CITATION: | Stephenson v QBCC [2017] QCAT 212 | |
PARTIES: | Michael Stephenson | |
| v | ||
| Queensland Building and Construction Commission (Respondent) | ||
APPLICATION NUMBER: | GAR312-16 | |
MATTER TYPE: | General administrative review matters | |
HEARING DATE: | On the papers | |
HEARD AT: | Brisbane | |
DECISION OF: | Member Rogers | |
DELIVERED ON: | 20 June 2017 | |
DELIVERED AT: | Brisbane | |
ORDERS MADE: | 1. The Scope of Works decision dated 6 October 2015 is a reviewable decision. 2. The time for filing an application to review the decision dated 6 October 2015 is extended to 19 December 2016. 3. The letter dated 5 October 2015 is not a reviewable decision. 4. The application to review the IRU decision of 23 November 2016 is dismissed. | |
CATCHWORDS: | PROFESSIONS AND TRADES – BUILDERS – STATUTORY INSURANCE SCHEME – Scope of Works decision – where scope of works decision made – where subsequent letter notified issues outside of claim – where applicant sought internal review of subsequent letter – whether each is a reviewable decision Queensland Building and Construction Commission Act 1991 (Qld), s 86(1)(g) Aramac Constructions Pty Ltd v Queensland Building and Construction Commission [2015] QCAT 364 Watkins v Queensland Building Services Authority [2013] QCAT 535 | |
APPEARANCES: | ||
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (‘QCAT Act’).
REASONS FOR DECISION
Mr Stephenson contracted with a builder for the construction of building works. In April 2015 he lodged a claim with the Queensland Building and Construction Commission (‘QBCC’) for defective and incomplete work under the contract. A Home Owners Warranty Assessment Report was completed on 18 August 2015 and a decision about the scope of works was made by Chris O’Shannessy of QBCC on 6 October 2015 (the ‘Scope of Works decision’). That decision included a notice advising Mr Stephenson of a right of review to this Tribunal.
Following the Scope of Works decision there was ongoing discussion between Mr Stephenson and the QBCC. Mr Stephenson sent a letter dated 12 September 2016 advising that the original Scope of Works decision would not adequately address the extensive issues at the site, referring to both the issues that had been previously identified and to various defect areas not mentioned in the scope of works, some of which had only emerged recently.
On 5 October 2016 Marie-France Wellington of the QBCC wrote back stating that the issues which had emerged recently would require a new claim and then referred to the appeal rights under the original decision. Mr Stephenson responded on 17 October seeking an internal review of the 5 October 2016 ‘decision’ by Marie-France Wellington on the ground that it did not respond to the substantive issues raised in his previous letter.
On 23 November Nancy Alexander of the QBCC Internal…
Continue reading Stephenson v QBCC
Sign in free to access the full text
- AGLC
- Stephenson v QBCC [2017] QCAT 212
- Case
- [2017] QCAT 212
- Decision Date
CaseChat Overview and Summary
The court needed to determine if the Scope of Works decision, dated 6 October 2015, and a letter, dated 5 October 2015, that notified issues outside of the claim, were each reviewable decisions. Additionally, the court had to assess the timeliness of the applicant's application to review the QBCC's internal review decision, dated 23 November 2016. The court held that the Scope of Works decision was a reviewable decision, and the time for filing an application to review this decision was extended to 19 December 2016. Conversely, the court found that the letter notifying issues outside of the claim was not a reviewable decision. Furthermore, the applicant's application to review the internal review decision was dismissed.
The court's reasoning was based on the interpretation of the relevant statutory provisions and the legal principles governing reviewable decisions. The court held that the Scope of Works decision was a reviewable decision as it was a determination of a matter relevant to a payment claim, and the letter was not a reviewable decision as it did not make a determination of a matter relevant to a payment claim. The court also found that the applicant's application to review the internal review decision was not filed within the required time frame, and therefore, the application was dismissed. The final orders were that the Scope of Works decision was a reviewable decision, the time for filing an application to review this decision was extended, the letter was not a reviewable decision, and the application to review the internal review decision was dismissed.
Orders
Orders of the court
1. The Scope of Works decision dated 6 October 2015 is a reviewable decision.
2. The time for filing an application to review the decision dated 6 October 2015 is extended to 19 December 2016.
3. The letter dated 5 October 2015 is not a reviewable decision.
4. The application to review the IRU decision of 23 November 2016 is dismissed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.