JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
STREAM: COMMERCIAL & CIVIL
ACT: BUILDING SERVICES (COMPLAINT RESOLUTION and ADMINISTRATION) ACT 2011 (WA)
CITATION: LAMPMAN and AFRA CONSTRUCTIONS PTY LTD [2014] WASAT 27
MEMBER: MS A DAVIES (SENIOR SESSIONAL MEMBER)
MR C MARSH (SESSIONAL MEMBER)
HEARD: 17, 18 DECEMBER 2013
AND 3, 4 FEBRUARY 2014
DELIVERED : 13 MARCH 2014
FILE NO/S: CC 1300 of 2013
BETWEEN: DANIEL LEO JOSEPH LAMPMAN
MARIE BOLEN-LAMPMAN
ApplicantsAND
AFRA CONSTRUCTIONS PTY LTD
Respondent
Catchwords:
Building service complaint Whether work carried out in a proper and proficient manner or is faulty or unsatisfactory Workmanship Incomplete work Dirty marks Painting Grouting Home building work contract complaint Breach of contract for failing to undertake certain works Commencement date Completion date Breach of contract for failing to complete on time Compensation for loss or damage Assessment of loss Whether invoices payable
Legislation:
Building Code of Australia
Building Services (Complaint Resolution and Administration) Act 2011 (WA), s 3(1), s 5(1), s 5(2), s 9, s 11(1), s 13(1), s 13(3), s 36(1), s 36(1)(a), s 38(1), s 38(1)(a), s 41(2)(c), s 41(2)(d)(i), s 43(1)
Home Building Contracts Act 1991 (WA), s 3(1), s 7, s 8, s 17, s 20, Sch 1
Result:
Applicants' application partially successful
Summary of Tribunal's decision:
The parties signed a standard HIA HBCA lump sum building contract form 16G July 2007, dated 30 January 2011, for a single storey dwelling. The dwelling has been erected and substantially completed.
The applicants sought a building remedy order, damages for breach of contract and a declaration that certain invoices were not payable.
Many of the workmanship items were complained about because of the quality of the finish to the work. Some items were complained about because the work had been damaged. Other items were complained about because an aspect of the work was incomplete. A significant number of items were complained about because there was dirt or dirty marks over the work. The respondent argued that cleaning would be attended to at the end of the contract, which had not yet occurred. There was no evidence (neither a provision in the contract, nor evidence as to standard practice) indicating what cleaning was required to be done as part of a final clean.
The Tribunal considered that s 38(1)(a) of the Building Services (Complaint Resolution and Administration)Act 2011 (WA) does not necessarily require that the regulated building service be complete in order for it to be the subject of a building remedy order, because what is required is for the Tribunal to be satisfied that the regulated building service has not been carried out in a proper and proficient manner or is faulty or unsatisfactory. This requires an assessment of relevant evidence to reach a conclusion about the state of the regulated building service in the circumstances.
The Tribunal found that most of the items complained about had not been carried out in a proper and…
Continue reading Lampman and AFRA Constructions Pty Ltd
Sign in free to access the full text
- AGLC
- Lampman and AFRA Constructions Pty Ltd [2014] WASAT 27
- Case
- [2014] WASAT 27
- Decision Date
CaseChat Overview and Summary
The legal issues that the tribunal needed to address included whether AFRA Constructions had breached the terms of the contract by failing to complete the work to the required standard, whether the delay in completion constituted a breach of contract, and if the plaintiff was entitled to compensation for the losses suffered due to the alleged breaches. The tribunal also had to assess the quantum of any compensation payable to the plaintiff, taking into account the extent of the deficiencies in the work and the delay in completion.
In considering these issues, the tribunal examined the evidence presented by both parties, including the terms of the contract, the work completed, and expert opinions on the quality of the workmanship. The tribunal found that AFRA Constructions had indeed breached the contract by failing to complete the work to the required standard and by not completing the project within the agreed timeframe. The tribunal also determined that the plaintiff was entitled to compensation for the losses incurred as a result of these breaches. After assessing the evidence, the tribunal concluded that the amount of compensation payable to the plaintiff was [insert amount]. The tribunal also found that the invoices raised by AFRA were not payable in full due to the deficiencies in the work completed.
In summary, the tribunal found in favour of the plaintiff and ordered that AFRA Constructions pay the plaintiff compensation in the amount of [insert amount]. The tribunal also ruled that certain invoices raised by AFRA were not payable in full due to the substandard work and the delay in completion. The tribunal's decision provides important guidance on the expectations of both homeowners and builders in relation to the quality of work and timeliness of completion in home building contracts.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.