Springs Golf Club Pty Ltd v Profile Golf Pty Ltd

Link copied
Case Copied 25 min read
CITATION: Springs Golf Club Pty Ltd v Profile Golf Pty Ltd [2006] NSWSC 344
HEARING DATE(S): 21 April 2006
 
JUDGMENT DATE : 

28 April 2006
JURISDICTION: Equity Division
Technology and Construction List
JUDGMENT OF: Rein AJ
DECISION: Summons dismissed.
CATCHWORDS: CONSTRUCTION CONTRACTS - Progress payments - Building and Construction Industry Security of Payment Act - Adjudicator's determination re payment schedule - Whether judicial review available - Whether valid adjudication application had been made - Whether valid payment schedule under the Act
LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999 (NSW), ss 3, 14, 17
CASES CITED: Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421; [2004] NSWCA 394
Clarence Street Pty Ltd v Isis Projects Pty Ltd [2005] NSWCA 391
Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd (2005) 21 BCL 364; [2005] NSWCA 229
Facade Innovations Pty Ltd v Timwin Constructions Pty Ltd [2005] NSWCA 197
Falgat Constructions Pty Ltd v Equity Australia Corp Pty Ltd (2005) 62 NSWLR 385; [2005] NSWCA 49
Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140
Parisienne Basket Shoes Pty Ltd v Whyte (1938) 59 CLR 369
Rothnere Pty Ltd v Quasar Constructions NSW Pty Ltd [2004] NSWSC 1151
Schokman v Xception Construction Pty Ltd [2005] NSWSC 297
Timbarra Protection Coalition Inc v Ross Mining NL (1999) 46 NSWLR 55; [1999] NSWCA 8
Transgrid v Siemens Ltd (2004) 61 NSWLR 521; [2004] NSWCA 395
PARTIES: Springs Golf Club Pty Ltd (Plaintiff)
Profile Golf Pty Ltd (First Defendant)
William Donald Mawney Taylor (Second Defendant)
FILE NUMBER(S): SC 2006/55025
COUNSEL: A Rogers (Plaintiff)
J Watson (First Defendant)
SOLICITORS: Brennan Tipple Partners (Plaintiff)
Brown Wright Stein (First Defendant)
Gadens Lawyers (Second Defendant)

- 1 -

IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY AND CONSTRUCTION LIST

Rein AJ

28 April 2006

2006/55025
Springs Golf Club Pty Ltd v Profile Golf Pty Ltd and 1 Other

JUDGMENT

1 HIS HONOUR: The Plaintiff, Springs Golf Club Pty Ltd (“Springs”) entered into a construction contract dated 2 April 2004, with the First Defendant, Profile Golf Pty Ltd (“Profile”), under which Profile was to perform work in connection with the Springs Golf Club in 2004 and 2005.

2 In July 2005, a dispute arose between Springs and Profile as to moneys properly payable to Profile by Springs. Springs and Profile, by their representatives, attended a meeting on 14 July 2005 in an attempt to resolve the dispute. Springs offered Profile a final payment of $30,310.00 to settle the dispute. Profile did not accept the offer but invited Springs to put an offer in writing, which Springs did not do.

3 On 29 July 2005, Profile, by way of a “payment claim”, sought payment of outstanding invoices for work completed under the contract totalling $155,700.96. On 9 August 2005, Springs wrote to Profile noting Profile’s letter of 29 July 2005. Springs did not specifically refer to Profile’s letter as a payment claim nor did it specifically refer to its own…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Springs Golf Club Pty Ltd v Profile Golf Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2006] NSWSC 344
Decision Date

CaseChat Overview and Summary

In Springs Golf Club Pty Ltd v Profile Golf Pty Ltd, the dispute involved a construction contract between the plaintiff, Springs Golf Club, and the defendant, Profile Golf. The plaintiff, a golf club, contracted Profile Golf to construct a clubhouse. The primary issue was whether judicial review was available to challenge an adjudicator's determination on a payment schedule under the Building and Construction Industry Security of Payment Act. This Act provides mechanisms for resolving disputes over progress payments in the construction industry.

The legal issues before the court included whether a valid adjudication application had been made, and whether the payment schedule in question was valid under the Act. The plaintiff argued that the adjudication application was flawed because it did not comply with the statutory requirements. They also contended that the payment schedule was invalid as it was not a genuine attempt to resolve the dispute. The court needed to determine the scope of judicial review available to challenge the adjudicator's determination and the validity of the payment schedule.

The court held that while the Act provides a speedy mechanism for resolving disputes over progress payments, it does not entirely exclude judicial review. The court could review the adjudicator's determination for jurisdictional error, such as procedural unfairness or an error of law. Regarding the validity of the payment schedule, the court found that the statutory requirements for a valid payment schedule were met, and therefore, the adjudicator's determination was valid. The plaintiff's application for judicial review was dismissed, and the adjudicator's determination in favour of the defendant was upheld.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established