Tyco Fire and Security v Norfolk Mechanical

Case [2007] NSWSC 585


CITATION: Tyco Fire & Security & Anor v Norfolk Mechanical & Ors [2007] NSWSC 585
HEARING DATE(S): 9, 10 and 15 May 2007
 
JUDGMENT DATE : 

13 June 2007
JURISDICTION: Commercial List
JUDGMENT OF: McDougall J at [1]
DECISION: See para [106] of judgment
CATCHWORDS: CONTRACTS - construction and interpretation - price adjustment clause - plaintiff gave defendant dispute notice - specific time regime for furtherance or resolution of dispute - whether time of the essence - whether defendant's response to dispute notice delivered in time - definition of "Business Day" - distinction between delivery and receipt - whether deemed receipt of notice amounts to delivery - whether time began to run from delivery - form of relief - costs
LEGISLATION CITED: Conveyancing Act 1919
English Bills of Exchange Act 1882
English Limitation Act 1939
CASES CITED: Australian Broadcasting Commission v Australasian Performing Right Association Limited (1973) 129 CLR 99
Curtice v London City and Midland Bank, Limited [1908] 1 K.B. 293
Eaglehill Ltd v J. Needham Builders Ltd [1973] AC 992
FAI General Insurance Company Ltd (In Liquidation) v Parras and Others (2002) 55 NSWLR 498
G R Mailman & Associates Pty Ltd v Wormald (Aust) Pty Ltd (1991) 24 NSWLR 80
Lolly Pops (Harbourside) Pty Ltd v Werncog Pty Ltd (1998) 9 BPR 16, 361
Newborough (Lord) v Jones [1975] Ch 90
NM Superannuation Pty Ltd v Hughes and Others (1992) 27 NSWLR 26
N.V. Stoomv Maats “de Maas” v Nippon Yusen Kaisha (The “Pendrecht”) [1980] 2 Lloyd’s Rep 56
Parras & Ors v FAI General Insurance Company Ltd (Prov Liq apptd) [2001] NSWSC 1077
Toll (FGCT) Pty Limited v Alphapharm Pty Limited and Others (2004) 219 CLR 165
United Scientific Holdings Ltd v Burnley Borough Council [1978] AC 904
United Scientific Holdings (see Gollin & Company Limited v Karenlee Nominees Proprietary Limited and Another (1983) 153 CLR 455
PARTIES: Tyco Fire & Security Pty Limited (First Plaintiff)
Firmagroup Operations Holdings Pty Limited (Second Plaintiff)
Norfolk Mechanical (Aust) Pty Limited (First Defendant)
Norfolk Electrical (Aust) Pty Limited (Second Defendant)
Norfolk Building Products (Aust) Pty Limited (Third Defendant)
FILE NUMBER(S): SC 50127/05
COUNSEL: S G Finch SC/G K J Rich (Plaintiffs)
A J L Bannon SC/D B Studdy (Defendants)
SOLICITORS: Allens Arthur Robinson (Plaintiffs)
Gilbert & Tobin (Defendants)

Tyco Fire & Security & Anor v Norfolk Mechanical & Ors [2007] NSWSC 585

INDEX TO JUDGMENT

Para
The issues 2
Factual background 5
Relevant contractual provisions 7
First issue: is time of the essence of clause 7.7(b)? 13
Issue 2: was Norfolk’s response delivered in time? 23
Background 23
The competing submissions 24
Decision 34
Approach to construction 35
Delivery and receipt: the relevant principles 39
Analysis 61
Conclusion 89
Consequences 91
Issues 14 to 17: the Completion Balance Sheets of 16 November and 9 December 2004 95
Relief 104
Orders 106


IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
COMMERCIAL LIST

McDOUGALL J

13 June 2007

      MECHANICAL PTY LIMITED & ORS

JUDGMENT

1 HIS HONOUR:…

Continue reading Tyco Fire and Security v Norfolk Mechanical

Sign in free to access the full text

Details
AGLC
Tyco Fire and Security v Norfolk Mechanical [2007] NSWSC 585
Case
[2007] NSWSC 585
Decision Date

CaseChat Overview and Summary

The matter between Tyco Fire and Security and Norfolk Mechanical involved a contractual dispute regarding a price adjustment clause. Norfolk Mechanical, the defendant, was required to provide a price adjustment notice to Tyco Fire and Security, the plaintiff, within a specified time frame. The plaintiff gave the defendant a dispute notice, and the contract outlined a specific regime for the resolution or furtherance of the dispute. The central legal issues were whether the time stipulated for the defendant's response was of the essence and whether the defendant's response to the dispute notice was delivered in time. Additionally, the court had to determine the meaning of "Business Day" in the context of the contract, whether the delivery or receipt of the notice was pertinent, and whether deemed receipt of the notice constituted delivery. The court also needed to decide whether the time began to run from the delivery of the notice and the appropriate form of relief, including the costs incurred.

The court held that the time for the defendant's response was indeed of the essence. The defendant's response to the dispute notice was not delivered in time, as the contract specified a strict time regime for such responses. Regarding the definition of "Business Day," the court ruled that the contract did not consider the receipt of the notice as the commencement of the time period but rather its delivery. The court clarified that deemed receipt of the notice did not equate to its delivery. Consequently, the time began to run from the delivery of the notice. As for the form of relief, the court awarded costs to the plaintiff, Tyco Fire and Security, for the defendant's failure to comply with the contractual obligations.

In summary, the court found that the defendant's response to the dispute notice was not timely, and the time period was triggered by the delivery of the notice rather than its receipt. The court awarded costs to the plaintiff, Tyco Fire and Security, for the defendant's non-compliance with the contractual obligations. The judgment emphasised the importance of adhering to strict time frames in contractual disputes and the consequences of failing to do so.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.