Thiess Contractors Pty Ltd v Murchison Zinc Co Pty Ltd

Link copied
Case Copied 13 min read

THIESS CONTRACTORS PTY LTD -v- MURCHISON ZINC CO PTY LTD [2000] WASC 71



SUPREME COURT OF WESTERN AUSTRALIACitation No:[2000] WASC 71
20/03/2000
Case No:CIV:2137/19962 MARCH 2000
Coram:TEMPLEMAN J9/03/00
9Judgment Part:1 of 1
Result: Application dismissed
PDF Version
Parties:THIESS CONTRACTORS PTY LTD (ACN 010 221 486)
MURCHISON ZINC CO PTY LTD (ACN 008 950 178)

Catchwords:

Civil procedure Western Australia
Rules of the Supreme Court, O 20 r 19
Application to strike out statement of claim
Dispute arising from a mining project's excavation and construciton contract
Application made on the basis that the plaintiff's is a global claim and that it was not pleaded with sufficient particularity

Legislation:

Rules of the Supreme Court, O 20 r 19

Case References:

John Holland Construction & Engineering Pty Ltd v Kvaerner R J Brown Pty Ltd (1997) 13 BCL 262
Nil

JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
    IN CHAMBERS
CITATION : THIESS CONTRACTORS PTY LTD -v- MURCHISON ZINC CO PTY LTD [2000] WASC 71 CORAM : TEMPLEMAN J HEARD : 2 MARCH 2000 DELIVERED : 9 MARCH 2000 PUBLISHED : 20 MARCH 2000 FILE NO/S : CIV 2137 of 1996 BETWEEN : THIESS CONTRACTORS PTY LTD (ACN 010 221 486)
    Plaintiff

    AND

    MURCHISON ZINC CO PTY LTD (ACN 008 950 178)
    Defendant



Catchwords:

Civil procedure Western Australia - Rules of the Supreme Court, O 20 r 19 - Application to strike out statement of claim - Dispute arising from a mining project's excavation and construction contract - Application made on the basis that the plaintiff's is a global claim and that it was not pleaded with sufficient particularity




Legislation:

Rules of the Supreme Court, O 20 r 19



(Page 2)

Result:

Application dismissed

Representation:


Counsel:


    Plaintiff : Mr P G Clifford
    Defendant : Mr D J Martino


Solicitors:

    Plaintiff : Fiocco Hopkins Nash
    Defendant : Pullinger Stewart


Case(s) referred to in judgment(s):

John Holland Construction & Engineering Pty Ltd v Kvaerner R J Brown Pty Ltd (1997) 13 BCL 262

Case(s) also cited:



Nil

(Page 3)

1 TEMPLEMAN J: This is an application to strike out substantial portions of the plaintiff's statement of claim in an action which was commenced in 1996.

2 The plaintiff is a mining company which, at the material time, was acting as agent for a group of joint venturers. The plaintiff carries on business as an underground and civil works contractor.

3 The action arises out of a contract made between the parties in September 1994 which was incorporated in a written document executed in November 1995.

4 The contract was for the excavation and construction of a decline. It was a schedule of rates contract comprising a number of documents including special and general conditions, drawings and specifications and the schedule of rates.

5 In its statement of claim, the plaintiff contends that on about 3 and 4 December 1994, the Superintendent, acting on behalf of the defendant,…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Thiess Contractors Pty Ltd v Murchison Zinc Co Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2000] WASC 71
Decision Date

CaseChat Overview and Summary

In the Supreme Court of Western Australia, Thiess Contractors Pty Ltd, a mining contractor, brought a claim against Murchison Zinc Co Pty Ltd, the client, over a dispute concerning an excavation and construction contract. The dispute arose from alleged breaches of contract and associated damages. Murchison Zinc Co Pty Ltd filed an application to have the plaintiff's statement of claim struck out, arguing that it was a global claim and lacked the required particularity as mandated by Rule 19 of the Supreme Court Rules 2003. The application hinged on the notion that the plaintiff's claims were not sufficiently detailed and that it failed to identify the specific breaches and the resultant damages with the requisite precision.

The court was required to determine whether the plaintiff's statement of claim met the legal standards set by the Supreme Court Rules and whether the application to strike out should be granted. This involved examining the sufficiency of the particulars provided in the statement of claim and whether the plaintiff's allegations were specific enough to inform the defendant of the nature of the claims and the basis upon which they were made. The court needed to balance the plaintiff's right to a fair opportunity to have its claims heard with the defendant's right to be protected from vague and unsubstantiated allegations.

In dismissing the application, the court held that the plaintiff's statement of claim, while not perfect, contained sufficient particulars to allow the defendant to understand the nature of the claims and to prepare an appropriate defence. The court noted that the plaintiff had identified the contract in question, the nature of the alleged breaches, and provided a general outline of the resulting damages. The court determined that the plaintiff's claims, though not ideal, were adequate to withstand a motion to strike out. The application was dismissed, allowing the case to proceed to trial.

Orders

Orders of the court

Application dismissed

Background

Background to the litigation

Thiess Contractors Pty Ltd (Thiess) entered into a contract with Murchison Zinc Co Pty Ltd (Murchison) for the excavation and construction of a mining project. Following alleged breaches of the contract by Murchison, Thiess initiated legal proceedings. The Statement of Claim outlined multiple causes of action, including claims for damages and specific performance, arising from various alleged defaults and breaches of the contract by Murchison. Thiess alleged that Murchison failed to provide timely access to the site, did not provide necessary information, and made changes to the scope of work without proper authorisation. These issues resulted in delays and increased costs for Thiess, leading to the claim for damages. Additionally, Thiess sought specific performance to compel Murchison to fulfil certain obligations under the contract.

Murchison filed an application to strike out the Statement of Claim pursuant to Order 20 Rule 19 of the Supreme Court of Western Australia. The basis for the application was that Thiess's claim was a global claim, meaning it was not pleaded with sufficient particularity, and that it failed to comply with the requirements of the rules of court. The application to strike out was heard by the court, which needed to determine whether the Statement of Claim met the necessary standards of particularity and compliance with procedural rules.

Decision

Reasons for decision

Issues
1. Whether the Statement of Claim constitutes a global claim and was not pleaded with sufficient particularity as required by the Rules of the Supreme Court.
2. Whether the Statement of Claim complies with the requirements of the rules of court concerning the particularity of pleadings.

Held
1. The court held that the Statement of Claim did not constitute a global claim and was pleaded with sufficient particularity as required by the Rules of the Supreme Court.
2. The court held that the Statement of Claim complies with the requirements of the rules of court concerning the particularity of pleadings.

Ratio Decidendi

Legal Principle Established

The court examined the Statement of Claim to determine whether it constituted a global claim and if it was pleaded with sufficient particularity. It considered the requirements set out in O 20 r 19 of the Rules of the Supreme Court. The court found that the plaintiff had set out specific claims relating to particular breaches of contract, rather than making a vague and general allegation. This meant that the claim was not a global claim, which is a broad, vague allegation that lacks specificity in the pleadings.

Furthermore, the court assessed whether the Statement of Claim met the particularity requirements of the rules of court. It found that the plaintiff had provided enough detail to enable the defendant to understand the nature of the claims and to prepare a defence. The court considered that the plaintiff had identified the contract in question, the specific breaches, and the resulting losses, which was sufficient to meet the requirements for particularity.

In reaching its decision, the court applied established principles concerning the sufficiency of pleadings. It relied on the need for a balance between ensuring that a plaintiff has sufficient particularity in their pleadings and avoiding excessive detail that would be burdensome. The court also referenced relevant case law to support its understanding of these principles, ensuring that it adhered to the established legal framework.

The ratio decidendi of this decision is that in disputes arising from construction contracts, a Statement of Claim need not be overly detailed to be considered sufficiently particular. Instead, it must provide enough information for the defendant to understand the nature of the claims and to prepare a defence. The court's decision does not depart from prior authority but reaffirms the balance required in assessing the particularity of pleadings.