Medium Neutral Citation: Toyne v Stokes [2022] NSWDC 292 Hearing dates: 13 July 2022 Date of orders: 26 July 2022 Decision date: 26 July 2022 Jurisdiction: Civil Before: Russell SC DCJ Decision: (1) Dismiss the plaintiff’s Notice of Motion filed on 14 September 2021.
(2) Strike out the Statement of Claim filed on 5 July 2021.
(3) Grant leave to the plaintiff to file an Amended Statement of Claim by 23 August 2022.
(4) Order the plaintiff to pay the defendant’s costs of the Notice of Motion filed on 14 September 2021.
(5) Dismiss the defendant’s Notice of Motion filed on 10 October 2021.
(6) Order the defendant to pay the plaintiff’s costs of the Notice of Motion filed on 10 October 2021.
Catchwords: PROCEDURE – Contracts for sale of land – purchaser did work on land and contaminated it with asbestos – contracts terminated by vendor – Supreme Court proceedings seeking relief against forfeiture of deposits – later District Court proceedings by vendor seeking damages against purchaser for contamination of land – whether District Court proceedings were estopped by Anshun principles – whether District Court proceedings should be stayed as an abuse of process
Legislation Cited: Conveyancing Act 1919 (NSW), s 55(2A)
Cases Cited: Champers Life Pty Ltd v Manojlovski [2010] NSWSC 641
Cromwell v County of Sac (1876) 94 U.S. 351
Hannigan v Inghams Enterprises Pty Ltd [2021] NSWSC 641
Henderson v Henderson (1843) 67 ER 319
Jacobellis v Ohio (1963) 378 U.S. 184
Johnson v Gore Wood & Co [2002] 2 AC 1
Port of Melbourne Authority v Anshun Pty Ltd [1981] HCA 45; (1981) 147 CLR 589
Stokes v Toyne [2019] NSWSC 274
Stokes v Toyne [2021] NSWSC 1049
Category: Procedural rulings Parties: Molly Toyne (Plaintiff)
Nathan Stokes (Defendant)Representation: Counsel:
Solicitors:
M Castle and A Bailey (Plaintiff)
N Oram (Defendant)
Baker Deane & Nutt (Defendant)
File Number(s): 2021/195454
Judgment
Background
-
In 2016 the plaintiff Ms Toyne was the vendor of land in Gundaroo and the defendant Mr Stokes was the purchaser. Between exchange and settlement Ms Toyne allowed Mr Stokes, a civil engineering contractor, to enter upon the land and perform work to make the property ready for subdivision. While on the land Mr Stokes demolished sheds which contained asbestos. The Agreements for Sale of Land were terminated by Ms Toyne and the deposits were forfeited to her.
-
By a Statement of Claim filed in this court on 5 July 2021 the Ms Toyne sued Mr Stokes for damages, particularised as $235,080 to remedy and remove asbestos from the plaintiff’s land and $2,500 to reinstate fences on the land.
-
The Statement of Claim filed on 5 July 2021 is short and quite defective. Ms Toyne filed a Notice of Motion on 14 September 2021 seeking leave to file an Amended Statement of Claim. The draft…
Continue reading Toyne v Stokes
Sign in free to access the full text
- AGLC
- Toyne v Stokes [2022] NSWDC 292
- Case
- [2022] NSWDC 292
- Decision Date
CaseChat Overview and Summary
The court examined the relationship between the proceedings in the Supreme Court and the District Court. It was determined that the Supreme Court proceedings were not precluded by the Anshun estoppel as they did not involve the same cause of action as the District Court proceedings. The court held that the Supreme Court proceedings were for relief against forfeiture of deposits, while the District Court proceedings were for damages for contamination of the land. These were distinct causes of action, and therefore, the Anshun estoppel did not apply. Furthermore, the court found that the District Court proceedings were not an abuse of process, as Toyne had a legitimate interest in seeking damages for the contamination caused by Stokes. Consequently, the court dismissed the motions filed by both parties and ordered costs in favour of Stokes.
The final orders of the court were to dismiss the plaintiff's notice of motion filed on 14 September 2021, strike out the plaintiff's statement of claim filed on 5 July 2021, and grant leave to the plaintiff to file an amended statement of claim by 23 August 2022. Additionally, the court ordered the plaintiff to pay the defendant's costs of the notice of motion filed on 14 September 2021. The court also dismissed the defendant's notice of motion filed on 10 October 2021 and ordered the defendant to pay the plaintiff's costs of that notice of motion. These orders effectively concluded the court's consideration of the procedural issues raised in the case and set the stage for any potential future claims that may be pursued by the parties.
Orders
Orders of the court
(1) Dismiss the plaintiff’s Notice of Motion filed on 14 September 2021.
(2) Strike out the Statement of Claim filed on 5 July 2021.
(3) Grant leave to the plaintiff to file an Amended Statement of Claim by 23 August 2022.
(4) Order the plaintiff to pay the defendant’s costs of the Notice of Motion filed on 14 September 2021.
(5) Dismiss the defendant’s Notice of Motion filed on 10 October 2021.
(6) Order the defendant to pay the plaintiff’s costs of the Notice of Motion filed on 10 October 2021.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.