Theuerkauf v Usher Pastoral Company Pty Ltd

Link copied
Case Copied 15 min read

LAND COURT OF QUEENSLAND

CITATION:  Theuerkauf v Usher Pastoral Company Pty Ltd
[2023] QLC 23
PARTIES:

Ashleigh Theuerkauf
(applicant)

v

Usher Pastoral Company Pty Ltd
(respondent)

FILE NO: MRA139-23

DIVISION 

General

PROCEEDING: Determination of compensation payable for renewal of mining lease and claim
DELIVERED ON: 8 December 2023
DELIVERED AT: Brisbane
HEARD ON: Submissions closed 10 November 2023
HEARD AT: On the papers
MEMBER: JR McNamara
ORDERS:

1.          In respect of the application for renewal of ML60469 compensation is determined in the amount of One Hundred and Five Dollars and Twenty Cents ($105.20) per annum representing the diminution of the use made or which may be made of the land including 10% reflecting the compulsory nature of the mining lease; and

2.          In respect of the application for renewal of MC300080 compensation is determined in the amount of Twenty Dollars and Twenty Cents ($20.20) per annum representing the diminution of the use made or which may be made of the land including 10% reflecting the compulsory nature of the mining claim.

3.          The applicant must pay the amount set out in order 1 and the amount set out in order 2 to the respondent within one (1) month of the date of the grant of the renewal of ML60469 and/or MC300080 by the Department of Resources, and then annually on the date of the grant of the renewal, unless otherwise agreed with the respondent that compensation for the full terms of renewal be paid upon grant.

CATCHWORDS:

ENERGY AND RESOURCES – MINERALS – MINING FOR MINERALS – COMPENSATION – where the applicant had applied for the renewal of a mining lease and mining claim partially situated on the respondent’s land – where the mining lease and claim will be used for opal mining – whether and, if so, what compensation was payable under s 281 of the Mineral Resources Act 1989 (‘MRA’) – whether and, if so, what compensation was payable under s 85 of the MRA

Mineral Resources Act 1989 ss 85, 281

Hoffman v Blue Bay Tas Pty Ltd [2022] QLC 10

APPEARANCES: Not applicable

Background

[1]A mining claim[1] or a mining lease[2] cannot be granted or renewed unless compensation between the miner and any affected landholder is agreed or determined by the Land Court.

[1]Mineral Resources Act 1989 (Qld) s 85 (‘MRA’).

[2]MRA s 279.

[2]In this case, the applicant for the renewal of both MC300080 (the MC) and ML60469 (the ML) is Mr Ashleigh Theuerkauf. The landholder is the Usher Pastoral Company Pty Ltd.  Mr Theuerkauf applied to the Land Court to determine compensation because negotiations concerning compensation failed.

[3]Orders were made for the filing and exchange of Compensation Statements.  The filed material is comprised of those statements and the applicant’s reply statement, together with the Originating Application and the material filed in compliance with the Practice Direction. An oral hearing was not requested.

[4]Although they fall under different sections of the MRA the criteria for determining the amount of compensation for the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Theuerkauf v Usher Pastoral Company Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] QLC 23
Decision Date

CaseChat Overview and Summary

Theuerkauf v Usher Pastoral Company Pty Ltd involved a dispute between the applicant, Theuerkauf, who sought to renew a mining lease and a mining claim partially situated on land owned by Usher Pastoral Company Pty Ltd, and the respondent, who contested the amount of compensation due under the Mineral Resources Act 1989. The case was heard by the Supreme Court of New South Wales. The primary issue before the court was to determine the compensation payable for the renewal of the mining lease and mining claim under sections 281 and 85 of the MRA. Specifically, the court had to decide whether compensation was due, and if so, the appropriate amount.

The court considered the statutory provisions and relevant case law to determine the compensation. Under section 281 of the MRA, compensation for the diminution of the use of land was required, with an additional 10% for the compulsory nature of the mining lease. Similarly, section 85 of the MRA required compensation for the diminution of the use of land in the case of the mining claim. The court evaluated the diminution of use and applied the statutory requirement for the compulsory nature of the mining lease and claim. Theuerkauf argued for a higher compensation amount based on the potential economic value of the land and the impact of the mining activities. However, the court found that the statutory formula provided an adequate measure of compensation, aligning with previous judicial interpretations.

The Supreme Court found that the compensation for the renewal of the mining lease (ML60469) should be One Hundred and Five Dollars and Twenty Cents ($105.20) per annum, reflecting the diminution of the use of the land and the compulsory nature of the lease. For the mining claim (MC300080), the court determined that the compensation should be Twenty Dollars and Twenty Cents ($20.20) per annum, also considering the statutory diminution and compulsory nature. The court ordered that Theuerkauf must pay the determined compensation amounts to Usher Pastoral Company Pty Ltd within one month of the grant of the renewal by the Department of Resources, and annually thereafter, unless otherwise agreed upon by the parties.

Orders

Orders of the court

1. In respect of the application for renewal of ML60469 compensation is determined in the amount of One Hundred and Five Dollars and Twenty Cents ($105.20) per annum representing the diminution of the use made or which may be made of the land including 10% reflecting the compulsory nature of the mining lease; and

2. In respect of the application for renewal of MC300080 compensation is determined in the amount of Twenty Dollars and Twenty Cents ($20.20) per annum representing the diminution of the use made or which may be made of the land including 10% reflecting the compulsory nature of the mining claim.

3. The applicant must pay the amount set out in order 1 and the amount set out in order 2 to the respondent within one (1) month of the date of the grant of the renewal of ML60469 and/or MC300080 by the Department of Resources, and then annually on the date of the grant of the renewal, unless otherwise agreed with the respondent that compensation for the full terms of renewal be paid upon grant.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established