Salisbury Mausoleum P/L v Both

Link copied
Case Copied 30 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Magistrates Appeals: Civil)

SALISBURY MAUSOLEUM P/L v BOTH

[2007] SASC 152

Judgment of The Honourable Justice Debelle

4 May 2007

CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - CONSTRUCTION AND INTERPRETATION OF CONTRACTS

Contract to make model of mausoleum – plaintiff deferred project for period of time – plaintiff later asks that project recommence - whether plaintiff repudiated contract – whether defendant terminated contract – whether later negotiations varied existing contract or created a new contract – appeal allowed.

Automatic Fire Sprinklers Pty Ltd v Watson (1946) 72 CLR 437; British and Beningtons Ltd v North Western Cachar Tea Co Ltd [1923] AC 48; Brogden v Metropolitan Railway Co (1877) 2 App Cas 666; Carr v J A Berriman Pty Ltd (1953) 89 CLR 327; Empirnall Holdings Pty Ltd v Machon Paull Partners Pty Ltd (1988) 14 NSWLR 523; Heyman v Darwins, Ltd [1942] AC 356; Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623; Murphy v Zamonex Pty Ltd (1993) 31 NSWLR 439; Progressive Mailing House Pty Ltd v Tabali Pty Ltd (1985) 157 CLR 17; Ross T Smyth & Co Ltd v T D Bailey Son & Co [1940] 3 All ER 60; Shevill v Builders Licensing Board (1982) 149 CLR 620; Sunbird Plaza Pty Ltd v Maloney (1988) 166 CLR 245; Universal Cargo Carriers Corporation v Citati [1957] 2 QB 401, applied.

SALISBURY MAUSOLEUM P/L v BOTH
[2007] SASC 152

Magistrates Appeals: Civil

  1. DEBELLE J.        The plaintiff carries on the business of constructing mausoleums.  It has constructed them in other States in Australia.  In 2001, it entered into an arrangement with the City of Salisbury to construct a mausoleum in the area of the Council and on land owned by the Council. 

  2. The plaintiff’s architect was Mr J Galluccio.  In order to assist the promotion of sales of crypts and niches in the mausoleum, the plaintiff decided to have a model made of the proposed mausoleum.  The plaintiff entered into a contract with the defendant, a model maker.  The defendant’s work premises were close to Galluccio’s office.  Galluccio often directly dealt with the defendant on behalf of the plaintiff.  In that respect, he acted as the plaintiff’s agent.   

    A Contract to Make a Model

  3. As the magistrate found, the terms of the contract were set out in the defendant’s quotation for the work dated 17 May 2001.  The essential terms of the contract were:

    ·that the defendant would construct a model of the proposed mausoleum to a scale of 1:87.

    ·the model was to be constructed according to drawings and information supplied by Galluccio.

    ·that the work was to be completed in the first week of July 2001.

    ·the total cost of the model was to be $14,000.

    The plaintiff accepted the quotation and completion date by an email dated 18 May 2001.  The defendant began the project.  He prepared drawings of the model.  The model was…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Salisbury Mausoleum P/L v Both and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2007] SASC 152
Decision Date

CaseChat Overview and Summary

In the matter of Salisbury Mausoleum P/L v Both, the plaintiff sought to enforce a contract with the defendant for the construction of a model of a mausoleum. The defendant had failed to complete the project by the agreed date and had subsequently sought damages for the plaintiff's alleged repudiation of the contract. The case was brought to the court for determination of the legal issues surrounding the repudiation and termination of the contract. The primary legal issues that the court had to address were whether the plaintiff had repudiated the contract and whether the defendant had terminated the contract. Additionally, the court had to determine whether the subsequent negotiations between the parties had varied the existing contract or created a new one.

The court held that the plaintiff had not repudiated the contract as it had merely deferred the project due to financial issues and had always intended to proceed with it. The court also found that the defendant had not terminated the contract as he had only asserted that the plaintiff had repudiated or terminated the contract. The court held that the contract made in May 2001 remained on foot unless the defendant terminated it. The court further held that the subsequent negotiations between the parties did not result in a new contract but only varied the existing contract. The court held that the plaintiff was liable to pay the defendant $8,800 in damages for the breach of contract.

The court allowed the appeal and set aside the magistrate's decision. The court held that the plaintiff had not repudiated the contract and that the defendant had not terminated the contract. The court held that the subsequent negotiations between the parties had only varied the existing contract. The court ordered that the plaintiff pay the defendant $8,800 in damages for the breach of contract.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

DEBELLE J
It seems that Galluccio arranged a meeting to see the defendant on 7 June 2002 but the defendant cancelled that meeting. Another meeting was arranged for 11 June but it did not proceed because the defendant could not be contacted. A meeting was rescheduled for 18 June. There is no evidence whether the meeting was held. Other attempts at meetings were made in the latter part of the year. Ultimately, the defendant agreed in November 2002 to complete the model by 18 December. The agreement is evidenced by a hand-written alteration to the letter of 6 May. The alteration changes the completion date to 18 December 2002 and is initialled by the defendant. The defendant failed to complete the model by that date. He did not provide the plaintiff with a model. The plaintiff commissioned another model maker to make the model. The Magistrate’s Decision The magistrate found that the plaintiff had repudiated the contract made in May 2001. He did not, however, find that the defendant had terminated the contract. He simply held that the lengthy pause between August 2001 and early 2002 “amounts to repudiation by the plaintiff, and the parties are forced to start again”. He then found that the emails exchanged between the parties in March, April and May 2002 did not result in a new contract. He held that, as the plaintiff had repudiated the initial contract, the defendant was entitled to $8,800 damages. He dismissed the plaintiff’s claim. For the reasons which follow, the magistrate erred in holding that the plaintiff had repudiated the contract and that was enough to conclude its contract with the defendants. The plaintiff’s clear evidence was that it always intended to proceed with the project. It only deferred performance until it resolved the financial issues. If the defendant believed that the plaintiff had repudiated the contract, it was necessary for him to decide whether he terminate it. However, he did not do so. The initial contract, therefore, remained on foot.Did Defendant Terminate the Contract? A party is entitled to terminate a contract if the other party repudiates it. However, neither breach nor repudiation by one contracting party of itself terminates the contract and it is necessary that the other party elect to treat it as discharged: Heyman v Darwins, Ltd [1942] AC 356; Automatic Fire Sprinklers Pty Ltd v Watson (1946) 72 CLR 435; Carr v J A Berriman Pty Ltd (1953) 89 CLR 327; Murphy v Zamonex Pty Ltd (1993) 31 NSWLR 439 at 454. As a general rule, one party remains bound to perform its obligations notwithstanding breach by the other unless he terminates the contract for the breach or repudiation by the other party. The contract made in May 2001 therefore remained on foot unless the defendant terminated it. I turn to consider whether the defendant terminated that contract. In his letter of 24 August 2001, the defendant referred to “a repudiation and termination of the agreement”. That expression appears in this context in that letter.I have enclosed an account for work to date. It is due for immediate payment. I consider this amount to be less than what I may otherwise claim but in goodwill gesture will accept it as full payment if the terms are complied with. If payment is not received within 7 days I reserve the right to claim to the fullest extent of my legal rights any amounts in excess of this amount due to what is a repudiation and termination of the agreement. I also advise that should full settlement not be made or other terms of settlement agreed by me in writing you will be liable for further costs. I regret that the Project has stalled and would welcome the opportunity to complete it if all matters can be resolved. When read in its context, it is apparent that the defendant is not terminating the contract. Instead, he is asserting that the plaintiff has repudiated or terminated the contract. As already mentioned, the plaintiff had not repudiated the contract. The plaintiff’s intention was merely to postpone the work until its financial difficulties had been resolved. Repudiation is a serious matter and is not to be lightly found or inferred: Ross T Smyth & Co Ltd v T D Bailey Son & Co [1940] 3 All ER 60 at 71; Shevill v Builders Licensing Board (1982) 149 CLR 620, per Wilson J at 633; Progressive Mailing House Pty Ltd v Tabali Pty Ltd (1985) 157 CLR 17, per Mason J at 32; Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623 per Brennan J at 643 and per Deane and Dawson JJ at 657. A party will not establish that the other has repudiated the contract unless he proves that the other party has “become wholly and finally disabled” from performing his contractual obligations: British and Beningtons Ltd v North Western Cachar Tea Co Ltd [1923] AC 48 per Lord Sumner at 72; Universal Cargo Carriers Corporation v Citati [1957] 2 QB 401 per Devlin J at 450; Sunbird Plaza Pty Ltd v Maloney (1988) 166 CLR 245, per Mason CJ at 262, with whom Deane, Dawson and Toohey JJ agreed, and per Gaudron J at 280. The plaintiff had not become disabled from performing its obligations. The magistrate erred in finding that the plaintiff had repudiated the contract.

Ratio Decidendi

Legal Principle Established

Established by: DEBELLE J

Full text does not contain this section.