SUPREME COURT OF QUEENSLAND
CITATION:
AMCI (IO) Pty Ltd v Aquila Steel Pty Ltd [2009] QSC 139
PARTIES:
AMCI (IO) PTY LTD ACN 123 253 485
(applicant)
v
AQUILA STEEL PTY LTD ACN 097 803 063
(respondent)
FILE NO/S:
1487/09
DIVISION:
Trial Division
PROCEEDING:
Civil trial
ORIGINATING COURT:
Supreme Court, Brisbane
DELIVERED ON:
4 June 2009
DELIVERED AT:
Brisbane
HEARING DATE:
15 May 2009
JUDGE:
Douglas J
ORDER:
Application dismissed.
CATCHWORDS:
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – OFFER AND ACCEPTANCE – MATTERS NOT GIVING RISE TO BINDING CONTRACT – STATEMENTS OF INTENTION, NEGOTIATIONS AND INVITATIONS TO TREAT - Where the parties are participants in an iron ore mining venture constituted by an agreement – whether the dispute resolution clause in the agreement is unenforceable as an agreement to agree and should be severed from it – whether the role of the arbitrator appointed under the clause is arbitrary and uncertain.
Commercial Arbitration Act 1985 (WA) s 22
Industrial Relations Act 1988 (Cth) s 170QK
National Labor Relations Act 1935 (US) s 8(d)Australia Pacific Airports (Melbourne) Pty Ltd v The Nuance Group (Australia) Pty Ltd [2005] VSCA 133 referred;
Carr v Brisbane City Council [1956] St R Qd 402, 411 considered;
Coal Cliff Collieries Pty Ltd v Sijehama Pty Ltd (1991) 24 NSWLR 1 considered and applied;
Con Kallergis Pty Ltd v Calshonie Pty Ltd (1988) 14 BCL 201, 211 referred;
Godecke v Kirwan (1973) 129 CLR 629 cited;
Himbleton Pty Ltd v Kumagai (NSW) Pty Ltd (1991) 29 NSWLR 44, 63 cited;
Petromec Inc v Petroleo Brasileiro SA Petrobras [2005] EWCA Civ 891; [2006] 1 Lloyds Rep 121, 153-154 at [120]-[121] considered;
Royal Botanic Gardens and Domain Trust v South Sydney City Council (2002) 76 ALJR 436, 445 at [40], 452-453 at [86]-[88] and 463 at [156] referred;
The Queensland Electricity Generating Board v New Hope Collieries Pty Ltd [1989] 1 Lloyd’s Rep. 205, 210 cited;
United Group Rail Services Pty Ltd v Rail Corporation NSW [2008] NSWSC 1364 cited;
Upper Hunter County District Council v Australian Chilling and Freezing Co Ltd (1968) 118 CLR 429, 436-437 cited;
Walford v Miles [1992] 2 AC 128, 138 referred;
Wellington City Council v Body Corporate 51702 (Wellington) [2002] 3 NZLR 486, 495-496 discussed;
Xstrata Queensland Ltd v Santos Ltd [2005] QSC 323 referred.COUNSEL:
W Sofronoff QC and A Pomerenke for the applicant
AJ Myers QC and MG Lundberg for the respondent
SOLICITORS:
Allens Arthur Robinson for the applicant
Mallesons Stephen Jaques for the respondent
Douglas J: The applicant, AMCI (IO) Pty Ltd, and the respondent, Aquila Steel Pty Ltd, are participants in an iron ore mining joint venture in Western Australia constituted by an agreement made on 14 February 2005. The certainty of the dispute resolution clause in that agreement is itself in dispute, AMCI seeking a declaration that it is unenforceable as a whole or that certain parts of it are unenforceable and should be severed from the agreement. The first submission for…
Keep reading for free
Create a free CaseChat account to read AMCI (IO) Pty Ltd v Aquila Steel Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2009] QSC 139
- Decision Date
CaseChat Overview and Summary
The court began by examining the nature of the contractual terms in question. It was necessary to determine whether the statements in the agreement amounted to a binding contract or were merely preliminary negotiations or invitations to treat. The court found that the clause, while it appeared to be an agreement to agree, was in fact a binding commitment to resolve disputes through arbitration. The court concluded that the clause was enforceable as it was not an agreement to agree but rather a clear directive to resolve disputes through arbitration, and it was not arbitrary or uncertain in its terms.
The court further examined the role of the arbitrator and found it to be well-defined within the clause. The court held that the arbitrator's role was not arbitrary or uncertain, as the clause provided specific guidelines for the appointment and conduct of the arbitrator. The court ultimately dismissed the application, affirming that the dispute resolution clause was valid and enforceable as part of the agreement between the parties.
The court's decision concluded that the dispute resolution clause was not an agreement to agree and was enforceable, and that the role of the arbitrator was clearly defined. The application by the parties to sever the clause or challenge the arbitrator's role was dismissed, leaving the clause intact and valid within the agreement.
Orders
Orders of the court
Application dismissed.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi