SUPREME COURT OF VICTORIA
COURT OF APPEAL
S EAPCI 2021 0031
| LUCAS STEPHENS | Applicant |
| v | |
| PAUL CAMERON | First Respondent |
| - and - | |
| JOSEPH ALESCI | Second Respondent |
---
| JUDGES: | KYROU, McLEISH and NIALL JJA |
| WHERE HELD: | MELBOURNE |
| DATE OF HEARING: | 15 June 2021 |
| DATE OF JUDGMENT: | 30 July 2021 |
| MEDIUM NEUTRAL CITATION: | [2021] VSCA 208 |
| JUDGMENT APPEALED FROM: | [2021] VCC 127 and County Court of Victoria, 11 March 2021 (Judge Woodward) |
---
BUILDING AND CONSTRUCTION – Major domestic building contracts – Contract for management of construction of two townhouses – Owners contracted with registered builder, who engaged trade contractors – Substantial amounts paid to builder for incomplete works – Whether contract a ‘domestic building contract’ for purposes of Domestic Building Contracts Act 1995 – Whether implied criterion of ‘responsibility’ limiting application of Domestic Building Contracts Act to contracts with persons responsible for works – No implied criterion – Contract for managing and arranging carrying out of construction of home a ‘domestic building contract’ – Whether applicant not a ‘builder’ for purposes of Domestic Building Contracts Act because respondents ‘owner-builders’ for purposes of Building Act 1993 – Respondents not ‘owner-builders’ – Applicant treated as builder for statutory building permit and insurance requirements – Concept of ‘owner-builder’ irrelevant to characterisation under Domestic Building Contracts Act – Leave to appeal refused – Domestic Building Contracts Act1995 ss 1, 3–5, 8, 29, 31, 132–3, Building Act 1993 24A, 25E, 135–6, 137B.
STATUTORY CONSTRUCTION – Whether s 40(2) of Domestic Building Contracts Act creates statutory entitlement to repayment of amounts retained by builder above prescribed progress payment limits – Imerva Corporation Pty Ltd v Kuna [2017] VSCA 168, considered, Cook’s Construction Pty Ltd v SFS 007.298.633 Pty Ltd (2009) 254 ALR 661, distinguished – No statutory entitlement – Whether contravention of s 40(2) founds unjust enrichment claim and forecloses defences – Contravention of s 40(2) may be vitiating factor in unjust enrichment claim, but does not foreclose all defences – Leave to appeal granted – Appeal allowed – Domestic Building Contracts Act ss 3, 13, 40, 132–3.
PRACTICE AND PROCEDURE – Interest – Whether ‘free-standing’ right to interest in action for moneys had and received – Heydon v NRMAPty Ltd[No 2] (2001) 53 NSWLR 600, Chow v Yang [2010] SASC 96, Peet Ltd v Richmond (2011) 33 VR 465, considered – Whether Domestic Building Contracts Act 1995 a ‘written instrument’ by virtue of which amount liable to be paid – Supreme Court Act 1986 ss 58, 60.
WORDS AND PHRASES – ‘contract price’ – ‘domestic building works’ – ‘domestic building contract’ – ‘major domestic building contract’ – ‘builder’ – ‘owner-builder’– ‘written instrument’.
---
| APPEARANCES: | Counsel | Solicitors |
| For the Applicant | Mr B B Carr with Ms M Clarkin | David Naidoo & Associates |
| For the Respondents | Mr S W Stuckey QC with | DSA Lawyers |
| Mr N A Andreou |
KYROU JA
McLEISH JA
NIALL JA:
In 2012, the respondents Paul Cameron and Joseph Alesci contracted with the applicant Lucas Stephens, for…
Continue reading Stephens v Cameron
Sign in free to access the full text
- AGLC
- Stephens v Cameron [2021] VSCA 208
- Case
- [2021] VSCA 208
- Decision Date
CaseChat Overview and Summary
The court was required to determine several legal issues, including whether the contract was a ‘domestic building contract’ for the purposes of the Domestic Building Contracts Act 1995. The court also had to decide if the concept of ‘responsibility’ implied a criterion limiting the application of the Act to contracts with persons responsible for the works. Additionally, the court needed to consider whether the applicants were ‘builders’ for the purposes of the Domestic Building Contracts Act, given that the respondents claimed to be owner-builders under the Building Act 1993. Finally, the court needed to assess whether a contravention of section 40(2) of the Domestic Building Contracts Act created a statutory entitlement to repayment of amounts retained by the builder above the prescribed progress payment limits and if such a contravention could foreclose all defences in a claim for unjust enrichment.
The court found that there was no implied criterion of ‘responsibility’ limiting the application of the Domestic Building Contracts Act to contracts with persons responsible for the works. Consequently, the contract for managing and arranging the carrying out of construction of the home was a ‘domestic building contract’ within the meaning of the Act. The court also held that the respondents were not owner-builders for the purposes of the Building Act 1993, and that the concept of ‘owner-builder’ was irrelevant to the characterisation under the Domestic Building Contracts Act. The court held that the applicants were builders for the purposes of the statutory building permit and insurance requirements. The court further found that there was no statutory entitlement to repayment of amounts retained by the builder above the prescribed progress payment limits. However, a contravention of section 40(2) could be a vitiating factor in a claim for unjust enrichment, but it did not foreclose all defences. Leave to appeal was refused in relation to the characterisation of the contract and the characterisation of the applicants as builders, but leave to appeal was granted in relation to the statutory entitlement to repayment of amounts retained by the builder.
The final orders of the court included the dismissal of the applicants' claims for the return of the amounts paid to the builder, the refusal of leave to appeal in relation to the characterisation of the contract and the characterisation of the applicants as builders, and the grant of leave to appeal in relation to the statutory entitlement to repayment of amounts retained by the builder.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.