SUPREME COURT OF QUEENSLAND
CITATION:
Santos Limited v Fluor Australia Pty Ltd [2016] QSC 129
PARTIES:
SANTOS LIMITED
ABN 80 007 550 923(applicant)
v
FLUOR AUSTRALIA PTY LTD
ABN 28 004 511 942(respondent)
FILE NO/S:
SC No 4848 of 2016
DIVISION:
Trial Division
PROCEEDINGS:
Originating application filed 13 May 2016 and application filed 30 May 2016
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
13 June 2016
DELIVERED AT:
Brisbane
HEARING DATE:
2 June 2016
JUDGE:
Douglas J
ORDERS:
1. Stay the principal proceedings filed 13 May 2016 pending the performance of the parties’ obligations pursuant to cl 60 of the contract between them.
2. Hear the parties further as to the form of the order and costs.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – SETTLEMENT OF DISPUTES – where Santos Limited (“Santos”) filed an application seeking an order that Fluor Australia Pty Ltd (“Fluor”) provide it with access to certain requested materials pursuant to a clause in the EPC contract between the parties – where Santos and Fluor are in a dispute about whether the requested materials must be provided pursuant to the EPC contract – where the parties have already exchanged detailed correspondence in relation to the issues in dispute – where Fluor is seeking a stay of Santos’s application pending the parties’ compliance with the dispute resolution process provided for in the EPC contract – where the parties used the contractual dispute resolution process in previous disputes and disagree about the utility of the process in the settlement of those disputes – where the parties have succeeded in compromising disputes under the EPC contract in the past – where Santos submits that the nature of the dispute makes it unlikely to be amenable to resolution by the dispute resolution process provided for in the EPC contract – whether the principal proceedings should be stayed pending the performance of the dispute resolution process provided for in the EPC contract
Admiral I Pty Ltd v Leighton Contractors Pty Ltd [2005] NSWSC 1105, distinguished
AMCI (IO) Pty Ltd v Aquila Steel Pty Ltd [2010] 2 Qd R 101; [2009] QSC 139, cited
Cable & Wireless plc v IBM UK Ltd [2002] EWHC 2059 (Comm); [2002] CLC QB 1319, applied
Dance With Mr D Ltd v Dirty Dancing Investments Pty Ltd [2009] NSWSC 332, cited
Downer EDI Mining Pty Ltd v Wambo Coal Pty Ltd [2012] QSC 290, cited
United Group Rail Services Ltd v Rail Corporation NSW (2009) 74 NSWLR 618; [2009] NSWCA 177, applied
Welker & Ors v Rinehart & Anor (No 2) [2011] NSWSC 1238, cited
Zeke Services Pty Ltd v Traffic Technologies Ltd [2005] 2 Qd R 563; [2005] QSC 135, considered
COUNSEL:
D G Clothier QC, with C A Schneider for the applicant
G A Thompson QC, with D M Turner for the respondent
SOLICITORS:
Corrs Chambers Westgarth for the applicant
Jones Day…
Keep reading for free
Create a free CaseChat account to read Santos Limited v Fluor Australia Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] QSC 129
- Decision Date
CaseChat Overview and Summary
The court found that the enforceability of the dispute resolution procedure adopted by the parties in cl 60 was undoubted. The countervailing considerations urged to justify the grant of a stay were not sufficient, in the court’s view, to make the reference to those procedures “obviously futile” or “so slight as not to justify enforcing the agreement”. The parties have succeeded in compromising such disputes in the past. The enforcement of the obligation in cl 60 will not deprive Santos of the right to have its claim determined judicially and may advance the public interest in obliging the parties to adhere to their agreement. That public interest lies in avoiding the potentially unnecessary use of court time and reducing the costs of civil litigation to both the public and litigants.
The court concluded that there is nothing to suggest that Santos will be prejudiced by being obliged to comply with its agreement. The history of previous dealings between the parties does not satisfy the court that there is no point in enforcing this agreement as it does demonstrate compromise by both parties.
The court ordered that the principal proceedings filed 13 May 2016 be stayed pending the performance of the parties’ obligations pursuant to cl 60 of the contract. The court also directed the parties to further appear to address the form of the order and costs.
Orders
Orders of the court
1. Stay the principal proceedings filed 13 May 2016 pending the performance of the parties’ obligations pursuant to cl 60 of the contract between them.
2. Hear the parties further as to the form of the order and costs.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.