Theuerkauf v Usher Pastoral Company

Link copied
Case Copied 12 min read

LAND COURT OF QUEENSLAND

CITATION:  Theuerkauf v Usher Pastoral Company [2024] QLC 17
PARTIES:

Ashleigh Wayne Theuerkauf
(applicant)

v

Usher Pastoral Company Pty Ltd
(respondent)

FILE NO:

MRA122-24

PROCEEDING: Application for compensation for mining claim renewal  
DELIVERED ON: 24 September 2024
DELIVERED AT: Brisbane
HEARD ON: Submissions closed 19 July 2024
HEARD AT: On the papers  
MEMBER: JR McNamara
ORDERS:

1.   In respect of the application for renewal of MC300081 compensation is determined in the amount of Fifty-Two Dollars and Eighty Cents ($52.80) per annum representing the diminution of the use made or which may be made of the land including 10% reflecting the compulsory nature of the mining claim; and

2.   The applicant must pay the amount set out in order 1 to the respondent within one (1) month of the date of grant of the renewal of MC300081 by the Department of Resources, and then annually on the date of the grant of the renewal, unless otherwise agreed with the respondent that compensation for the full terms of renewal be paid upon grant.

CATCHWORDS:

ENERGY AND RESOURCES – MINERALS – MINING FOR MINERALS – COMPENSATION – where the applicant has applied for a mining claim renewal situated on the respondent’s land – where the mining claim would be used for opal mining – whether and if so, what compensation is payable under s 85 of the Mineral Resources Act 1989

Mineral Resources Act 1989 s 85

Theuerkauf v Usher Pastoral Company Pty Ltd [2023] QLC 23
Daunis v Usher Pastoral Company Pty Ltd [2023] QLC 24

APPEARANCES: Not applicable

Background

  1. A mining claim cannot be granted or renewed unless compensation between the miner and any affected landholder is agreed or determined by the Land Court.[1]

    [1]Mineral Resources Act 1999 (Qld) s 85 (‘MRA’).

  1. Mr Ashleigh Theuerkauf is the applicant for the renewal of MC300081 and the Usher Pastoral Company Pty Ltd is the affected landholder. Mr Theuerkauf applied to the Land Court to determine compensation because he has been unable to negotiate compensation with the respondent. 

  1. On 17 May 2024 I made orders for the filing of compensation statements. The applicant filed their compensation statement in compliance with those orders. On 8 July 2024, the respondent advised the Court by way of email that they would not be filing a response compensation statement and confirmed this again on 9 August 2024. The filed material therefore is comprised solely of the applicant’s statement.

  1. I am satisfied that it is appropriate to decide the application without an oral hearing and the parties, after receiving notice of the proposal to decide the application on the papers, have not requested an oral hearing.[2]

    [2]Land Court Rules 2022 s 36(1)(a).

  1. MC300081 is the subject of this application. It is in the ‘Bush Paddock’ portion of Mount Margaret Station (Lot 447 on SP196201), an area of approximately 70,000 hectares located 50km west of Eromanga.  Mount Margaret Station was acquired by Usher Pastoral Company in 2017. The local regional council is…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Theuerkauf v Usher Pastoral Company and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] QLC 17
Decision Date

CaseChat Overview and Summary

Theuerkauf, the applicant, sought the renewal of a mining claim (MC300081) situated on Usher Pastoral Company's land, for the purpose of opal mining. The dispute before the court was whether any compensation was payable under section 85 of the Mineral Resources Act 1989, and if so, what amount was appropriate. The court was tasked with determining the annual compensation payable to Usher Pastoral Company for the use of their land by the applicant’s mining claim.

The central legal issue was the interpretation and application of section 85 of the Mineral Resources Act 1989. The court had to decide whether the applicant's use of the respondent's land for opal mining warranted compensation and, if so, how to calculate the appropriate amount. The court considered factors such as the diminution of the use made or which may be made of the land and the compulsory nature of the mining claim.

The court found that compensation was payable and set the annual amount at Fifty-Two Dollars and Eighty Cents ($52.80), reflecting a 10% adjustment for the compulsory nature of the mining claim. This amount represented the diminution of the use made or which may be made of the land. The court ordered that the compensation must be paid by the applicant to the respondent within one month of the grant of the renewal and annually thereafter, unless otherwise agreed.

The final orders of the court mandated the payment of compensation in the determined amount and specified the payment schedule. The applicant was to pay the sum to the respondent within one month of the grant of the renewal and annually thereafter, unless a different arrangement was agreed upon by both parties.

Orders

Orders of the court

1. In respect of the application for renewal of MC300081 compensation is determined in the amount of Fifty-Two Dollars and Eighty Cents ($52.80) per annum representing the diminution of the use made or which may be made of the land including 10% reflecting the compulsory nature of the mining claim; and

2. The applicant must pay the amount set out in order 1 to the respondent within one (1) month of the date of grant of the renewal of MC300081 by the Department of Resources, and then annually on the date of the grant of the renewal, unless otherwise agreed with the respondent that compensation for the full terms of renewal be paid upon grant.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established