JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

IN CHAMBERS

CITATION:   THUNDELARRA LTD -v- RICHMOND [No 2] [2013] WASC 392

CORAM:   EDELMAN J

HEARD:   14, 15 & 17 OCTOBER 2013

DELIVERED          :   29 OCTOBER 2013

FILE NO/S:   CIV 2515 of 2012

BETWEEN:   THUNDELARRA LTD

Plaintiff

AND

WILLIAM ROBERT RICHMOND
First Defendant

KALLENIA MINES PTY LTD
Second Defendant

Catchwords:

Contract - Construction of contract terms - Irrelevance of pre-contractual negotiations - Operation of Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves - Relevance of expert evidence

Legislation:

Nil

Result:

Specific performance ordered
Declarations made

Category:    B

Representation:

Counsel:

Plaintiff:     Mr S Penglis

First Defendant             :     In person

Second Defendant         :     In person (Mr W R Richmond)

Solicitors:

Plaintiff:     Herbert Smith Freehills

First Defendant             :     In person

Second Defendant         :     In person

Cases referred to in judgment:

Able Demolitions and Excavations Pty Ltd v Wilson [2012] WASC 61

Anaconda Nickel Ltd v Tarmoola Australia Pty Ltd [2000] WASCA 27; (2000) 22 WAR 101

Byrnes v Kendle [2011] HCA 26; (2011) 243 CLR 253

Chartbrook Ltd v Persimmon Homes Ltd [2009] UKHL 38; [2009] AC 1101

Donyette Pty Ltd v Toplodge Nominees Pty Ltd [No 2] [2011] WASC 141

Eastern Metropolitan Regional Council v Four Seasons Constructions Pty Ltd [2000] WASC 178; (2000) 22 WAR 372

Hammond v Vam Ltd [1972] 2 NSWLR 16

HPM Pty Ltd v Fear [2002] WASCA 249

John Alexander's Clubs Pty Ltd v White City Tennis Club Ltd [2010] HCA 19; (2010) 241 CLR 1

McCourt v Cranston [2012] WASCA 60

Meehan v Jones [1982] HCA 52; (1982) 149 CLR 571

Mineralogy Pty Ltd v Sino Iron Pty Ltd [2013] WASC 194

Miorada v Miorada [2005] WASC 105

Netglory Ltd v Caratti [2013] WASC 364

Re Hoffman [2004] WASCA 238; (2004) 187 FLR 263

Red Hill Iron Ltd v API Management Pty Ltd [2012] WASC 323

Upper Hunter County District Council v Australian Chilling & Freezing Co Ltd [1968] HCA 8; (1968) 118 CLR 429

Vincent Nominees Pty Ltd v Western Australian Planning Commission [2012] WASC 28

Table of Contents

Introduction
Glossary of terms used in these reasons
The mining licences held by Mr Richmond and Kallenia Mines
The Agreement between Thundelarra and the defendants
Events subsequent to the Agreement
The matters in issue
Issue 1:      The proper construction of 'define[d] a JORC compliant resource'

The competing constructions
Mr Richmond's first submission
Mr Richmond's second submission
Thundelarra's submission
The evidence of pre‑contractual negotiations and surrounding circumstances

Issue 2:      Did Thundelarra 'define a JORC compliant resource' in Red Bore?

Application of the proper construction
The focus on the Runge Report
The expert evidence generally
The two experts called by the defendants:  Mr Jones and Mr Procter
The quality assurance and quality control procedures adopted during the geological assessment stage

(1)      Mr Jones' conclusion should be rejected because his premise was wrong
(2)      Mr Jones' conclusion should be rejected because it is incorrect

The conclusion that there is a…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Thundelarra Ltd v Richmond [No 2] and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2013] WASC 392
Decision Date

CaseChat Overview and Summary

Thundelarra Ltd commenced proceedings against Richmond in the Supreme Court of Western Australia. The dispute revolves around the interpretation of certain terms within a contract, specifically focusing on the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code) and the reliability of expert evidence provided by Mr Jones. The primary issue before the court was whether the expert evidence presented by Mr Jones regarding the verifiability and reliability of certain mineral resources was accurate and sufficient under the terms of the contract and the JORC Code.

The court had to determine the extent to which Mr Jones' evidence on the verifiability and reliability of mineral resources was reliable and whether it adhered to the requirements set out in the JORC Code. Mr Jones had initially argued that certain samples could not be verified or were unreliable, suggesting that these factors were critical to the compliance of the reports with the JORC Code. However, the court found that Mr Jones' premise, which posited a single, absolute notion of verifiability and reliability, was flawed. The court held that the concepts of verifiability and reliability are inherently subjective and flexible, and that the JORC Code does not demand a specific level of these attributes. Instead, the Code is designed to accommodate varying degrees of uncertainty and confidence.

The court rejected Mr Jones' conclusion, finding that his premise was incorrect and that his evidence did not accurately reflect the flexible nature of the JORC Code's requirements. The court concluded that Mr Jones' opinion, which suggested that a lack of verifiability or reliability rendered a report non-compliant with the JORC Code, did not align with the broader principles of the Code. As a result, the court found that the reports in question were, in fact, compliant with the JORC Code. The court’s reasoning led to the dismissal of Thundelarra Ltd’s claims against Richmond.

Background

Background to the litigation

Decision

Reasons for decision

Mr Jones' conclusion should be rejected because his premise was wrong The premise of Mr Jones' opinion was incorrect. This premise was that there is a single correct notion of 'verifiability' and 'reliability' which underpins the JORC Code, and without which a report would not be JORC Code compliant. In his oral evidence, Mr Jones elaborated in this way:[119]The purpose of all this quality control is to allow the competent person to verify the accuracy of the samples, okay. If the samples are not accurate and reliable, you can’t calculate a resource because the information might be incorrect ... this is all about verifying the samples, okay. If the samples are not correct, the resource can’t be calculated.(Emphasis added). [119] ts 173 (Mr Jones). One reason why this premise is incorrect is self‑evident. The concepts of 'verifiability' and 'reliability' are inherently flexible and often subjective concepts. Veritas was the Roman goddess of truth. But, apart from mythology, the concepts of verifiability and reliability are abstract and heavily dependent upon judgement. In Mr Jones' second report,[120] the absolute language of 'cannot be verified' became more equivocal. He suggested that the quality assurance and quality control 'were inadequate' and had 'insufficient standards, duplicates and blanks' to allow the proper verification. He suggested that a Competent Person would reasonably disqualify the resource estimate as meeting the minimum requirements of the JORC Code.[120] Exhibit A2 (Witness Statement of Mr Jones, 12 September 2013), 'Response: Red Bore Prospect Mineralisation'. During oral evidence Mr Jones eventually accepted that issues of quality assessment and quality control involved a 'spectrum' of degrees of confidence where different people might have different degrees of confidence.[121] Mr Jones' evidence came to be expressed in more personal terms: he focused upon his view that he could not verify the accuracy of the 50‑odd holes other than the 11 holes which he considered sufficient, his opinion that the 11 holes were not sufficient, and that he would not use that data in his estimates.[122] [121] ts 175 - 176 (Mr Jones).[122] ts 199 (Mr Jones). Mr Jones' eventual position in oral evidence is more accurate than his earlier absolute statements, but his view is still flawed because the notions of verification and accuracy are not concepts which, by themselves, are required by the JORC Code. The JORC Code does not require any particular level of verifiability or reliability. Indeed, I have already explained above at [84] ‑ [85] why the abstract concepts of verifiability and reliability are not principles, which, if violated, would cause a report to not be compliant with the JORC Code. This conclusion should be unsurprising. The JORC Code is a Code concerned with the manner and circumstances of appropriate reporting. It acknowledges degrees of uncertainty and the possibility of reporting matters which might be the subject of a low degree of confidence.

Ratio Decidendi

Legal principle established