JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
IN CHAMBERS
CITATION: SIAM STEEL INTERNATIONAL PLC -v- COMPASS GROUP (AUSTRALIA) PTY LTD [2014] WASC 415
CORAM: LE MIERE J
HEARD: 17 SEPTEMBER 2014
DELIVERED : 7 NOVEMBER 2014
FILE NO/S: CIV 1113 of 2014
BETWEEN: SIAM STEEL INTERNATIONAL PLC
Plaintiff
AND
COMPASS GROUP (AUSTRALIA) PTY LTD
Defendant
Catchwords:
Arbitration agreement - Whether the International Arbitration Act 1974 (Cth) applies - No notice of dispute given - Arbitration agreement is not inoperative - Proceedings stayed - Parties referred to arbitration
Legislation:
Commercial Arbitration Act 1985 (WA)
Commercial Arbitration Act 2012 (WA), s 8
Commercial International Arbitration Act 1974 (Cth), s 7
Result:
Proceedings stayed
Parties referred to arbitration
Category: B
Representation:
Counsel:
Plaintiff: Mr P G Clifford
Defendant: Mr M N Solomon SC
Solicitors:
Plaintiff: Alan Rumsley
Defendant: Norton Rose Fulbright Australia
Case(s) referred to in judgment(s):
Bakri Navigation Company Ltd v Owners of Ship 'Golden Glory' Glorious Shipping SA (1991) 217 ALR 152
Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7; (2014) 88 ALJR 447
Hi‑Fert Pty Ltd v Kiukiang Maritime Carriers Inc (1998) 155 ALR 94
Lightsource Technologies Australia Pty Ltd v Pointsec Mobile Technologies AB [2011] ACTSC 59
Mannai Investment Company Ltd v Eagle Star Assurance Co Ltd [1997] AC 749
LE MIERE J:
Overview
In May 2012 the plaintiff, Siam Steel International Plc (SSI), entered into an agreement with the defendant, Compass Group (Australia) Pty Ltd (Compass), by which SSI agreed to supply accommodation buildings at the Gateway Village in South Headland for $28,997,543. The relevant terms of the contract included the following. SSI was to provide security of 10% of the contract price by way of an approved banker's undertaking. When Compass agreed to make an advance payment to SSI, SSI was required to provide additional security in an amount equal to that advance payment. SSI was to make progress payment claims for complete shipments upon the issue of a certificate of practical completion by Compass. There were other terms relating to security by SSI and payments to SSI. SSI provided Compass with three banker's undertakings in the amount of $4,349,631.
SSI made shipments of materials under the contract. Compass reported to SSI that the first shipment contained alleged plumbing defects. As a result, SSI and Compass agreed to vary the payment terms of the contract which included Compass retaining 20% of the value of each shipment by way of retention monies. SSI has submitted progress payment claims and has been paid a total of $20,073,265. SSI says that Compass has retained the sum of $7,317,967 by way of cash retention.
SSI says that it has carried out rectification works and that it has achieved practical completion and that Compass has taken occupation of the works. Compass alleges that SSI has not completed the work and that it is in breach of the contract because of defects in the work.
By a letter in December 2013 Compass stated its intention to have recourse…
Keep reading for free
Create a free CaseChat account to read Siam Steel International PLC v Compass Group (Australia) Pty... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] WASC 415
- Decision Date
CaseChat Overview and Summary
The court had to determine whether the absence of a formal notice of dispute under the contract invalidated the arbitration agreement or if the arbitration clause remained enforceable despite the lack of a formal notice. Additionally, the court had to decide if the International Arbitration Act 1974 (Cth) applied to the arbitration agreement and if the proceedings should be stayed pending arbitration.
The court held that the objective of interpreting an arbitration agreement, like any commercial contract, is to achieve a commercially sensible result. The requirement for a formal notice of dispute under the contract was intended to ensure clarity and formality so that the recipient knew that the dispute resolution process had been triggered and the relevant rights were being exercised. The court found that the notice provided by the appellant, although not strictly in the form required by the contract, was sufficient to bring home to a reasonable reader that there was a dispute and that it was a notice under the contract. The court concluded that the arbitration agreement was not inoperative due to the lack of a formal notice of dispute and that the International Arbitration Act applied to the arbitration agreement. Consequently, the court stayed the proceedings and referred the parties to arbitration.
The court ordered the proceedings to be stayed and the parties to be referred to arbitration in accordance with the terms of the arbitration agreement. The court further ordered that each party bear its own costs of the proceedings.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
The objective of the construction of an arbitration agreement, like any commercial contract, is to achieve a commercially sensible result. In Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7; (2014) 88 ALJR 447 French CJ, Hayne, Crennan and Kiefel JJ said:[T]his Court has reaffirmed the objective approach to be adopted in determining the rights and liabilities of parties to a contract. The meaning of the terms of a commercial contract is to be determined by what a reasonable businessperson would have understood those terms to mean. That approach is not unfamiliar. As reaffirmed, it will require consideration of the language used by the parties, the surrounding circumstances known to them and the commercial purpose or objects to be secured by the contract. Appreciation of the commercial purpose or objects is facilitated by an understanding 'of the genesis of the transaction, the background, the context [and] the market in which the parties are operating'. As Arden LJ observed in Re Golden Key Ltd, unless a contrary intention is indicated, a court is entitled to approach the task of giving a commercial contract a businesslike interpretation on the assumption 'that the parties … intended to produce a commercial result'. A commercial contract is to be construed so as to avoid it 'making commercial nonsense or working commercial inconvenience' [35]. The objective approach applied under principles of commercial construction requires the use of a 'reasonable person' to determine the parties' intention. The relevant principle is the 'perspective rule' under which the reasonable person is taken to stand in the shoes of the addressee of the words at issue: Carter JW, The Construction of Commercial Contracts (2013) [11‑22]. In Mannai Investment Company Ltd v Eagle Star Assurance Co Ltd [1997] AC 749 the House of Lords considered the validity of notices to terminate a lease. Lord Steyn characterised the notices as belonging to the general class of unilateral notices served under contractual rights reserved eg notices to quit, notices to determine licences, notices to complete and notices under charter parties or contracts of afreightment. Lord Steyn said that such notices may be valid if they are sufficiently clear and unambiguous to leave a reasonable recipient in no reasonable doubt as to how and when they are intended to operate. Lord Steyn added:That test postulates that the reasonable recipient is left in no doubt that the right reserved is being exercised. It acknowledges the importance of such notices. The application of that test is principled and cannot cause any injustice to a recipient of the notice (768). The purpose of a notice of dispute under cl 48.1 is to inform the other party that there is a dispute, to identify the dispute and to inform the other party that the rights of the party giving the notice are being exercised and the time limited for referring the matter to arbitration has begun to run. A notice of dispute therefore requires some measure of formality so that the recipient knows that the dispute resolution process has been triggered and the relevant rights are being exercised and time has begun to run. That a measure of formality is required for a notice of dispute is confirmed by the terms of cl 48.2. That clause refers to the service of a notice of dispute. There must be something which can properly be described as 'a notice' and it must be served. A notice is a direct and definite statement of a thing, as distinguished from supplying materials from which the existence of such a thing may be inferred. A notice of dispute under cl 48.1 is a notice which brings home to the mind of a reasonable reader that there is a dispute between the parties and that it is a notice under cl 48.1. The notice must also adequately identify the matters the subject of that dispute . Any other construction would not be a businesslike interpretation of the clause.