Supreme Court
New South Wales
Medium Neutral Citation: The Owners - Strata Plan No 97315 v Icon Co (NSW) Pty Ltd [2023] NSWSC 363 Hearing dates: 4 April 2023 Date of orders: 13 April 2023 Decision date: 13 April 2023 Jurisdiction: Equity - Technology and Construction List Before: Darke J Decision: Notice of Motion for rejection and variation of referee’s report is dismissed with costs.
Catchwords: BUILDING AND CONSTRUCTION – defective sunshades on façade of residential tower – referral of issues to referee – referee to determine whether builder liable and, if so, what is the proper rectification method – referee finds builder liable in respect of structurally inadequate sunshades – referee faced with competing rectification methods – referee concludes that C Bracket Solution is proper rectification method – whether referee misconstrued contract in finding that C Bracket Solution would achieve conformity with the contract – whether referee’s findings concerning visibility of brackets perverse or based upon a failure to understand evidence – held that referee made no error of principle, and his findings of fact were clearly open to him – not appropriate to exercise discretion to reject or vary the referee’s report – motion dismissed
Legislation Cited: Home Building Act 1989 (NSW), s 18B(1)
Supreme Court Rules 1970 (NSW), Pt 72 r 13
Uniform Civil Procedure Rules 2005 (NSW), rr 20.14, 20.24
Cases Cited: Bannister & Hunter Pty Ltd v Transition Resort Holdings (No 3) [2013] NSWSC 1943
Bellgrove v Eldridge (1954) 90 CLR 613
Chloride Batteries Australia Ltd v Glendale Chemical Products Pty Ltd (1988) 17 NSWLR 60
Chocolate Factory Apartments Pty Ltd v Westpoint Finance Pty Ltd [2005] NSWSC 784
Homebush Abattoir Corporation v Bermria Pty Ltd (1991) 22 NSWLR 605
Super Pty Ltd v SJP Formwork (Aust) Pty Ltd (1992) 29 NSWLR 549
Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272; [2009] HCA 8
Category: Procedural rulings Parties: The Owners – Strata Plan No 97315 (Plaintiff)
Icon Co (NSW) Pty Ltd (Defendant)Representation: Counsel:
Solicitors:
Mr F Corsaro SC (Plaintiff)
Mr D T Miller SC with Mr M J Smith (Defendant)
Project Lawyers (Plaintiff)
Minter Ellison (Defendant)
File Number(s): 2020/175890 Publication restriction: None
Judgment
Introduction
-
These proceedings were commenced in July 2020 by the plaintiff (“Owners Corporation”) against the defendant builder (“Icon”) in respect of alleged structural and non-structural defects in the building known as the Opal Tower at Olympic Park.
-
On 14 July 2022, the Court made various orders including an order pursuant to Uniform Civil Procedure Rules 2005 (“UCPR”) r 20.14 that certain matters be referred to an expert referee (Mr Steven Goldstein) for enquiry and report. The referee was required to enquire and report on questions as to what extent, if at all, Icon is liable for certain alleged defects and, to the extent Icon is liable for such defects, what is the proper rectification methodology. The alleged defects the subject of the reference constituted some of the non-structural defects alleged in the proceedings.
-
The…
Keep reading for free
Create a free CaseChat account to read The Owners - Strata Plan No 97315 v Icon Co (NSW) Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] NSWSC 363
- Decision Date
CaseChat Overview and Summary
The legal issues before the court were whether the referee misconstrued the contract in finding that the C Bracket Solution would achieve conformity with the contract and whether the referee's findings concerning the visibility of the brackets were perverse or based on a failure to understand the evidence. The court was also required to determine if it was appropriate to exercise its discretion to reject or vary the referee's report.
The court found that the referee made no error of principle in reaching his conclusions. The referee's findings of fact were clearly open to him, and there was no basis for the court to conclude that the referee's findings were perverse or that he had failed to understand the evidence. Given that the referee had considered the evidence and the contract, and had reached his conclusions on a proper basis, the court held that it was not appropriate to exercise its discretion to reject or vary the referee's report. Consequently, the motion was dismissed.
The court's final orders were to dismiss the motion brought by the Owners - Strata Plan No 97315, affirming the referee's conclusions regarding the proper rectification method for the defective sunshades and the builder's liability.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi