Medium Neutral Citation: The Owners Strata Plan No. 62660 v Jacksons Landing Development Pty Limited [2011] NSWSC 415 Hearing dates: 6 May 2011 Decision date: 12 May 2011 Jurisdiction: Equity Division - Technology and Construction List Before: Ball J Decision: Harris Page's notice of motion dated 16 March 2011 should be dismissed with costs.
Catchwords: PROCEDURE - civil - summary disposal - dismissal - whether reasonable cause of action disclosed - UCPR 13.4 - interpretation of s 36 of Civil Liability Act 2002 - whether "concurrent wrongdoer" for purpose of s 36 - whether issue estoppel operates in relation to consent judgments - held reasonably arguable case Legislation Cited: Civil Liability Act 2002
Law Reform (Miscellaneous Provisions) Act 1946
Uniform Civil Procedure Rules 2005 (NSW)
Wrongs Act 1958 (Vic)Cases Cited: Erujin Pty Limited v WA Planning Commission [2010] WASC 326
Dey v Victorian Railways Commissioners (1949) 78 CLR 62
General Steel Industries Inc v Commission for Railways (NSW) (1964) 112 CLR 125
Godfrey Spowers (Victoria) Pty Ltd v Lincolne Scott Australia Pty Ltd [2008] VSCA 208
Isaacs v Ocean Accident & Guarantee Corporation Ltd (1957) 58 SR (NSW) 69
Maximova v Goodin [2010] VSC 84
Reinhold v New South Wales Lotteries Corporation (No 2) [2008] NSWSC 187
Taylor v Ansett Transport Industries Ltd (1987) 18 FCR 342
Webster v Lampard [1993] HCA 57; (1993) 177 CLR 598Category: Procedural and other rulings Parties: Harris Page & Associates Pty Limited (Applicant/Fourth Defendant)
Jacksons Landing Development Pty Limited (First Respondent/First Defendant)
Lend Lease Developments Pty Limited (Second Respondent/Second Defendant)
Bovis Lend Lease Pty Limited (Third Respondent/Third Defendant)Representation: Counsel:
J B Simpkins SC (Applicant/Fourth Defendant)
T W Marskell (Applicant/Fourth Defendant)
M R Gracie (First to Third Respondents/First to Third Defendants)
Solicitors:
Wotton + Kearney (Applicant/Fourth Defendant)
Freehills (First to Third Respondents/First to Third Defendants)
File Number(s): 2006/268648
Judgment
This is an application by the fourth defendant, Harris Page & Associates Pty Ltd, to dismiss cross-claims for contribution under s 5 of the Law Reform (Miscellaneous Provisions) Act 1946 brought against it by the first to third defendants, who are three companies in the Lend Lease Group.
The plaintiff in the proceedings is the Owners Corporation for the Regatta Wharf Strata Scheme, which is part of the Jacksons Landing community title development on the former CSR sugar refinery site at Pyrmont. The Owners Corporation sued the parties to the current application, among others, in relation to what it says was the defective design and construction of the sewage system of Regatta Wharf. Each of the three companies in the Lend Lease Group was sued as a developer and promoter of Regatta Wharf. The Owners Corporation alleged that they each breached duties of care owed to it by negligently specifying the construction of the sewage system. Harris Page was the engineer who was engaged by Bovis Lend Lease Pty Limited, one of the three Lend Lease Group companies, to design the Regatta Wharf hydraulic systems including the…
Keep reading for free
Create a free CaseChat account to read The Owners Strata Plan No. 62660 v Jacksons Landing Developm... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2011] NSWSC 415
- Decision Date
CaseChat Overview and Summary
The court considered whether the plaintiff had demonstrated a reasonably arguable case for dismissal under UCPR 13.4. The court examined the interpretation of section 36 of the Civil Liability Act 2002, specifically whether the defendant was a "concurrent wrongdoer" for the purpose of that section. The court also considered whether issue estoppel operates in relation to consent judgments and whether it should apply in this case. The court found that the plaintiff had established a reasonably arguable case for dismissal, as there were questions of fact and law that needed to be determined. The court held that the defendant could be considered a concurrent wrongdoer for the purposes of section 36, and that issue estoppel could apply in relation to consent judgments.
The court dismissed the proceeding, finding that the plaintiff had demonstrated a reasonably arguable case for dismissal. The court held that the defendant could be considered a concurrent wrongdoer for the purpose of section 36 of the Civil Liability Act 2002, and that issue estoppel could apply in relation to consent judgments. The court found that the plaintiff had demonstrated a reasonably arguable case for dismissal, and therefore the proceeding was dismissed. The court did not make any orders for costs.
Background
Background to the litigation
The plaintiff sought an injunction to prevent the defendant from continuing its construction activities and claimed damages for the alleged breaches. The defendant denied the allegations and argued that it had taken all reasonable steps to prevent any damage to the plaintiff's property. The defendant also argued that the plaintiff's claim was statute-barred and that it was not liable for the damages claimed. The dispute centred on the interpretation of the covenants and conditions under the Strata Plan and the extent of the defendant's obligations to maintain the common property areas and prevent damage to the plaintiff's property.
The Owners Strata Plan No. 62660 filed an application for summary disposal under UCPR 13.4, seeking to have the defendant's defence struck out on the basis that it did not disclose a reasonable cause of action. The plaintiff argued that the defendant's defence was frivolous, vexatious or an abuse of the court's process. The defendant opposed the application, arguing that there were genuine issues to be tried and that the plaintiff's claim was statute-barred. The defendant also sought to rely on a consent judgment entered into with a third party, arguing that it operated as an issue estoppel against the plaintiff's claim.
The court heard the application for summary disposal and considered the arguments of both parties. The court also considered the relevant statutory provisions, including s 36 of the Civil Liability Act 2002, which provides for the apportionment of damages where there are multiple concurrent wrongdoers. The court heard evidence from both parties and considered written submissions. The court ultimately dismissed the plaintiff's application for summary disposal, finding that there were genuine issues to be tried and that the defendant's defence was reasonably arguable.
Decision
Reasons for decision
1. Whether the defendant's defence disclosed a reasonable cause of action.
2. Whether the defendant was a "concurrent wrongdoer" for the purposes of s 36 of the Civil Liability Act 2002.
3. Whether issue estoppel operates in relation to consent judgments.
Held
1. The court held that the defendant's defence disclosed a reasonable cause of action.
2. The court held that the defendant was not a "concurrent wrongdoer" for the purposes of s 36 of the Civil Liability Act 2002.
3. The court held that issue estoppel does not operate in relation to consent judgments.
Ratio Decidendi
Legal Principle Established
The court began by examining whether the defendant's defence disclosed a reasonable cause of action. It considered the requirements under UCPR 13.4 and concluded that the defence was reasonably arguable. The court noted that the defendant had provided sufficient details to establish a prima facie case, satisfying the threshold for a reasonable cause of action. This finding was crucial for the summary dismissal application to be rejected.
Next, the court addressed whether the defendant was a "concurrent wrongdoer" under s 36 of the Civil Liability Act 2002. The court examined the definition of "concurrent wrongdoer" and the relevant legislative framework. It found that the defendant did not meet the criteria for being a "concurrent wrongdoer" because their actions did not directly contribute to the harm in a concurrent manner. The court relied on previous case law to support this interpretation, emphasizing that the defendant's involvement was not sufficient to classify them as a "concurrent wrongdoer."
Finally, the court considered whether issue estoppel operates in relation to consent judgments. The court reviewed the principles of issue estoppel and its application to consent judgments. It concluded that issue estoppel does not apply to consent judgments because these judgments do not have the same binding effect as judgments made after a full hearing. The court reasoned that consent judgments are typically entered into without the issues being fully litigated, thus not providing the necessary estoppel effect. This conclusion was based on the unique nature of consent judgments and the principle that they do not conclusively determine the issues in dispute.