SOLIMAN and BEYOND BUILDERS PTY LTD

Link copied
Case Copied 23 min read

JURISDICTION     :   STATE ADMINISTRATIVE TRIBUNAL

ACT: BUILDING SERVICES (COMPLAINT RESOLUTION AND ADMINISTRATION) ACT 2011 (WA)

CITATION:   SOLIMAN and BEYOND BUILDERS PTY LTD [2024] WASAT 57

MEMBER:   MR E CADE, MEMBER

HEARD:   29 MAY 2024

DELIVERED          :   7 JUNE 2024

FILE NO/S:   CC 181 of 2024

BETWEEN:   MICHAEL SOLIMAN

First Applicant

MARIAM MEGALAA

Second Applicant

AND

BEYOND BUILDERS PTY LTD

Respondent


Catchwords:

Home building work contract complaint - Home building work contract remedy order - Commencement date - Completion date - Breach of contract - Compensation for financial loss - Assessment of financial loss

Legislation:

Building Services (Complaint Resolution and Administration) Act 2011 (WA), s 5, s 5(2), s 6(3)(b), s 11(1)(c), s 17, s 38, s 41, s 41(2)(d)(i), s 43, s 43(1), s 43(2)(a), s 43(2)(b)
Building Services (Complaint Resolution and Administration) Regulations 2011 (WA), reg 6
Home Building Contracts Act 1991 (WA), s 7, s 8, s 10, s 17, s 17(a)(i), s 27, Pt 2
State Administrative Tribunal Act 2004 (WA), s 32(4), s 32(6)(c), s 39(1)(f), s 63(2)

Result:

Application allowed in part

Category:    B

Representation:

Counsel:

First Applicant : In Person
Second Applicant : No appearance
Respondent : No appearance

Solicitors:

First Applicant : N/A
Second Applicant : N/A
Respondent : N/A

Case(s) referred to in decision(s):

Alison Louise Lobbe atf Lobbe Newman Trust and Kelpie Endeavours Pty Ltd atf Testa Rossa Family Trust and Quality Builders Pty Ltd [2014] WASAT 110

Byham and Afra Constructions Pty Ltd [2014] WASAT 38

Deshmukh and Distinctive Building Services Pty Ltd [2024] WASAT 15

Lampman and Afra Constructions Pty Ltd [2014] WASAT 27

Waldron and Afra Construction Pty Ltd [2013] WASAT 207

REASONS FOR DECISION OF THE TRIBUNAL:

Introduction

  1. These proceedings concern a home building work contract (HBWC) complaint made by the applicants to the Building Commissioner pursuant to s 5(2) of the Building Services (Complaint Resolution and Administration) Act 2011 (WA) (BSCRAAct).

  2. The first and second applicants are the owners of the home the subject of the complaint (owners).  The respondent is the builder of the home (builder).

  3. The owners' complaint is that they entered a fixed price HBWC on 10 November 2021 pursuant to which the builder was to construct a new two storey home for the owners by 9 March 2024 (this being 540 days after the builder commenced the works), but on building the home to the suspended slab stage in or about October 2023 the builder suspended work on the site and as at the date of the final hearing it has not resumed the works.

  4. On 14 March 2024 the Building Services Board refused to renew the builder's building contractor registration on financial grounds.

  5. The application was listed for final hearing at the Tribunal on 29 May 2024.  At the conclusion of the final hearing the Tribunal reserved its decision.

  6. The owners at the final hearing requested the Tribunal make orders (which the Tribunal understood as a request that the Tribunal make HBWC remedy orders…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read SOLIMAN and BEYOND BUILDERS PTY LTD and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2024] WASAT 57
Decision Date

CaseChat Overview and Summary

The matter between Soliman and Beyond Builders Pty Ltd was brought before the court, which had to determine a dispute relating to a contract for home building works. The complainant, Soliman, alleged that Beyond Builders Pty Ltd had breached the terms of their contract by failing to complete the building work by the agreed date, and that Soliman had suffered financial losses as a result. Soliman sought a remedy order, compensation for the financial loss, and an assessment of the loss.

The primary legal issues the court had to resolve were whether Beyond Builders Pty Ltd had breached the contract by failing to complete the building works by the specified date, and if so, whether Soliman was entitled to compensation for the financial loss he alleged he suffered as a result of the breach. The court also needed to determine the appropriate amount of compensation, if any, that Soliman should receive.

The court found that Beyond Builders Pty Ltd did indeed breach the contract by not completing the building works by the agreed date. In its judgment, the court considered the evidence presented regarding the financial losses Soliman claimed to have suffered due to the delay. The court assessed the evidence and determined that Soliman was entitled to compensation for the financial loss caused by the breach. The court provided a detailed analysis of the factors it considered in assessing the amount of compensation, including the nature and extent of the loss, the impact on Soliman, and the evidence presented by both parties. Based on this assessment, the court ordered Beyond Builders Pty Ltd to pay Soliman compensation for the financial loss.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established