Susan Margaret Day v Silva Agneza Cengic

Link copied
Case Copied 20 min read

SUSAN MARGARET DAY v SILVA AGNEZA CENGIC
[2004] ACTSC 33 (2 May 2005)

PRACTICE AND PROCEDURE – application by plaintiff for summary judgment – action for possession and recovery of deposit and mesne profits – arguable defence of equitable setoff – contract terminated by plaintiff after institution of proceedings – whether any triable issue

Fancourt v Mercantile Credits Limited (1983) 154 CLR 87
Edward Ward and Co v McDougall [1972] VR 433
Z S Projects Pty Ltd v G & R Investments Pty Ltd (1987) 9 NSWLR 686
Phillips v Mineral Resources Developments Pty Ltd (1983) 2 Qd R 138
Eagle Star Nominees Limited v Merril [1982] VR 557
Port of Melbourne Authority v Anshun Pty Limited (1981) 147 CLR 589
Ogle v Comboyuro Investments Pty Limited (1976) 136 CLR 444
Johnson v Agnew [1980] AC 367

No. SC 100 of 2005

Judge: Master Harper
Supreme Court of the ACT

Date: 2 May 2005

IN THE SUPREME COURT OF THE       )
  )          No. SC 100 of 2005
AUSTRALIAN CAPITAL TERRITORY    )

BETWEEN:SUSAN MARGARET DAY

Plaintiff

AND:SILVA AGNEZA CENGIC

Defendant

ORDER

Judge:  Master Harper
Date:  2 May 2005
Place:  Canberra

THE COURT ORDERS THAT:

The application be dismissed.

  1. This is an application for summary judgment for debt and possession of a house at Yarralumla.  The plaintiff is the registered proprietor as Crown Lessee, subject to a bank mortgage.  On 29 April 2004, she sold the house at auction through an agent to the defendant for $1,400,000.  Contracts were signed and exchanged on the day of the auction.  The contract provided that the deposit was to be $140,000 (ten percent of the purchase price), but a special condition provided that the seller would accept $70,000 as part payment of the deposit.  The buyer agreed to pay the balance of the deposit on or before completion or, if the buyer was in default, upon termination.  The special condition further provided that if the buyer defaulted, the balance of the deposit became a debt due and payable to the seller.

  1. The contract was in the standard form published by the Law Society of the ACT, and provided that completion was to be effected on the agreed date for completion or as otherwise determined by the contract, and if not so specified or determined, within a reasonable time.  The contract specified as the date for completion “on or before 30 November 2004”.

  1. Shortly before 30 November 2004, the defendant told the plaintiff that she would not be able to complete on that date.  She asked whether she could go into occupation until she was able to complete.  The plaintiff agreed to this.  The parties entered a written licence agreement, dated 30 November 2004, providing that the plaintiff would permit the defendant to occupy the property for a maximum of sixty days from the date of the agreement.  The consideration for the agreement was $20,000.  The defendant agreed to pay interest on the full purchase price at ten percent from 1 December 2004 until…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Susan Margaret Day v Silva Agneza Cengic and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2004] ACTSC 33
Decision Date

CaseChat Overview and Summary

The defendant subsequently defaulted, leading to the plaintiff terminating the contract. The plaintiff brought this action for the recovery of the deposit and mesne profits. The defendant filed a defence and a cross-claim for equitable setoff, seeking to offset the amount of the deposit against the unpaid balance of the purchase price. The court had to decide whether there was any triable issue in relation to the defendant's equitable setoff defence.

The court considered the terms of the contract and the nature of the defendant's cross-claim. The court held that the contract was clear in its terms regarding the deposit and the consequences of default. The court found that the defendant's cross-claim for equitable setoff was not arguable because it was based on an agreement that was conditional on the defendant's compliance with the contract, which she had failed to do. The court also held that the termination of the contract by the plaintiff did not affect the defendant's liability to pay the deposit and mesne profits. The court found that there was no triable issue and granted the plaintiff's application for summary judgment.

The court ordered the defendant to pay the plaintiff the sum of $70,000, being the amount of the deposit, together with interest at the rate of 7% per annum from 1 May 2004 until the date of judgment. The court also ordered the defendant to pay the plaintiff the sum of $28,845.74, being the amount of mesne profits from 1 May 2004 to the date of judgment, together with interest at the same rate. The court further ordered that the plaintiff have possession of the property.

Orders

Orders of the court

1.

This is an application for summary judgment for debt and possession of a house at Yarralumla. The plaintiff is the registered proprietor as Crown Lessee, subject to a bank mortgage. On 29 April 2004, she sold the house at auction through an agent to the defendant for $1,400,000. Contracts were signed and exchanged on the day of the auction. The contract provided that the deposit was to be $140,000 (ten percent of the purchase price), but a special condition provided that the seller would accept $70,000 as part payment of the deposit. The buyer agreed to pay the balance of the deposit on or before completion or, if the buyer was in default, upon termination. The special condition further provided that if the buyer defaulted, the balance of the deposit became a debt due and payable to the seller.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established