Upper Hunter Timbers Pty Ltd v Forestry Commission of NSW

Link copied
Case Copied 45 min read
CITATION: UPPER HUNTER TIMBERS PTY LTD v FORESTRY COMMISSION OF NSW [1999] NSWCA 125
FILE NUMBER(S): CA 40671/98
HEARING DATE(S): 22 April 1999
JUDGMENT DATE:
21 May 1999

PARTIES :


Upper Hunter Timbers Pty Limited - A
Forestry Commission of NSW - R
JUDGMENT OF: Priestley JA at 1; Sheller JA at 2; Stein JA at 59
LOWER COURT JURISDICTION: Supreme Court - Equity Division
LOWER COURT FILE NUMBER(S) : 3609/97
LOWER COURT JUDICIAL OFFICER: Bryson J
COUNSEL: D J Hammerschlag/M Green - A
J E Griffiths - R
SOLICITORS: Deacons Graham & James - A
Crown Solicitor of NSW - R
CATCHWORDS: CONTRACT - finality - merely agreement to agree; CONTRACT - assignment - novation; CONTRACT - Government body - whether contract fettered discretion; CONTRACT - frustration by commencement of Act - loss of bargain damages
ACTS CITED: Forestry Act 1916
Forestry Revocation & National Parks Reservation Act 1996
Enviromental Planning & Assessment Act 1979
Timber Industry (Interim Protection) Act 1992
Frustrated Contracts Act 1978
Limitations Act 1969
CASES CITED:
Ansett Transport Industries (Operations) Pty Ltd v The Commonwealth (1977) 139 CLR 54 at 77
Camberwell City Council v Camberwell Shopping Centre Ltd (1994) 1 VR 163 at 182
DECISION: 1. Appeal allowed in part; 2. Set aside so much of the order of Bryson J of 17 August 1998 as gave judgment for the respondent on the Mount Royal Claim and the order that the appellant pay the respondent’s costs of the proceedings; 3. Remit the matter to the Equity Division for a determination of the extent, if any, to which the respondent was in breach of the agreement made on 14 November 1988 during the period on and from 14 August 1991 to 31 December 1996 and the damages, if any, the result of such breach for which the respondent is liable having regard to the provisions of the Frustrated Contracts Act; 4. Order that the costs of the hearing before Bryson J be determined by the Judge hearing the matter remitted taking into account the result of the remitted proceedings; 5. No order as to the costs of the appeal.

THE SUPREME COURT
OF NEW SOUTH WALES
COURT OF APPEAL
                            CA 40671/98
                            ED 3609/97

                                PRIESTLEY JA
                                SHELLER JA
                                STEIN JA

UPPER HUNTER TIMBERS PTY LIMITED v FORESTRY COMMISSION OF NEW SOUTH WALES


The appellant claimed damages for breach of contract by the respondent in relation to two agreements. The first of these agreements was allegedly made in 1963 between the respondent and Woolooma Timber Co Pty Limited (Woolooma), whereby the respondent agreed to sell Woolooma timber situated on Crown land which was subsequently gazetted as part of the Stewarts Brook State Forest. The appellant alleged that Woolooma’s rights were transferred to it in or after July 1985 either when the contract was novated or when it exercised Woolooma’s rights under the contract on the basis of a common assumption between it and the respondent that they were the parties to the contract.

The second agreement was…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Upper Hunter Timbers Pty Ltd v Forestry Commission of NSW and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[1999] NSWCA 125
Decision Date

CaseChat Overview and Summary

Upper Hunter Timbers Pty Ltd (the appellant) and the Forestry Commission of New South Wales (the respondent) were parties to litigation concerning a contract for the supply of timber. The dispute centred on the respondent's alleged breaches of this contract and the consequences of a subsequent legislative change. The case was heard in the Court of Appeal of New South Wales.

The primary legal issues before the Court of Appeal were whether the contract constituted a mere agreement to agree, whether the contract had been validly assigned or novated, whether the contract improperly fettered the respondent's statutory discretion, and the extent to which the contract was frustrated by the commencement of the *Forestry Legislation (Amendment) Act 1991* (NSW) and the appellant's entitlement to damages for loss of bargain.

The Court of Appeal found that the contract was not merely an agreement to agree and that the respondent had breached its obligations under the agreement. It also determined that the commencement of the *Forestry Legislation (Amendment) Act 1991* did not automatically frustrate the entire contract, but rather impacted certain aspects of it. The court applied principles of contract law concerning the interpretation of agreements, the effect of statutory intervention on contractual obligations, and the assessment of damages for breach and frustration, including the application of the *Frustrated Contracts Act 1978* (NSW).

The appeal was allowed in part. The court set aside the previous judgment in favour of the respondent on the Mount Royal Claim and the order for costs. The matter was remitted to the Equity Division for a determination of the respondent's breaches of the agreement between 14 August 1991 and 31 December 1996, and the damages payable by the respondent, considering the *Frustrated Contracts Act*. The costs of the original hearing were to be determined by the judge hearing the remitted proceedings, and there were no orders as to the costs of the appeal.

Orders

Orders of the court

1. Appeal allowed in part; 2. Set aside so much of the order of Bryson J of 17 August 1998 as gave judgment for the respondent on the Mount Royal Claim and the order that the appellant pay the respondent’s costs of the proceedings; 3. Remit the matter to the Equity Division for a determination of the extent, if any, to which the respondent was in breach of the agreement made on 14 November 1988 during the period on and from 14 August 1991 to 31 December 1996 and the damages, if any, the result of such breach for which the respondent is liable having regard to the provisions of the Frustrated Contracts Act; 4. Order that the costs of the hearing before Bryson J be determined by the Judge hearing the matter remitted taking into account the result of the remitted proceedings; 5. No order as to the costs of the appeal.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established