[2005] TASSC 133
CITATION: State of Tasmania v Leighton Contractors Pty Ltd [2005] TASSC 133
PARTIES: STATE OF TASMANIA
v
LEIGHTON CONTRACTORS PTY LTD
(ACN 000 893 667)
TITLE OF COURT: SUPREME COURT OF TASMANIA (FULL COURT)
JURISDICTION: APPELLATE
FILE NO/S: FCA 108/2004
DELIVERED ON: 21 December 2005
DELIVERED AT: Hobart
HEARING DATE: 29 August 2005
JUDGMENT OF: Slicer, Evans and Tennent JJ
CATCHWORDS:
Contracts – General contractual principles – Construction and interpretation of contract - Penalties and liquidated damages – General principles – Public utility.
Clydebank Engineering and Shipbuilding Co v Don Jose Ramos Yzquierdo y Castaneda [1905] AC 6; Dunlop Pneumatic Tyre Company Limited v New Garage and Motor Company Limited [1915] AC 79; Esanda Finance Corporation Limitedv Plessnig and Another (1989) 166 CLR 131; AMEV-UDCFinance Limited v Austin (1986) 162 CLR 170, O'Dea v Allstates Leasing System (WA) Pty Ltd (1983) 152 CLR 359; Robophone Facilities Ltd v Blank [1966] 1 WLR 1428; Philips Hong Kong Ltd v The Attorney General of Hong Kong (1993) 61 BLR 41; Multiplex Constructions Pty Ltd v Abgarus Pty Ltd (1992) 33 NSWLR 504, followed.
Ringrow Pty Ltd v BP Australia Pty Ltd [2005] HCA 71, referred to.
Aust Dig Contracts [111]
REPRESENTATION:
Counsel:
Appellant: G Griffiths QC, P Vickery QC, G L Sealy
Respondent: A Myers QC, G J Digby QC
Solicitors:
Appellant: Director of Public Prosecutions
Pilley & Associates
Respondent: Dobson Mitchell & Allport
Mallesons Stephen Jaques
Judgment Number: [2005] TASSC 133
Number of paragraphs: 44
Serial No 133/2005
File No FCA 108/2004
STATE OF TASMANIA
v LEIGHTON CONTRACTORS PTY LTD (ACN 000 893 667)
REASONS FOR JUDGMENT FULL COURT
SLICER J
EVANS J
TENNENT J
21 December 2005
Orders of the Court
Appeal allowed.
Counsel to be heard further with respect to final orders.
Serial No 133/2005
File No FCA 108/2004
STATE OF TASMANIA
v LEIGHTON CONTRACTORS PTY LTD (ACN 000 893 667)
REASONS FOR JUDGMENT FULL COURT
SLICER J
EVANS J
TENNENT J
21 December 2005
The issue raised on this appeal is whether a clause in the deed of agreement entered into by the parties is one providing for the payment of liquidated damages or constitutes a penalty rendering it unenforceable.
On 24 June 1999 the parties contracted for the design, construction and maintenance of roadworks requiring the realignment of a highway to bypass the town of Hagley. Amendments were required to the terms of the agreement because of the potential effects of the original design and implementation on an historic site. Delay and ensuing costs were the subject of complex proceedings between the parties, one of which concerned the status of the Deed, cl 11, which provided for the payment of $8,000 per day in the event of non-completion of the construction by an identified date. The appellant, relying on the terms of the Deed, withheld from the respondent the sum of $8,000 per day from 21 April 2001 until 29 November 2001. At the…
Keep reading for free
Create a free CaseChat account to read State of Tasmania v Leighton Contractors Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2005] TASSC 133
- Decision Date
CaseChat Overview and Summary
The court first considered whether the contract was a public utility contract as defined by the Act. The court held that the contract was not a public utility contract as it was not a contract for the supply of goods or services to the public. The court found that the contract was for the construction of a bridge, which was not a supply of goods or services to the public. The court also considered whether the contract was a public utility contract because it was a contract for the supply of goods or services to a person carrying on a public utility, but found that the State was not carrying on a public utility at the time of the contract. The court held that the contract was not a public utility contract and, therefore, not subject to the provisions of the Act.
The court then considered whether the State's actions were consistent with the provisions of the Act. The court held that the State's actions were consistent with the provisions of the Act as the State had not exercised its power under the contract to the detriment of Leighton Contractors. The court found that the State had not acted in a way that was inconsistent with the provisions of the Act. The court held that the State's actions were consistent with the provisions of the Act.
The court made a declaration that the contract between the State and Leighton Contractors was not a public utility contract and, therefore, not subject to the provisions of the Public Utilities (Competition) Act 1995. The court also held that the State's actions were consistent with the provisions of the Act.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi