Swan v Santos GLNG Pty Ltd (No 2)

Link copied
Case Copied 8 min read

PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND


CITATION:

Swan v Santos GLNG Pty Ltd & Ors (No 2) [2017] QPEC 17

PARTIES:

STEPHEN JOHN SWAN
(applicant)

v

SANTOS GLNG PTY LTD ACN 131 271 648

(first respondent)

and

PAPL DOWNSTREAM PTY LTD  ACN 147 649 205
(second respondent)

and

TOTAL GLNG AUSTRALIA ACN 146 680 524

(third respondent)

and

THE CHIEF EXECUTIVE ADMINISTERING THE ENVIRONMENTAL PROTECTION ACT 1994

(fourth respondent)

FILE NO/S:

D80 of 2015

DIVISION:

Planning & Environment Court

PROCEEDING:

Application for costs

ORIGINATING COURT:

Planning & Environment Court, Maroochydore

DELIVERED ON:

24.03.2017

DELIVERED AT:

Planning & Environment Court, Maroochydore

HEARING DATE:

On the papers.  Submissions received until 16.2.17

JUDGE:

Robertson DCJ

ORDER:

The applicant pay the costs of the proceeding of the first, second and third respondents, to be assessed on the standard basis or as agreed. 

CATCHWORDS:

COSTS - PLANNING – ENVIRONMENT: where applicant wholly unsuccessful in application for orders pursuant to s 505 of the Environmental Protection Act 1994; whether applicant had any reasonable prospects of successfully obtaining such orders; where applicant had failed to properly particularise or relate evidence to alleged breaches of Environmental Authorities, whether applicant had obstructed or delayed or acted unreasonably in the proceeding.

Legislation

Environmental Protection Act 1994 ss 430, 431, 505

Sustainable Planning Act 2009 s 457

Cases

Cox & Ors v Brisbane City Council & Anor (No 2) [2014] QPELR 92

LMRM Pty Ltd v Brisbane City Council [2017] QPEC 7

Caloundra City Council v McCreath [1998] QPELR 179

COUNSEL:

R Litster QC of Counsel for the Applicant

J Horton QC and DM Favell of Counsel for the Respondent

SOLICITORS:

P&E Law for the Applicant

Carter Newell for the 1st, 2nd and 3rd Respondents

Department of Environment and Heritage Protection for the Fourth Respondent

  1. On 3 February 2017, I dismissed Mr Swan’s application for reasons published that day.  The parties have each provided written submissions on the issue of costs. 

  1. Santos seeks an order that Mr Swan pay their costs of and incidental to the proceeding to be assessed on the standard basis, if not agreed.  Mr Swan submits that there should be no order as to costs. 

  1. The court has a general discretion with respect to costs.[1] The discretion is broad, but should be exercised judicially. There is no presumption that costs should ordinarily follow the event, nor that parties have some qualified privilege against an adverse costs order. Section 457(2) sets out a non-exhaustive list of matters to which the court may have regard.[2] It is common ground that the discretion to order costs of a “proceeding” in s 457(1) extends to a proceeding such as this pursuant to s 505 of the Environmental Protection Act 1994.[3] 

    [1]Section 457 of the Sustainable Planning Act 2009 (the SPA).

    [2]Cox & Ors v Brisbane City Council & Anor (No 2) [2014] QPELR 92; LMRM Pty Ltd v Brisbane City Council [2017] QPEC 7 at [2].

    [3]See by analogy Caloundra City Council v McCreath [1998] QPELR…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Swan v Santos GLNG Pty Ltd (No 2) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] QPEC 17
Decision Date

CaseChat Overview and Summary

The case of Swan v Santos GLNG Pty Ltd (No 2) involved the applicant seeking orders under section 505 of the Environmental Protection Act 1994 against the respondents. The applicant alleged that the respondents had breached their Environmental Authorities in relation to the operation of a coal seam gas project. The application was dismissed, and the applicant's costs were ordered to be paid by the respondents.

The court was required to consider the criteria for awarding costs under section 505(12) of the Act, including whether the applicant had any reasonable prospects of successfully obtaining the orders sought and whether the applicant had obstructed or delayed or acted unreasonably in the proceeding. The court also had to determine whether the applicant had failed to properly particularise or relate evidence to the alleged breaches of the Environmental Authorities.

The court found that the applicant had no reasonable prospects of success in obtaining the orders sought and had failed to properly particularise or relate evidence to the alleged breaches of the Environmental Authorities. The court also found that the applicant had obstructed or delayed or acted unreasonably in the proceeding by engaging in vexatious conduct. The court held that these factors justified the award of costs to the respondents.

The court ordered that the applicant pay the costs of the proceeding of the first, second and third respondents, to be assessed on the standard basis or as agreed. This decision highlights the importance of properly particularising and relating evidence to the alleged breaches of Environmental Authorities and the consequences of obstructing or delaying or acting unreasonably in proceedings.

Orders

Orders of the court

The applicant pay the costs of the proceeding of the first, second and third respondents, to be assessed on the standard basis or as agreed.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.