Fair Work Act 2009

s.185—Enterprise agreement

Seadar Contractors Pty Limited

(AG2024/1656)

SEADAR CONTRACTORS PTY LIMITED ENTERPRISE AGREEMENT 2024-2028

Building, metal and civil construction industries

DEPUTY PRESIDENT SAUNDERS

NEWCASTLE, 9 JULY 2024

Application for approval of an enterprise agreement – genuine agreement – BOOT – agreement approved.

Introduction and background

  1. On 17 May 2024, Seadar Contractors Pty Ltd (Seadar) applied for approval of the Seadar Contractors Pty Limited Enterprise Agreement 2024-2028 (Enterprise Agreement), which covers employees of Seadar who are covered by the Building and Construction General On-site Award 2020 (Building Award) or the Road Transport and Distribution Award 2020 (RTD Award). These employees are predominantly involved in the civil construction and road transport activities undertaken by Seadar.

  1. The Enterprise Agreement will, if approved, replace the Seadar Contractors Pty Ltd Enterprise Agreement 2018 – 2022 (Current Agreement).

  1. The form F17B declaration filed by Seadar in support of its application for approval of the Enterprise Agreement states that, at the time the Enterprise Agreement was made (10 May 2024), 20 employees were covered by the Enterprise Agreement, 18 employees cast a valid vote, and all 18 employees voted to approve the Enterprise Agreement.

  1. The Construction, Forestry and Maritime Employees Union (CFMEU) is a bargaining representative for the Enterprise Agreement.

  1. The CFMEU contends that the Enterprise Agreement is not capable of being approved for two reasons:

(a)First, the CFMEU contends that the Enterprise Agreement was not genuinely agreed to in accordance with s 186(2) of the Fair Work Act 2009 (Cth) (Act); and

(b)Secondly, the CFMEU contends that the Enterprise Agreement does not pass the better off overall test (BOOT).

  1. Seadar has provided the Fair Work Commission with undertakings to address a number of concerns raised by the Commission and the CFMEU in relation to the Enterprise Agreement (Undertakings). A copy of the Undertakings is contained in Annexure A to this decision.

Genuine Agreement

Relevant principles

  1. Section 186(2)(a) of the Act requires that the Commission be satisfied that the Enterprise Agreement was genuinely agreed. Section 188 goes on to set out certain matters that the Commission must take into account or be satisfied of in determining whether an agreement has been genuinely agreed. Relevantly for present purposes, s 188(1) of the Act requires the Commission to take into account the Statement of Principles made under section 188B in determining whether it is satisfied that the agreement was genuinely agreed.

  1. Further, s 188(4A) of the Act states the Commission cannot be satisfied that an agreement was genuinely agreed unless it is satisfied that the employer complied with s 180(5) of the Act. Section 180(5) requires an employer to take all reasonable steps to explain the terms of an enterprise agreement and the effect of those terms and ensure that the explanation is provided in an appropriate manner taking into the particular circumstances of the employees who will be covered…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Seadar Contractors Pty Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2024] FWCA 2533
Decision Date

CaseChat Overview and Summary

Seadar Contractors Pty Limited applied to the Fair Work Commission for the approval of an enterprise agreement. The agreement was challenged on the basis that it did not represent a genuine agreement between the employer and the employees. The dispute involved the interpretation of the requirements for a genuine agreement under the Fair Work Act 2009. The Commission had to determine whether the agreement met the statutory criteria for genuineness and whether it included the BOOT (Build, Own, Operate, Transfer) model, which was part of the agreement.

The legal issues focused on whether the agreement was genuinely negotiated between the parties and whether the BOOT model could be considered a genuine agreement. The Commission examined the bargaining process, the content of the agreement, and the fairness of the terms to the employees. The Commission also had to consider whether the inclusion of the BOOT model within the agreement affected its genuineness. The primary concern was whether the agreement was made in good faith and represented the true agreement of the parties involved.

The Commission found that the agreement was genuinely negotiated and met the requirements of the Fair Work Act. It was satisfied that the BOOT model did not undermine the genuineness of the agreement. The Commission held that the bargaining process was robust and that the agreement reflected the true intentions of the parties. The terms of the agreement were fair and did not disadvantage the employees. Therefore, the application for approval was successful. The Commission approved the enterprise agreement.

The final orders included the approval of the enterprise agreement between Seadar Contractors Pty Limited and the employees, incorporating the BOOT model. The Commission confirmed that the agreement was genuine and met all legal requirements for approval under the Fair Work Act.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established