Medium Neutral Citation: Strata Plan 4834 v Zhang; Strata Plan 4834 v Huynh [2012] NSWLEC 1199 Hearing dates: 10 May 2012 and 11 July 2012 Decision date: 11 July 2012 Jurisdiction: Class 2 Before: Galwey AC Decision: (1)The application is upheld in part.
(2)Within 90 days of the date of these orders Mr Zhang is to engage a suitably qualified arborist (minimum AQF level 3), having all appropriate insurance, to remove the Norfolk Island Hibiscus to no more than 300 mm above ground level. The work is to be carried out in accordance with the WorkCover NSW Code of Practice for the Amenity Tree Industry.
(3)The applicant is to provide all access necessary for the works in (2) during reasonable hours of the day, given reasonable notice, and may supervise such access.
(4)The applicant is to serve, no later than 2 August 2012, a copy of these orders on the owners of 23 Lancelot Street and 22 Illawarra Street, Allawah.
(5)Within 90 days of the date of these orders Ms Huynh is to engage a suitably qualified arborist (minimum AQF level 3), having all appropriate insurance, to remove the Camphor Laurel to no more than 300 mm above ground level. The work is to be carried out in accordance with the WorkCover NSW Code of Practice for the Amenity Tree Industry.
(6)Ms Huynh is to provide the applicant and the owners of 23 Lancelot Street and 22 Illawarra Street, Allawah, with at least 3 working days' notice of the works in (5) and the timing of those works.
(7)The applicant and the owners of 23 Lancelot Street and 22 Illawarra Street, Allawah, are to provide all access necessary for the works in (5) during reasonable hours of the day, and may supervise such access.
(8) The exhibits are retained.
Catchwords: TREES (DISPUTES BETWEEN NEIGHBOURS): damage to property; application upheld in part; tree removal ordered; compensation dismissed. Cases Cited: Kristeller v Matis [2012] NSWLEC 1027
Strata Plan 4834 v Zhang; Strata Plan 4834 v Huynh [2012] NSWLEC 1159Category: Principal judgment Parties: Strata Plan 4834 (Applicant both matters)
Teng Zhang (20070 of 2012) (Respondents)
Lily Huynh (20071 of 2012)Representation: Jennifer Borg [Agent for Strata Plan] (Applicant both matters)
(20070 of 2012)
Teng Zhang (Respondent in person)
(20071 of 2012)
Lily Huynh (Respondent in person)
File Number(s): 20070 and 20071 of 2012
EXTEMPORE Judgment
This decision was given as an extemporaneous decision. It has been revised and edited prior to publication.
Relevant background
ACTING COMMISSIONER: These proceedings incorporate two applications made by a Strata Plan against two separate respondents, each of whom owns neighbouring property, each with a tree on their respective property. Mr Zhang has a Norfolk Island Hibiscus on his land and Ms Huynh a Camphor Laurel on hers. Both matters were initially heard at an onsite hearing on 10 May 2012, when I found that that both trees have contributed to damage of the applicant's garage walls and that removal of…
Keep reading for free
Create a free CaseChat account to read Strata Plan 4834 v Zhang; Strata Plan 4834 v Huynh and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] NSWLEC 1199
- Decision Date
CaseChat Overview and Summary
The court held that the trees were an unreasonable interference with the reasonable enjoyment of the common property by the other owners. The court found that the trees were planted in a way that interfered with the enjoyment of the common property, and that the interference was not justified by any benefit to the owners of the units. The court also held that there were appropriate orders that could be made to remedy the interference. The court ordered that both Mr Zhang and Ms Huynh engage suitably qualified arborists to remove the trees to no more than 300 mm above ground level, in accordance with the WorkCover NSW Code of Practice for the Amenity Tree Industry. The court also ordered that the applicant and the owners of two adjacent properties provide access for the removal of the trees and that notice of the removal be given to those parties.
The court's orders were that Mr Zhang and Ms Huynh engage suitably qualified arborists to remove the trees to no more than 300 mm above ground level, in accordance with the WorkCover NSW Code of Practice for the Amenity Tree Industry. The applicant and the owners of two adjacent properties were to provide access for the removal of the trees, and notice of the removal was to be given to those parties. The exhibits were to be retained.
Orders
Orders of the court
(1)The application is upheld in part.
(2)Within 90 days of the date of these orders Mr Zhang is to engage a suitably qualified arborist (minimum AQF level 3), having all appropriate insurance, to remove the Norfolk Island Hibiscus to no more than 300 mm above ground level. The work is to be carried out in accordance with the WorkCover NSW Code of Practice for the Amenity Tree Industry.
(3)The applicant is to provide all access necessary for the works in (2) during reasonable hours of the day, given reasonable notice, and may supervise such access.
(4)The applicant is to serve, no later than 2 August 2012, a copy of these orders on the owners of 23 Lancelot Street and 22 Illawarra Street, Allawah.
(5)Within 90 days of the date of these orders Ms Huynh is to engage a suitably qualified arborist (minimum AQF level 3), having all appropriate insurance, to remove the Camphor Laurel to no more than 300 mm above ground level. The work is to be carried out in accordance with the WorkCover NSW Code of Practice for the Amenity Tree Industry.
(6)Ms Huynh is to provide the applicant and the owners of 23 Lancelot Street and 22 Illawarra Street, Allawah, with at least 3 working days' notice of the works in (5) and the timing of those works.
(7)The applicant and the owners of 23 Lancelot Street and 22 Illawarra Street, Allawah, are to provide all access necessary for the works in (5) during reasonable hours of the day, and may supervise such access.
(8) The exhibits are retained.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.