FEDERAL COURT OF AUSTRALIA
The Summit Group (Australia) Pty Ltd v Owners Corporation 1 Plan No PS746020J [2020] FCA 1847
File number: VID 479 of 2020 Judgment of: COLVIN J Date of judgment: 23 December 2020 Catchwords: COMMUNICATIONS LAW - application for declaration that carrier entitled to access property to install radio communications antennas and equipment - application for injunction restraining respondents from preventing carrier from carrying out works on property - where carrier gave notice of intention to access property under Telecommunications Act 1997 (Cth) - where notice specified range of dates proposed to enter property - where range of dates included dates before required period of notice - whether notice allowed required period of notice - whether proposed activities in respect of low-impact facilities - whether period of notice affected validity of notice - application dismissed Legislation: Telecommunications Act 1997 (Cth) Part 6, Schedule 3, cl 15, cl 17 Cases cited: Australian Mines and Metals Association Inc v Construction, Forestry, Maritime, Mining and Energy Union [2018] FCAFC 223; (2018) 268 FCR 128
Certain Lloyd's Underwriters Subscribing to Contract No IH00AAQS v Cross [2012] HCA 56; (2012) 248 CLR 378
Forrest & Forrest Pty Ltd v Wilson [2017] HCA 30; (2017) 262 CLR 510
Hutchison 3G Australia Pty Ltd v Director of Housing [2004] VSCA 99
Minister for Employment and Workplace Relations v Gribbles Radiology Pty Ltd [2005] HCA 9; (2005) 222 CLR 194
Project Blue Sky Inc v Australian Broadcasting Authority [1998] HCA 28; (1998) 194 CLR 355
SZTAL v Minister for Immigration and Border Protection [2017] HCA 34; (2017) 262 CLR 362
Division: General Division Registry: Victoria National Practice Area: Other Federal Jurisdiction Number of paragraphs: 83 Date of last submissions: 18 December 2020 (Applicant)
21 December 2020 (Respondents)Date of hearing: 14 December 2020 Counsel for the Applicant: Mr M Hoyne Solicitor for the Applicant: South East Lawyers Counsel for the Respondents: Mr J Lipinski Solicitor for the Respondents: SBA Law ORDERS
VID 479 of 2020 BETWEEN: THE SUMMIT GROUP (AUSTRALIA) PTY LTD
Applicant
AND: OWNERS CORPORATION 1 PLAN NO PS746020J
First Respondent
OWNERS CORPORATION 2 PLAN NO PS746020J
Second Respondent
OWNERS CORPORATION 8 PLAN NO PS746020J
Third Respondent
OWNERS CORPORATION 5 PS746020J
Fourth Respondent
OWNERS CORPORATION 6 PS746020J
Fifth Respondent
ORDER MADE BY:
COLVIN J
DATE OF ORDER:
23 DECEMBER 2020
THE COURT ORDERS THAT:
1.The application is dismissed.
2.The applicant pay the respondents' costs of the application to be assessed if not agreed.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
REASONS FOR JUDGMENT
COLVIN J:
The Summit Group (Australia) Pty Ltd (Summit) seeks to install radio communications antennas and associated equipment on the common property of a building in Port Melbourne that is the subject of a strata plan. On 18 May 2020, Summit gave notice of its intention to access the common property (Notice). The respondents represent those with an interest in the…
Keep reading for free
Create a free CaseChat account to read The Summit Group (Australia) Pty Ltd v Owners Corporation 1... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] FCA 1847
- Decision Date
CaseChat Overview and Summary
The court examined the notice's adherence to the required period of notice and whether the specified dates were within the allowable timeframe. The carrier argued that the notice was valid despite including dates before the required period of notice, suggesting that the notice was not rendered invalid by this. The court considered that a notice might be considered stale if the passage of time rendered it ineffective, but no such argument was presented by the Owners. The court concluded that the delay in the dispute did not render the notice invalid, and thus, had the court been persuaded that the notice was valid, it would have granted the declaratory relief sought by the carrier.
Ultimately, the court dismissed the application because it found that the carrier's notice did not comply with the necessary statutory requirements. The court did not find the arguments presented by the carrier sufficient to overcome the statutory obligations under the Telecommunications Act. The court also noted that both parties agreed that costs should follow the event, resulting in an order that the applicant would pay the Owners' costs. The dismissal of the application and the order for costs reflect the court's determination that the carrier's application was not justified under the circumstances presented.
Orders
Orders of the court
1. The application is dismissed.
2. The applicant pay the respondents' costs of the application to be assessed if not agreed.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi