SUPREME COURT OF QUEENSLAND
CITATION:
Stockland Property Management P/L v Cairns CC & Ors [2009] QCA 311
PARTIES:
STOCKLAND PROPERTY MANAGEMENT PTY LTD
ACN 000 059 398
(appellant/applicant)
v
CAIRNS CITY COUNCIL
(respondent/first respondent)
MIRVAC FUNDS LIMITED ACN 002 561 640
(respondent/second respondent)
CHIEF EXECUTIVE, DEPARTMENT OF TRANSPORT
(respondent/third respondent)
CHIEF EXECUTIVE, DEPARTMENT OF MAIN ROADS
(respondent/fourth respondent)FILE NO/S:
Appeal No 1466 of 2009
P & E Appeal No 105 of 2008DIVISION:
Court of Appeal
PROCEEDING:
Application for Leave Integrated Planning Act
ORIGINATING COURT:
Planning and Environment Court at Brisbane
DELIVERED ON:
16 October 2009
DELIVERED AT:
Brisbane
HEARING DATE:
24 July 2009
JUDGES:
McMurdo P, Keane JA and Wilson J
Separate reasons for judgment of each member of the Court, each concurring as to the orders madeORDERS:
1. Application for leave to appeal refused
2. Applicant to pay the respondents' costs of the application for leave to appeal to be assessed on the standard basis
CATCHWORDS:
ENVIRONMENT AND PLANNING – ENVIRONMENTAL PLANNING – DEVELOPMENT CONTROL – APPLICATIONS – FORM AND CONTENTS OF APPLICATION – INCLUSION OF IMPACT STATEMENTS – where second respondent developer made application to council for development permit for material change of use – where application a development application (superseded planning scheme) – where council agreed to assess application under superseded planning scheme – where Department of Main Roads ("DMR") objected to application and required council to refuse application – where DMR indicated it would reconsider its objection if developer provided additional road access to development site – where developer purported to amend its application by including Lot 301 – where Lot 301 was a State resource – where developer did not indicate use of a State resource or evidence that State satisfied pursuant to s 3.2.1(5) of the Integrated Planning Act 1997 (Qld) ("IPA") – where s 12(1) of the Integrated Planning Regulation 1998 (Qld) ("IPR") requires evidence where application involves "taking or interfering with a [State] resource" – where P & E Court held that application involved interfering with a State resource – where P & E Court held that amended application remained a "properly made application" pursuant to s 3.2.1(7) of IPA despite absence of evidence – where pursuant to s 4.1.5A of IPA the P & E Court excused developer's non-compliance in failing to provide evidence – whether the P & E Court erred in law
Integrated Planning Act 1997 (Qld), s 3.2.1, s 3.2.3, s 3.2.9,
s 3.2.15, s 4.1.5A, s 4.1.56
Integrated Planning Regulation 1998 (Qld), s 12, Sch 10Barro Group Pty Ltd v Redland Shire Council & Others [2009] QPEC 9, cited
Deputy Commissioner of Taxation v Clark (2003) 57 NSWLR 113; [2003] NSWCA 91, cited
Fawkes Pty Ltd v Gold Coast City Council [2008] 2 Qd R 1; [2007] QCA 444, considered
Lamb v Brisbane City Council [2007] 2 Qd R 538; [2007] QCA 149, cited
Rebenta Pty Ltd v Wise [2009] NSWCA 212, cited
Stockland Property…
Keep reading for free
Create a free CaseChat account to read Stockland Property Management Pty Ltd v Cairns City Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2009] QCA 311
- Decision Date
CaseChat Overview and Summary
The central legal issues before the court involved the interpretation and application of sections 3.2.1(5) and 3.2.1(7) of the IPA and section 12(1) of the IPR. The court needed to determine whether the P & E Court was correct in holding that the amended development application was a properly made application despite the absence of evidence that the State had been satisfied regarding the use of a State resource. Additionally, the court needed to decide whether the P & E Court was correct in excusing the developer's non-compliance with the requirement to provide evidence under section 4.1.5A of the IPA.
The court found that the P & E Court correctly interpreted and applied the relevant provisions of the IPA and the IPR. The court held that the application involved interfering with a State resource and that the absence of evidence did not render the application improperly made. The court also found that the P & E Court was correct in excusing the developer's non-compliance under section 4.1.5A of the IPA. The court concluded that the P & E Court did not err in law and dismissed the appeal. The court further ordered that the applicant pay the respondents' costs of the application for leave to appeal, to be assessed on the standard basis.
Orders
Orders of the court
1. Application for leave to appeal refused
2. Applicant to pay the respondents' costs of the application for leave to appeal to be assessed on the standard basis
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi