The Coast Protection Board v Carramatta Holdings Pty Ltd

Link copied
Case Copied 85 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Full Court)

THE COAST PROTECTION BOARD v CARRAMATTA HOLDINGS PTY LTD

[2015] SASCFC 64

Judgment of The Full Court

(The Honourable Chief Justice Kourakis, The Honourable Justice Gray and The Honourable Justice Stanley)

4 May 2015

ENVIRONMENT AND PLANNING - COURTS AND TRIBUNALS WITH ENVIRONMENT JURISDICTION - SOUTH AUSTRALIA - ENVIRONMENT, RESOURCES AND DEVELOPMENT COURT AND ITS PREDECESSORS - GENERAL MATTERS

PROCEDURE - JUDGMENTS AND ORDERS - AMENDING, VARYING AND SETTING ASIDE - VARIATION AND SETTING ASIDE OF CONSENT JUDGMENT

The first respondent owns 831 hectares of land alongside cliffs at Bosanquet Bay, the land  had been purchased from the third respondent in August 2009.  The first respondent divided the land into two components, 192 hectares of coastal land which was zoned coastal conservation under the District Council of Ceduna Development Plan, the remaining land was zoned rural living under the same Development Plan.

In April 2008 the first respondent cleared and levelled 5.5 hectares of sand dunes and spread the sand over approximately 13 hectares forming part of the coastal land. The first respondent ceased this work on intervention from the fourth respondent and the appellant. A notice to cease work was further issued under the Native Vegetation Act 1991 (SA).

In July 2008 the fourth respondent issued an enforcement notice under the Development Act 1993 (SA) to remedy the breach of that Act. The first respondent appealed that enforcement notice to the Environment, Resources and Development Court. The appellant commenced proceedings in the same court in October 2008 seeking orders against the first, second and third respondents.

The parties attended a settlement conference and agreed to a resolution of the matters in dispute in the Environment, Resources and Development Court. The member of the Court pursuant to s 16(7) of the Environment, Resources and Development Court 1993 (SA) made consent orders to give effect to the settlement reached at the conference.

A Commissioner made a consent order for the revegetation, rehabilitation and preservation of vegetation on the coastal land. Attached to that order was a report that makes reference to conditions of rehabilitation provided by the appellant.

Applications where made in January and March 2010 by the first respondent to the Native Vegetation Council, the Council forwarded the applications to the Assessment Panel in January 2011.  In April 2012 those applications were granted, for the purposes of implementing the Commissioner's orders, with certain conditions attaching.

Further reports, by the same author, were prepared outlining that the delay had significantly increased the complexity of site rehabilitation.  The previously recommended methods were now considered to have a negative impact on native fauna that had since developed.

The first and second respondents applied to the Environment, Resources and Development Court to reopen and revoke or vary the consent orders of the Court.  The Judge refused to do so.  The first and second respondents successfully appealed that decision to a single Judge of this Court.

Held (per Kourakis CJ):

1. The Environment, Resources and Development Court has…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read The Coast Protection Board v Carramatta Holdings Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2015] SASCFC 64
Decision Date

CaseChat Overview and Summary

The Coast Protection Board appealed to the Supreme Court of South Australia against an order of a single judge of that court. The single judge had allowed an appeal from the Environment, Resources and Development Court (ERD Court). The original proceedings in the ERD Court concerned development works undertaken by Carramatta Holdings Pty Ltd on land at Bosanquet Bay, near Ceduna. These works, which involved clearing and levelling sand dunes, were alleged by the Coast Protection Board to have been undertaken without necessary approvals and in breach of the Native Vegetation Act 1991 (SA). The dispute ultimately led to a consent order being made in the ERD Court. Carramatta later sought to have this consent order revoked or varied.

The central legal issue before the Supreme Court was whether the ERD Court retained jurisdiction to revoke or vary a consent order made pursuant to an agreed compromise of an enforcement action, notwithstanding a binding agreement between the parties that led to that order. This involved considering the applicability of the High Court's decision in *Harvey v Phillips* and the scope of the ERD Court's powers under section 85(17) of the Development Act 1993 (SA), which allows the court to act on its own motion.

The Supreme Court, comprising Kourakis CJ, Gray and Stanley JJ, allowed the appeal, albeit for reasons that differed from the single judge. While acknowledging the prima facie application of the principle in *Harvey v Phillips*, the Court found that the specific facts and circumstances of the matter, including the broad remedial purposes of the Development Act and the express power of the ERD Court to act on its own motion, permitted the Court to entertain Carramatta's application to revoke or vary the consent order. The Court concluded that the plain words of section 85(17) should not be read down to deny the ERD Court this power, even in the context of a consent order arising from an agreed compromise.

The Court dismissed the appeal, meaning that the matter was remitted back to the ERD Court for a rehearing of Carramatta's application to revoke or vary the consent order.

Orders

Orders of the court

Background

Background to the litigation

The matter has a long and complicated history. In reaching my conclusions I have had regard to the history. I have drawn on the detailed summary provided by the Judge of this Court in his reasons in the paragraphs that follow. Background Scott Thomas Rowlands is a director and shareholder of Carramatta. The company owns 831 hectares of land alongside cliffs at Bosanquet Bay, approximately five kilometres from Ceduna in a locality known as Ceduna Waters. In 2008, the land was owned by the third respondent Peter Norman Betts. Carramatta purchased the land from Mr Betts in August 2009. Carramatta divided the land into two components and new titles were issued. The first, the coastal land, comprised 192 hectares and abutted the cliff tops. The majority of the coastal land was zoned coastal conservation under the District Council of Ceduna Development Plan. The balance of the land, the subdivision land, was zoned rural living under the Development Plan. Carramatta intended to subdivide the subdivision land into 384 allotments. Carramatta commenced development works on the land. The Coast Protection Board claimed that by April 2008 Carramatta had cleared and levelled 5.5 hectares of sand dunes and spread the sand over approximately 13 hectares forming part of the coastal land. Upon intervention by the District Council of Ceduna, the Native Vegetation Council and the Board, Carramatta ceased these works. In May 2008, Dr Rowlands informed officers of the District Council and the Board that he was not aware that he required development approval to undertake the excavation or approval to clear native vegetation. The works undertaken in April 2008 comprised “development” within the meaning of the Development Act 1993 (SA). The works involved excavation or filling within coastal land of more than 9 cubic metres,[24] and that they required approval by the relevant authority being the District Council.[25][24] Development Regulations 2008 (SA) schedule 2 clause 5.[25] Development Act 1993 (SA) sections 32, 33. In about April 2008, the Native Vegetation Council through the agency of the Department of Water, Land and Biodiversity Conservation served Carramatta with a direction under section 31E of the Native Vegetation Act 1991 (SA) requiring the cessation of all earthworks. That section relevantly provides:(1)If an authorised officer who has been expressly authorised by the Minister to issue directions under this section has reasonable grounds on which to believe that a person has breached this Act, or is likely to breach this Act, the authorised officer may do such of the following as the officer considers necessary or appropriate in the circumstances:(a) direct the person to refrain, either for a specified period or until further notice, from the act, or course of action, that constitutes, or would constitute, the breach;(b) if, in the opinion of the authorised officer, a breach has occurred and the breach is a minor breach—direct the person to make good the breach in a manner, and within a period, specified by the authorised officer;(c) take such urgent action as is required or is, in the opinion of the authorised officer, desirable because of any situation arising from the breach or likely breach (as the case may be).…(8)A person who contravenes or fails to comply with a direction under this section is guilty of an offence.Maximum penalty: $10 000.…

Evidence

Evidence Before The Court

Decision

Reasons for decision

Either way the importance of the inclusion of the discretion given to the ERD Court to act on its own motion is in the recognition that there may be good reason for the ERD Court to review a remedial order and act even in the absence of any application by the parties to the enforcement action. That consideration, together with the purposes of the Development Act more generally to which I earlier referred, strongly militates against reading down the plain words of the power conferred by s 85(17) of the Development Act so as to deny the ERD Court a power to amend orders made pursuant to an agreed compromise of an enforcement action.Conclusion I would dismiss the appeal. This is an appeal from an order of a Judge of this Court allowing an appeal from the Environment, Resources and Development Court. Carramatta Holdings Pty Ltd sought to reopen proceedings in the Environment, Resources and Development Court with a view to revoking or varying the terms of a consent order. The Judge of that Court dismissed the application on the basis that the Court’s jurisdiction had not been enlivened because of a binding agreement between the parties that led to the consent order. The Judge relied on the High Court decision in Harvey v Phillips. [23][23] Harvey v Phillips (1956) 95 CLR 235. The Judge of this Court allowed the appeal and directed the matter be reheard in the Environment, Resources and Development Court. The Judge reasoned that, notwithstanding the underlying agreement between the parties, it was still open to the Court to exercise its jurisdiction to revoke or vary the consent order. The Judge considered that the decision of Harvey v Phillips did not apply. I have reached the conclusion, for reasons that differ from those of the Judge under appeal, that it is appropriate for the application to be reheard in the Environment, Resources and Development Court. I respectfully disagree with the Judge under appeal as to the applicability of the decision in Harvey v Phillips. However, I have reached the view that there are many impediments to the enforceability of the binding agreement such that this Court does have jurisdiction to entertain the application to revoke or vary the consent order. I consider that the principle in Harvey v Phillips has prima facie application but that the facts and circumstances of the matter dictate that the Court may entertain the application. My reasons follow. The matter has a long and complicated history. In reaching my conclusions I have had regard to the history. I have drawn on the detailed summary provided by the Judge of this Court in his reasons in the paragraphs that follow. Background Scott Thomas Rowlands is a director and shareholder of Carramatta. The company owns 831 hectares of land alongside cliffs at Bosanquet Bay, approximately five kilometres from Ceduna in a locality known as Ceduna Waters. In 2008, the land was owned by the third respondent Peter Norman Betts. Carramatta purchased the land from Mr Betts in August 2009.

Ratio Decidendi

Legal Principle Established