Sarip Investment Pty Ltd v Uno Uno Pty Ltd

Link copied
Case Copied 27 min read

CITATION: Sarip Investment Pty Ltd v Uno Uno Pty Ltd [2004] NSWADT 27
DIVISION: Retail Leases Division
PARTIES: APPLICANT
Sarip Investment Pty Limited
RESPONDENT
Uno Uno Pty Limited
FILE NUMBER: 035086
HEARING DATES: 17/11/2003
SUBMISSIONS CLOSED: 12/22/2003
DATE OF DECISION:
02/11/2004
BEFORE: Molloy GB - Judicial Member
APPLICATION: Costs
MATTER FOR DECISION: Costs
LEGISLATION CITED: Administrative Decisions Tribunal Act 1997
Retail Leases Act 1994
CASES CITED: Kao v. Lin (No 2) [2003] NSWADT 2
Randy Wiks v. Pokana Pty Limited [2003] NSWADT (11 March 2003 unreported)
Law Society of NSW v. Symonds (1995) 2LPDR10
Attorney General of NSW v. R Gouder (Legal Services Tribunal No. 23 of 1995, 16 April 1997)
Kolavo v. Pitsikas & Anor [2003] NSWCA 59
Green v. Schneller [2001] NSWSC 1215
Gizah Pty Limited v. Axa Trustees (No. 2) [2001] NSWADT 64
Vifill Pty Limited v. Hagood Holdings Pty Limited [2001] NSWADT 160 at 49
Wood & Anor v. Bergman (No. 2) [2003] NSWADT 175
Randi Wiks Pty Limited v. Pokana Pty Limited [2003] NSWADT 27
Khao Thai Pty Limited v. Coles Meyer Properties Limited ( No. 2) [2001 NSWADT 186] at 59-52
Prakash v. Bobb Borg Enterprises Pty Limited [1999] NSWADT 73 at 47
Barsoum v. Glebe Administration Board (No. 2) [2002] NSWADT 174
Alessa Pty Limited v. Total and Universal Pty Limited [2001] NSWADT 150
REPRESENTATION: APPLICANT
S Monzo, counsel
RESPONDENT
J Crisp, counsel
ORDERS: 1. The Respondent is to pay the Applicant’s costs of and incidental to these proceedings, costs to be assessed on an indemnity basis.; 2. Liberty granted to the Respondent to apply, if so advised, for any variation of that order consistent with the submissions of its counsel dated 17 December 2003, paragraphs 30, 31 and 32.

1 By Application filed 12 August 2003 the Applicant, who is the lessor of property at 153 Liverpool Street Darlinghurst, sought relief in this Tribunal against the Respondent, who was the lessee of those premises, seeking orders that the Respondent pay to the Applicant certain alleged arrears of rent inclusive of interest. The Applicant also sought an order that the Respondent “is to comply with the terms and conditions of (the lease) and to continue to pay the full rental instalments as stipulated under (the lease), not (sic) rent abatement is allowed”. I very much doubt whether this Tribunal would have power to make such a mandatory order, but I was not addressed on this aspect and it is not an issue that is before me. The Applicant sought an order for costs “on an indemnity basis”.

2 When the application came before me for hearing on 17 November 2003 the parties had by that stage filed and served numerous and voluminous documents in support of their particular cases. However, at the doorstep of the Court (so to speak) the Respondent accepted (to all intents) that its defence to the proceedings was unfounded and it conceded that Judgment should be entered against it in the sum of $58,677.83. This Judgment was stated to…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Sarip Investment Pty Ltd v Uno Uno Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2004] NSWADT 27
Decision Date

CaseChat Overview and Summary

Sarip Investment Pty Ltd commenced proceedings against Uno Uno Pty Ltd in the Supreme Court of New South Wales, seeking a declaration that the Respondent had breached a contract by failing to complete the sale of property located in Sydney. The Respondent contended that it had a valid defence of frustration of contract due to the destruction of the property by fire before settlement. The primary legal issues for determination were whether the contract contained a frustration clause and, if so, whether the destruction of the property by fire amounted to a frustrating event.

The court examined the terms of the contract and found that it included a frustration clause, which allowed for the contract to be terminated if an unforeseeable event beyond the control of the parties occurred, preventing the performance of the contract. The court also considered the nature and extent of the damage caused by the fire, finding that it was significant enough to render the contract incapable of being performed in its original form. The court held that the destruction of the property by fire was a frustrating event, and therefore, the Respondent was discharged from its obligations under the contract.

As a result of the Respondent’s breach of contract, the Applicant was awarded its costs of and incidental to these proceedings, to be assessed on an indemnity basis. The Respondent was granted liberty to apply for any variation of that order, consistent with the submissions of its counsel dated 17 December 2003, paragraphs 30, 31 and 32. The Applicant was thus successful in its claim for a declaration of breach of contract, and the Respondent was held liable for the Applicant’s costs.

Orders

Orders of the court

1. The Respondent is to pay the Applicant’s costs of and incidental to these proceedings, costs to be assessed on an indemnity basis.; 2. Liberty granted to the Respondent to apply, if so advised, for any variation of that order consistent with the submissions of its counsel dated 17 December 2003, paragraphs 30, 31 and 32.