DISTRICT COURT OF QUEENSLAND
CITATION: Stokes Wheeler Pty Ltd v Herriot [2003] QDC 333
PARTIES: STOKES WHEELER PTY LTD (ACN 080 554 623)
Plaintiff
and
IAIN HERRIOT
Defendant
FILE NO/S: D347/2003
DIVISION: Civil
PROCEEDING: Application
ORIGINATING COURT:
District Court, Southport
DELIVERED ON:
22 August 2003 DELIVERED AT: Southport
HEARING DATE: 28 July 2003
JUDGE: Alan Wilson SC DCJ
ORDER: Judgment for the plaintiff against the defendant in the sum of $32,947.30, and interest under clause 42.9 of the contract between the plaintiff and the defendant from 17 June 2002 to the date of this judgment.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRCTION OF PARTICULAR CONTRACT – Where defendant engaged plaintiff to undertake building work, pursuant to a building contract incorporating Australian Standards AS2124-1992 – where plaintiff issued progress claim – where superintendent appointed under contract issued a payment certificate in respect of that progress claim outside the periods provided under the contract – whether progress claim was validly issued – meaning and effect of clause 42.1 of the building contract – whether defendant should be granted a stay of execution of judgment
Cases considered:
Algons Engineering Pty Ltd v Abigroup Constructions Pty Ltd (unreported, Supreme Court of NSW, Rolfe J, 14 October 1997)
Carroll v Jensen (1900) 10 QLJ 60
Brewarrina Shire Council v Beckhaus Civil Pty Ltd [2003] NSWCA 4
Craine v Colonial Mutual Fire Insurance Co Ltd (1920) 28 CLR 305
Daysea Pty Ltd v Watpac Pty Ltd [2001] QCA 49Dey v Victorian Railways Commissioners (1949) 78 CLR 62
Foster & Ors v Northern Land Council (1998) NTSC 62Japaul Pty Ltd v St Hilliers (Qld) Pty Ltd, unreported
McMaster Pty Ltd v Redcliff City Council [2000] QSC 92 McPhee v Zarb [2002] QSC 4
Merritt Cairns Constructions Pty Ltd v Wulguru Heights Pty Ltd (1995) 2 Qd R 521
The Commonwealth v Clark (1994) 2 VR 333
Williams v Spautz (1992) 174 CLR 509
Zauner Construction Pty Ltd v No. 2 Pitt Street Pty Ltd [2001] VSC 154COUNSEL: Mr T Matthews – applicant/plaintiff
Mr S Sheaffe – respondent/defendantSOLICITORS: Dibbs Barker Gosling – applicant/plaintiff
McLaughlins – respondent/defendant
The plaintiff seeks summary judgment pursuant to UCPR r 292(1), under which judgment may be entered if the Court is satisfied that a defendant has no real prospect of successfully defending all or part of a claim, and there is no need for a trial of the claim (or part of it)[1].
[1] UCPR r 292(2); as to the nature of the test under the UCPR, see McPhee v Zarb [2002] QSC 4
The plaintiff as builder and the defendant as developer entered into a contract to renovate an existing commercial building for a contract sum of $337,236.90. The contract was in the form of Australian Standard AS2124-1992, with special conditions. Conrad & Gargett was appointed to the office of Superintendent under the contract. The plaintiff commenced work at the end of January 2002, and the works were certified for practical…
Keep reading for free
Create a free CaseChat account to read Stokes Wheeler Pty Ltd v Herriot and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2003] QDC 333
- Decision Date
CaseChat Overview and Summary
The court considered the language of the contract and found that the progress claim was validly issued as it was made in accordance with the provisions of the contract. The court also held that clause 42.1 of the building contract meant that the superintendent's authority to issue a payment certificate was limited to the periods specified in the contract, and any payment certificate issued outside those periods was invalid. However, the court found that the invalidity of the payment certificate did not affect the validity of the progress claim. The court also rejected Stokes Wheeler's argument for a stay of execution of judgment.
The court held that the progress claim was validly issued and that clause 42.1 of the building contract did not affect the validity of the progress claim. The court found that the invalidity of the payment certificate did not affect the validity of the progress claim, and therefore, the plaintiff was entitled to payment. The court also rejected the defendant's argument for a stay of execution of judgment. The court ordered that judgment be entered for the plaintiff against the defendant in the sum of $32,947.30, and interest under clause 42.9 of the contract from 17 June 2002 to the date of this judgment.
Orders
Orders of the court
Judgment for the plaintiff against the defendant in the sum of $32,947.30, and interest under clause 42.9 of the contract between the plaintiff and the defendant from 17 June 2002 to the date of this judgment.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.