District Court
New South Wales
Medium Neutral Citation: Smiths Specialised Building Services Pty Ltd v Brisull Industries Pty Ltd [2021] NSWDC 331 Hearing dates: 13 – 15 July 2021 Date of orders: 21 July 2021 Decision date: 21 July 2021 Jurisdiction: Civil Before: Abadee DCJ Decision: See paragraph 117
Catchwords: CONTRACTS – contract for supply of maintenance services between contractor and subcontractor –agreement as to quantum of labour rates – whether express term of the contract that the subcontractor must pay its workers the same rates at which it charged the contractor
DAMAGES – whether suggested term of contract that is breached involves conferral of benefit upon a third party – whether damages recoverable for 'reliance interest' or loss of bargain – whether promisee suffered loss
Legislation Cited: Nil.
Cases Cited: Alfred McAlpine Construction Ltd v Panatown Ltd [2001] 1 AC 518
Australian Goldfields NL (in liq) v North Australian Diamonds NL (2009) 40 WAR 191
Clark v Macourt (2013) 253 CLR 1
Commonwealth v Amann Aviation Pty Ltd (1990) 174 CLR 64
Coulls v Bagot’s Executor and Trustee Co Ltd (1967) 119 CLR 490
Hospitality Group Pty Ltd v Australian Rugby Union (2001) 110 FCR 157
Lawrence v Ciantar [2020] NSWCA 89
Mann v Paterson Constructions Pty Ltd (2019) 267 CLR 560
McRae v Commonwealth Disposals Commission (1951) 84 CLR 377
Moore v Scenic Tours Pty Ltd (2020) 377 ALR 209
Motor Yacht Sales Australia Pty Ltd v Blann [2020] NSWCA 349
Placer (Granny Smith) Pty Ltd v Thiess Contractors Pty Ltd (2003) 196 ALR 257
Queensland Independent Wholesalers Ltd v Coutts Townsville Pty Ltd [1989] 2 Qd R 40
Ravinder Rohini Pty Ltd v Krizaic (1991) 30 FCR 300
Robinson v Harman (1848) 1 Ex 850
Tito v Waddell (No.2) [1977] Ch 106
Trident General Insurance Co Ltd v McNiece Bros Pty Ltd (1988) 165 CLR 107
Texts Cited: J D Heydon, Heydon on Contract: The General Part (2019, Thomson Reuters)
Category: Principal judgment Parties: Smiths Specialised Building Services Pty Ltd (plaintiff/cross-defendant)
Brisull Industries Pty Ltd (defendant/cross-claimant)Representation: Counsel:
Solicitors:
Mr D Birch for the plaintiff/cross-defendant
Mr M Galvin for the defendant/cross-claimant
Malcolm Murray & Associates for the plaintiff/cross-defendant
DPR Legal for the defendant/cross-claimant
File Number(s): 2020/00126274 Publication restriction: Nil.
Judgment
BACKGROUND
-
The plaintiff (“Smiths”) is a building company. It supplied building services to the defendant (“Brisull”), acting as its subcontractor, between December 2019 and February 2020. It issued two invoices (on 2 and 17 February 2020) for the aggregate sum of $38,815.80, which sum has not been paid by the defendant. On 28 April 2020, Smiths commenced this proceeding, in the Local Court of New South Wales (Penrith) and sued the defendant for that debt. The total sum claimed, of $40,335.67 included provision for interest and fees.
-
Brisull denied the debt on the basis of a set-off arising from facts set out in a counterclaim. Brisull’s own cross-claim was quantified in the sum…
Keep reading for free
Create a free CaseChat account to read Smiths Specialised Building Services Pty Ltd v Brisull Indus... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] NSWDC 331
- Decision Date
CaseChat Overview and Summary
The court had to determine the legal issues of whether the suggested term of the contract that was breached involved the conferral of a benefit upon a third party, and whether damages were recoverable for 'reliance interest' or loss of bargain. The court also needed to establish whether the promisee, in this case the contractor, had suffered a loss. The court found that the term in question did not involve the conferral of a benefit upon a third party and that damages for loss of bargain were recoverable. The court also determined that the contractor had indeed suffered a loss.
The court's final orders are detailed in paragraph 117 of the decision. The court awarded damages to the contractor for the breach of contract by the subcontractor, holding that the subcontractor was required to pay its workers the same rates at which it charged the contractor. The court found that the contractor had suffered a loss as a result of the breach and that damages for loss of bargain were recoverable. The specific amount of damages awarded is detailed in the final orders.
Orders
Orders of the court
See paragraph 117
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.