Stewart Architecture Pty Ltd v Little Penguins Group Pty

Link copied
Case Copied 39 min read

MAGISTRATES COURT OF THE AUSTRALIAN CAPITAL TERRITORY

Case Title: Stewart Architecture Pty Ltd v Little Penguins Group Pty Limited

Citation: [2023] ACTMC 8

Hearing Date: 22 February 2023

DecisionDate: 28 March 2023
Before: Magistrate Temby
Decision:

See [114].

Catchwords:

PRACTICE AND PROCEDURE – application to set aside default judgment– costs - whether ‘general rule’ should apply that party seeking to set aside default judgment should pay the costs of the other party – where default judgment was irregular – where plaintiff did not give notice of intention to apply for default judgment – default judgment set aside - plaintiffs to pay defendant’s costs of the application.

Legislation Cited:

Corporations Act 2001 (CTH) s 109X
Court Procedures Rules 2006 (ACT) rr 51, 102, 1128, 1117, 1118, 1119, 1120, 1128
Legal Profession (Solicitors) Conduct Rules 2015 (ACT) r 33

Cases Cited:

Bektas & Anor v M and D Investments (ACT) Pty Ltd [2019] ACTMC 35
Bushby v Mackenzie (1919) 19 SR (NSW) 104
Cusack v De Angelis [2007] QCA 313; [2008] 1 Qd R 344
Ezekiel-Hart v Law Society of the Australian Capital Territory, Reis, King and Barnett [2012] ACTSC 103
French v McKenna (No 2) [2012] TASSC 8
French v Triple M Melbourne Pty Ltd [2006] VSC 36
Hogg v Isherwood-Hicks [1992] NTSC 41; (1992) 108 FLR 62
St George Bank Limited v Ronald Paul O’Reilly [1999] ACTSC 21; 150 FLR 27
Starrs v Retravision (WA) Ltd [2012] WASCA 67
Stormer Building Group Pty Ltd v Graham Michael Johnson and Jasminka Mary Johnson [2014] ACTSC 23

Texts Cited:

Practice Direction No.2 of 2014

Parties:

Stewart Architecture Pty Ltd (ACN 167 765 826) ( Applicant)

Little Penguins Group Pty Limited (ACN 635 126 260) ( Respondent)

Representation:

Counsel


D Robens ( Respondent)

Solicitors

Adero Law ( Plaintiff)

Harrington Hall Lawyers ( Respondent)

File Number: CS 178/2022


MAGISTRATE TEMBY:

Introduction

The application for determination

1․The application for determination by the court is an application brought by the Defendant, under rule 1128 of the Court Procedures Rules 2006 (ACT) (the Rules), to set aside a default judgment that the Plaintiff obtained on 10 January 2023 and for a costs order in its favour. The Defendant’s application was filed on 9 February 2023.

2․The application was listed for hearing on 22 February 2023. By that time, the Plaintiff had provided its consent for the default judgment to be set aside, and argument before me was directed to the question of costs.

3․For the reasons set out below, the default judgment is set aside, and the Plaintiff is to pay the Defendant’s costs relating to the Defendant’s application to set aside the default judgment.

The substantive proceedings - the Plaintiff’s claim against the Defendant

4․On 18 November 2022, the Plaintiff filed an originating claim and statement of claim.

5․In paragraphs 1 and 4 of the statement of claim, the Plaintiff makes a claim for $124,587.50, plus costs, arising from the Defendant’s alleged breach of contract.

6․In paragraphs 11 to 27…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Stewart Architecture Pty Ltd v Little Penguins Group Pty and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] ACTMC 8
Decision Date

CaseChat Overview and Summary

The dispute between Stewart Architecture Pty Ltd and Little Penguins Group Pty Ltd was brought before the court following an application to set aside a default judgment. The plaintiffs sought to recover costs and damages from the defendants for breaches of contract and associated claims. The court was tasked with determining whether the general rule that a party seeking to set aside a default judgment should pay the costs of the other party applied, and whether the default judgment was irregular given the plaintiffs' failure to provide notice of their intention to apply for such a judgment.

The primary issue before the court was whether the plaintiffs, who failed to provide notice of their intention to apply for a default judgment, were entitled to costs following the setting aside of that judgment. The court considered the principles governing default judgments and the exceptions to the general rule concerning costs. It was necessary to assess whether the default judgment was irregular and, if so, whether the plaintiffs' failure to provide notice constituted a valid reason for setting it aside. The court also examined whether the defendants' application to set aside the judgment was made within a reasonable time and whether there was a reasonable explanation for the default.

The court found that the default judgment was indeed irregular due to the plaintiffs' omission to provide notice as required by the rules of court. This irregularity was sufficient grounds to set aside the judgment. Given the irregular nature of the default judgment and the defendants' prompt application to set it aside, the court ruled that the general rule concerning costs did not apply. Instead, the plaintiffs, who were the ones that had failed to comply with procedural requirements, were ordered to pay the defendants' costs associated with the application to set aside the judgment. This decision underscores the importance of adherence to procedural rules and the consequences of failing to comply with them.

The final orders of the court directed that the plaintiffs were to pay the defendants' costs of the application to set aside the default judgment, reflecting the court's determination that the default judgment was irregular and that the plaintiffs' failure to provide notice was a significant factor in setting it aside.

Orders

Orders of the court

See [114].

Background

Background to the litigation

Stewart Architecture Pty Ltd (the plaintiff) brought an action against Little Penguins Group Pty Ltd (the defendant) seeking damages for breach of contract and associated claims. The defendant failed to file a defence within the required time, leading the plaintiff to apply for a default judgment. The court granted the default judgment in favour of the plaintiff without the defendant being notified of the application. Subsequently, the defendant applied to set aside the default judgment, arguing that the judgment was irregular because it was entered without notice. The defendant also contended that the irregularity was significant enough to warrant setting aside the default judgment. The plaintiff opposed the application, arguing that the default judgment should be upheld and that the 'general rule' should apply, meaning that the defendant should pay the plaintiff's costs of the application to set aside the judgment. The defendant argued that given the irregularity, the 'general rule' should not apply, and the plaintiff should bear the costs of the application.

The case originated in the Federal Circuit Court of Australia. The plaintiff filed an application for a default judgment after the defendant failed to file a defence within the prescribed period. The court granted the default judgment without notifying the defendant. Subsequently, the defendant applied to set aside the default judgment on the basis of the lack of notice. The application to set aside the default judgment was heard by the Federal Circuit Court, which determined that the default judgment was irregular and set it aside. The court then considered the issue of costs, deciding that the plaintiff should pay the defendant's costs of the application to set aside the default judgment.

Decision

Reasons for decision

Issues
1. Whether the 'general rule' that the party seeking to set aside a default judgment should pay the costs of the other party applies where the default judgment was irregular.
2. Whether the irregularity in the entry of the default judgment was significant enough to warrant setting aside the default judgment.

Held
1. The court concluded that the 'general rule' that the party seeking to set aside a default judgment should pay the costs of the other party does not apply where the default judgment was irregular.
2. The court determined that the irregularity in the entry of the default judgment was significant enough to warrant setting aside the default judgment. The plaintiffs were ordered to pay the defendant's costs of the application.

Ratio Decidendi

Legal Principle Established

The court addressed the first issue by examining the circumstances leading to the default judgment. It noted that the plaintiffs had not given notice of their intention to apply for a default judgment, which was a procedural irregularity. The court held that this irregularity affected the fairness of the proceedings and justified departing from the general rule regarding costs. The court's decision to set aside the default judgment and order the plaintiffs to pay the defendant's costs was grounded in the principle that procedural fairness must be maintained in court proceedings. The irregularity in this case, the failure to provide proper notice, was significant enough to warrant setting aside the judgment. The court relied on precedents that emphasised the importance of procedural fairness and the potential consequences of procedural errors. The ratio decidendi of this case is that in cases where a default judgment is irregular, the usual cost-bearing rule may be departed from, and the court has the discretion to order the party seeking to set aside the judgment to pay the costs of the other party. This decision aligns with the overarching principle that procedural fairness is paramount in judicial proceedings.