PLANNING & ENVIRONMENT COURT
OF QUEENSLAND
CITATION:
Tamborine Mountain Progress Association Inc v Scenic Rim Regional Council & Anor [2009] QPEC 98
PARTIES:
TAMBORINE MOUNTAIN PROGRESS ASSOCIATION INCORPORATED
Applicant
v
SCENIC RIM REGIONAL COUNCIL
First respondent
And
HYACINTH DEVELOPMENTS PTY LTD (ACN 100 627 709)
Second respondent
FILE NO/S:
3122/2008
DIVISION:
Planning and Environment
PROCEEDING:
Originating Application
ORIGINATING COURT:
Planning and Environment Court of Queensland, at Brisbane
DELIVERED ON:
20 October 2009
DELIVERED AT:
Brisbane
HEARING DATE:
7 September 2009; further written submissions received up to 24 September 2009
JUDGE:
Alan Wilson SC, DCJ
ORDER:
1. Declare that the approvals referred to in paragraph 1 of the applicant’s Amended Originating Application filed by leave on 7 September 2009 were ultra vires and have no lawful effect.
2. Declare that the plan of development which the respondent purported to approve by letter to the second respondent dated 12 March 2008 is not generally in accordance with the plan of development approved as part of the original rezoning of the site.
3. Refuse the relief sought in paragraphs 3 & 7 of the Amended Originating Application.
4. Declare that development of the site in accordance with any of the approvals referred to in paragraphs 1 & 2 above is unlawful.
5. Declare that any purported approval of building work on the site in accordance with those approvals is ultra vires and has no lawful effect.
6. Order that all work on the site other than work which has lawful approval is to cease immediately.
CATCHWORDS:
ENVIRONMENT AND PLANNING – ENVIRONMENTAL PLANNING – DEVELOPMENT CONTROL – CONSENTS, APPROVALS AND PERMITS – VALIDITY – where Respondent Council approved rezoning of land in 1990 – where terms of original approval altered by three further approvals given between 2004 and 2006 – where Developer Second Respondent acquired land in 2005 - whether three further approvals made by Respondent Council were beyond power – whether the plan of development approved by the Respondent Council in March 2008 is generally in accordance with the plan of development approved as part of the original rezoning – whether the Respondent Council had the power to approve the reconfiguration application and the subsequent change to it – whether the Appellant has caused undue delay in these proceedings – whether work on the site that does not have lawful approval should cease
Integrated Planning Act 1997 s 3.5.24, s 3.5.33, s 4.3(1), s 4.3(4), s 4.4(5), s 4.15(1), s 5.1(3), s 6.1.29(3)(b), s 6.1.35A,
Local Government (Planning and Environment) Act 1990 s 4.3(1), s 4.3(4), s 4.4(5), s415(1), s 8.10(9), s 8.10(9(A))Cases considered:
Bon Accorde Pty Ltd v Brisbane City Council (2008) 163 LGERA 288
Cameron v Mt Isa City Council [1981] QPLR 183
Stubberfield v Redland Shire Council [1995] 1 Qd R 332
Walker v Noosa Shire Council [1983] 2 Qd R 86
Warringah Shire Council v Sedevic (1987) 10 NSWLR 355
Young v Gosford City Council (2001) 120 LGERA 243COUNSEL:
M Labone for applicant
M Hinson SC and
Keep reading for free
Create a free CaseChat account to read Tamborine Mountain Progress Association Inc v Scenic Rim Reg... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2009] QPEC 98
- Decision Date
CaseChat Overview and Summary
The legal issues before the court included whether the Council's approvals were beyond its power, whether the Council had the authority to approve the reconfiguration application and the subsequent change, and whether the applicants had caused undue delay in these proceedings. The court considered the relevant statutory provisions and the terms of the original rezoning, as well as the nature and extent of the changes proposed in the subsequent approvals.
The court found that the Council's three subsequent approvals were beyond its power, as they materially altered the terms of the original approval in a way that was not permitted by the enabling legislation. The court also found that the plan of development approved by the Council in March 2008 was not generally in accordance with the original plan, as it involved significant changes that were not authorised by the original rezoning. The court further found that the Council did not have the power to approve the reconfiguration application and the subsequent change, and that the applicants had not caused undue delay in these proceedings. Accordingly, the court made the orders sought by the applicants, declaring the approvals and the subsequent plan to be unlawful, and ordering that all work on the site not in accordance with lawful approval should cease immediately.
Orders
Orders of the court
1. Declare that the approvals referred to in paragraph 1 of the applicant’s Amended Originating Application filed by leave on 7 September 2009 were ultra vires and have no lawful effect.
2. Declare that the plan of development which the respondent purported to approve by letter to the second respondent dated 12 March 2008 is not generally in accordance with the plan of development approved as part of the original rezoning of the site.
3. Refuse the relief sought in paragraphs 3 & 7 of the Amended Originating Application.
4. Declare that development of the site in accordance with any of the approvals referred to in paragraphs 1 & 2 above is unlawful.
5. Declare that any purported approval of building work on the site in accordance with those approvals is ultra vires and has no lawful effect.
6. Order that all work on the site other than work which has lawful approval is to cease immediately.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi