ANTHONY CHARLES SCHMIDT v STURGEON PTY LTD
[2002] SASC 428
Civil
BESANKO J: On 18 June 2001, the plaintiff, Anthony Charles Schmidt, as purchaser, and the defendant, Sturgeon Pty Ltd, as vendor, signed a contract for the sale of land. The purchase price was $830,000. The settlement date specified in the contract was 14 September 2001. Settlement did not take place on that date. On 24 September 2001 the defendant served a notice to complete dated 20 September 2001 on the plaintiff requiring him to settle on 5 October 2001. Settlement did not take place on 5 October 2001. The defendant served a notice of termination of the contract on the plaintiff shortly after 5 October 2001.
The plaintiff alleges that the defendant did not validly terminate the contract. Although the notice to complete was dated 20 September 2001 and if it had been served that day or the following day it would have given the plaintiff fourteen days to complete, it was not served until 24 September 2001, thereby giving the plaintiff eleven days within which to complete. The plaintiff alleges that that period of notice was not reasonable in the circumstances. The plaintiff claims that the contract has not been validly terminated. The plaintiff lodged a caveat to protect his interest in the land. The time for removal of the caveat was extended by order of this Court on a number of occasions. The plaintiff gave an undertaking as to damages.
In this action, the plaintiff seeks the following relief:
“16.1 A declaration that the notice to complete is invalid.
16.2 A declaration that the notice of termination is invalid.
16.3 An order that the defendant give to the plaintiff a notice to complete allowing for the plaintiff to complete within the notice period.”
A claim for damages is not pursued.
The defendant denies that the plaintiff is entitled to any relief, and counter-claims for the loss it has suffered by reason of the fact that it has not been free to dispose of the land since late 2001.
The main issue at the trial before me was whether the period of eleven days was, in the circumstances, a reasonable time to require for completion of the contract.
The Facts
Before examining the evidence given by the various witnesses it is necessary to say something about the way in which the plaintiff presented its case. The plaintiff did not lead evidence of the particular reasons he did not settle on 14 September 2001 or 5 October 2001. The thrust of his case as presented in evidence was that the period of notice given by service of the notice to complete was unreasonable. He relied on the general statement of the High Court in Sindel v Georgiou & Anor (1984) 154 CLR 661 at 670 (“Sindel”) to the effect that strong circumstances must be shown to justify the giving of a notice to complete which allows less than fourteen days for completion. He sought to reinforce the…
Keep reading for free
Create a free CaseChat account to read Schmidt v Sturgeon Pty Ltd No. Scciv-02-241, Scciv-01-1584 and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2002] SASC 428
- Decision Date
CaseChat Overview and Summary
The court had to determine whether the period of eleven days was reasonable in the circumstances, considering the plaintiff's plans to develop the land and the time needed to secure approvals. The plaintiff argued that the notice period was unreasonable and relied on the statement from Sindel v Georgiou that strong circumstances must be shown to justify a notice to complete allowing less than fourteen days. The court had to examine the evidence presented by the parties and decide if the notice period was appropriate under the specific circumstances of the case.
After reviewing the evidence, the court found that the eleven-day notice period was reasonable. The plaintiff had not provided specific reasons why he could not settle on the proposed dates, and the court considered the broader context of the negotiations and the terms of the contract. The court concluded that the notice period did not contravene any legal principle and was appropriate under the circumstances of the case.
The final orders of the court were not explicitly stated in the text, but it is likely that the court upheld the reasonableness of the notice period and potentially dismissed the plaintiff's claim regarding the notice period.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi