ACT CIVIL & ADMINISTRATIVE TRIBUNAL
SPEDDING v THE OWNERS – UNITS PLAN 3941 (Unit Titles) [2022] ACAT 49
UT 3/2022
Catchwords: UNIT TITLES – statutory construction – meaning of “notice of reduced quorum decision under section 3.10(1)” in section 3.11(2) of schedule 3 of the Unit Titles (Management) Act 2011 – whether temporal requirement to give written notice of reduced quorum decision within seven days after the meeting is imported into section 3.11(2) – whether reduced quorum decisions at annual general meeting took effect despite written notice of the decisions being given to unit owners more than seven days after the meeting – whether a reduced quorum decision takes effect immediately subject to being disallowed by a petition signed by a majority of unit owners under section 3.11(3) – held that the reduced quorum decisions made at the annual general meeting did not take effect
Legislation cited: ACT Civil and Administrative Tribunal Act 2008, ss 53, 55
Legislation Act 2001, ss 146, 151
Unit Titles (Management) Act 2011 s 39, sch 3 ss 3.6, 3.9, 3.10, 3.11
Cases cited:Leonard v Michie [2019] ACAT 14
SZTAL v Minister for Immigration and Border Protection [2017] HCA 34
Woolmer v The Owners – Units Plan No 346 [2019] ACAT 95
List of
Texts/Papers cited: Explanatory Statement, Unit Titles (Management) Bill 2011, Sch 3
Tribunal:Senior Member M Orlov
Date of Orders: 10 June 2022
Date of Reasons for Decision: 10 June 2022
AUSTRALIAN CAPITAL TERRITORY )
CIVIL & ADMINISTRATIVE TRIBUNAL ) UT 3/2022
BETWEEN:
DAVID SPEDDING
Applicant
AND:
THE OWNERS – UNITS PLAN 3941
Respondent
TRIBUNAL:Senior Member M. Orlov
DATE:10 June 2022
ORDER
The Tribunal orders that:
The separate question in paragraph 1 of the orders made on 29 April 2022 is answered in the affirmative.
The Tribunal declares that in the events that happened and on the proper construction of sections 3.10(1) and 3.11 of schedule 3 of the Unit Titles (Management) Act 2011, the reduced quorum decisions made at the annual general meeting of the respondent on 16 December 2021 did not take effect because the respondent did not give written notice of the reduced quorum decision to unit owners within seven days after the meeting.
The amended unit titles application filed on 31 March 2022 is otherwise dismissed.
The parties have liberty to apply for any consequential orders within seven days of the date of these orders.
………………………………..
Senior Member M Orlov
REASONS FOR DECISION
Introduction and overview
The issue in this application is whether reduced quorum decisions made at the annual general meeting of the owners corporation held on 16 December 2021 took effect, where the owners corporation gave notice of the reduced quorum decisions to unit owners on 4 January 2022, which was more than seven days after the meeting.
There is no factual dispute. The issue turns on the proper construction of sections 3.10(1) and 3.11 of schedule 3 of the Unit Titles (Management) Act 2011 (UTM Act),…
Keep reading for free
Create a free CaseChat account to read Van Vliet v Landscape Enterprises Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] NSWPICPD 49
- Decision Date
CaseChat Overview and Summary
The court was required to interpret the provisions of the Act, specifically the interplay between sections 3.10(1) and 3.11(2) of Schedule 3, to determine if a temporal requirement for the written notice of reduced quorum decisions under section 3.10(1) should be applied to section 3.11(2). Additionally, it needed to decide whether the reduced quorum decisions at the AGM took effect despite the delayed written notice and if such decisions took immediate effect subject to being disallowed by a petition signed by a majority of unit owners under section 3.11(3).
The court held that the statutory language in section 3.11(2) did not explicitly import the temporal requirement of section 3.10(1). Consequently, the delayed written notice did not invalidate the decisions made at the AGM. The court found that the reduced quorum decisions did take effect immediately, but they were subject to being disallowed by a petition signed by a majority of unit owners under section 3.11(3). However, in this instance, the court ruled that the decisions made at the AGM did not take effect because the written notice was provided beyond the seven-day period required by section 3.10(1).
The court's final orders determined that the decisions made at the AGM were invalid due to the failure to provide the written notice within the stipulated timeframe. The court did not allow the reduced quorum decisions to stand, thereby affirming the plaintiff's contention regarding the invalidity of those decisions.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.