Stepanoski v Aslan (No 6)

Link copied
Case Copied 7 min read

Supreme Court


New South Wales

Medium Neutral Citation: Stepanoski v Aslan (No 6) [2020] NSWSC 900
Hearing dates: 13, 24 February 2020; 7 May 2020 (Submissions)
Date of orders: 16 July 2020
Decision date: 16 July 2020
Jurisdiction:Equity
Before: Emmett AJA
Decision:

1. Direct the entry of judgment for the Plaintiffs against the Defendant in the sum of $2,698,656.28 in lieu of the judgment entered on 11 December 2018 (Stepanoski v Aslan(No 2) [2018] NSWSC 1916).

2. Order the Defendant to pay the Plaintiffs’ costs of the proceedings, save for any costs attributable to the application by the Plaintiffs for leave to reopen.

Catchwords:

DAMAGES — Quantification of damages to which the plaintiffs or defendant would be entitled — Variation of earlier judgment — Reformulation of quantum after reopening of case granted to read and tender additional evidence on damages

Legislation Cited:

Evidence Act 1995 (NSW), s 79

Cases Cited:

Gates v City Mutual Life Assurance Society Limited (1986) 160 CLR 1; [1986] HCA 3

Robinson v Harman (1848) 1 Exch 850; 154 ER 363

Stepanoski v Aslan [2018] NSWSC 1160

Stepanoski v Aslan (No 2) [2018] NSWSC 1916

Stepanoski v Aslan (No 3) [2019] NSWSC 1445

Stepanoski v Aslan (No 4) [2019] NSWSC 1859

Stepanoski v Aslan (No 5) [2020] NSWSC 139

Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272; [2009] HCA 8

Category:Consequential orders (other than Costs)
Parties: Tony Stepanoski (First Plaintiff/First Cross Defendant)
Sonja Stepanoski (Second Plaintiff/Second Cross Defendant)
Mohammad Jamal Aslan (also known as Jim Aslan) (Defendant/Cross Claimant)
Representation:

Counsel:
P Folino-Gallo (Plaintiffs/Cross Defendants)
D C Eardley (Defendant/Cross Claimant)

Solicitors:
Redenbach Lee Lawyers (Plaintiffs/ Cross Defendants)
Stewart & Associates (Defendant/Cross Claimant)
File Number(s): 2016/139580

Judgment

  1. This is the sixth judgment in the resolution of the dispute between the plaintiffs, Mr Tony Stepanoski and Mrs Sonia Stepanoski (the Owners), and the defendant, Mr Jamal Aslan (the Builder), arising out of a building contract made between the Owners and the Builder. On 30 July 2018, I published my reasons for concluding that the contract between the parties was a Lump Sum Contract rather than a Cost Plus Contract. [1] The Owners then sought the entry of judgment for damages for breach of contract by the Builder for such amounts as were not disputed by the Builder. On 11 December 2018, I directed the entry of judgment for the Owners against the Builder in the sum of $225,710.38 and reserved the further hearing of the balance of the Owners’ claim. [2] However, I subsequently ordered that enforcement of that judgment be stayed.

    1. See Stepanoski v Aslan [2018] NSWSC 1160.

    2. See Stepanoski v Aslan (No 2) [2018] NSWSC 1916.

  2. On 28 October 2019, I published my reasons for the conclusions that I had reached at that stage on the question of the assessment of damages payable by the Builder to the Owners. [3] I reserved the question of costs and gave…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Stepanoski v Aslan (No 6) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] NSWSC 900
Decision Date

CaseChat Overview and Summary

The case of Stepanoski v Aslan (No 6) was heard in the Supreme Court of Victoria. The parties involved were the plaintiffs, Stepanoski, and the defendant, Aslan. The dispute pertained to the calculation of damages awarded in a previous judgment, specifically focusing on the quantification of damages to which the plaintiffs or the defendant would be entitled. The previous judgment had been reopened to allow for the reading and tendering of additional evidence regarding damages.

The primary legal issues before the court were whether the additional evidence provided a sufficient basis for varying the original damages assessment and how this new evidence should be integrated into the calculation. The court had to determine whether the reopening of the case was warranted and if the new evidence was reliable and relevant. Furthermore, it was necessary to establish whether the new evidence warranted a reformulation of the quantum of damages.

In addressing these issues, the court considered the procedural fairness in reopening the case and the admissibility of the additional evidence. The court concluded that the new evidence was relevant and credible, justifying a variation of the earlier judgment. The court then proceeded to reformulate the quantum of damages by integrating the new evidence into the calculation. The result was a revised amount of damages awarded to the plaintiffs, reflecting the impact of the additional evidence on the overall assessment.

The final orders of the court included a variation of the earlier judgment to reflect the new quantum of damages, taking into account the additional evidence presented. The court's decision provided clarity on the procedure for reopening cases to incorporate new evidence and the standards for assessing the admissibility and impact of such evidence on the final damages award.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.