestic and commercial building and construction services in Queensland. The respondent is a builder and…
Keep reading for free
Create a free CaseChat account to read EHome Construction Pty Ltd v GCB Constructions Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] QSC 291
- Decision Date
CaseChat Overview and Summary
The court found that the payment claim was not made within the required timeframe as per section 75 of the Act. The inclusion of retention monies in the claim did not render it invalid, but the lateness of the claim meant it did not qualify for adjudication. The court held that the adjudicator had erred in considering the claim due to the late filing. Consequently, the decision of the adjudicator was quashed, and the claim was dismissed. The sum paid into court by EHome was ordered to be paid out to GCB, with orders on costs to be determined subsequently.
Orders
Orders of the court
1.
The originating application is dismissed.
2.
The question of the order which should be made as to costs will be determined on the papers and in this regard the parties are directed to file and serve submissions on that question within seven days of today, such submissions to be limited to three pages.
3.
The sum of $668,342.58 together with any accretions thereto which has been paid into Court by the applicant must be paid out to the first respondent.
4.
Order 3 is stayed until 4 pm on 25 September 2020.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.