Medium Neutral Citation: SafeWork NSW v SLD Projects Pty Ltd [2022] NSWDC 574 Hearing dates: 14 November 2022 Date of orders: 18 November 2022 Decision date: 18 November 2022 Jurisdiction: Criminal Before: Scotting DCJ Decision: 1 SLD Projects Pty Ltd is convicted.
2 The appropriate fine is one of $240,000 which will be reduced by 25% to reflect the plea of guilty.
3 I impose a fine of $180,000.
4 The offender is to pay the prosecutor’s costs of the proceedings, as agreed or assessed.
5 I order pursuant to s 122(2) Fines Act 1996 that 50% of the fine is to be paid to the prosecutor.
Catchwords: CRIMINAL LAW – prosecution – work health and safety – duty of persons undertaking business – duty of employers – risk of death or serious injury – injury to worker
SENTENCING - objective seriousness - deterrence - aggravating factors - mitigating factors – penalty
SENTENCING PRINCIPLES - no record of previous convictions - good prospects of rehabilitation - remorse - plea of guilty - assistance to law enforcement authorities
Legislation Cited: Cases Cited: Attorney-General (NSW) v Ceerose Pty Ltd [2019] NSWCCA 35
Attorney-General (NSW) v DSF Constructions Pty Ltd [2019] NSWCCA 33
Attorney-General (NSW) v Macmahon Mining Services Pty Ltd [2019] NSWCCA 8
Bulga Underground Operations Pty Ltd v Nash [2016] NSWCCA 37
Fines Act 1996
R v Borkowski (2009) 195 A Crim R 1
R v Thomson & Houlton (2000) 49 NSWLR 383
R v Youkhana [2004] NSWCCA 412
SafeWork NSW v Grandcity Constructions Pty Ltd [2018] NSWDC 398
Category: Sentence Parties: SafeWork NSW (Prosecutor)
SLD Projects Pty Ltd (Defendant)Representation: Counsel:
Solicitors:
N Read (Prosecutor)
E James (Defendant)
Legal, Department of Customer Service (Prosecutor)
Sparke Helmore Lawyers (Defendant)
File Number(s): 2021/256543 Publication restriction: None
JUDGMENT
Introduction
-
SLD Projects Pty Ltd (the offender) appears for sentence after it pleaded guilty to an offence pursuant to s 32 Work Health and Safety Act 2011 (the Act) in that it failed to comply with the health and safety duty it owed pursuant to s 19(1) of the Act and thereby exposed Mark Prendergast to a risk of death or serious injury.
-
The maximum penalty for the offence is $1.5 million.
Facts
-
The parties tendered an Agreed Statement of Facts that can be summarised as follows.
Background
-
The offender conducted a business involving provision of home building construction services, including new home builds and alterations and extensions to existing homes.
-
Simon La Delfa was the offender’s sole director and sole employee. Mr La Delfa managed the business and was personally involved in work undertaken by the offender. He worked alongside and supervised workers engaged by the offender.
-
The offender was engaged on a project to renovate and extend a residential home (the project) in Forestville NSW (the site). The offender was the principal contractor for the project.
-
On or around 23 July 2019 the offender engaged Labour Revolution…
Keep reading for free
Create a free CaseChat account to read SafeWork NSW v SLD Projects Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] NSWDC 574
- Decision Date
CaseChat Overview and Summary
The court had to determine whether the company failed to meet its duty of care and if the prosecution proved the requisite intent or recklessness. Additionally, the court needed to assess the objective seriousness of the breach, considering factors such as the risk of death or serious injury, the extent of the harm caused, and the company's history of compliance with health and safety regulations. The court also evaluated various sentencing principles, including the offender's criminal history, prospects of rehabilitation, expression of remorse, and the assistance provided to law enforcement.
The court found that SLD Projects Pty Ltd was guilty of the charges, highlighting the significant risk to workers' safety posed by the company's actions. Despite the company having no previous convictions, the court considered the severity of the breach and the serious injury caused. The court acknowledged the company's cooperation with authorities and its plea of guilty as mitigating factors. After weighing all relevant considerations, the court imposed a fine of $180,000, reduced from $240,000 due to the guilty plea, and ordered the company to pay the prosecutor's costs and half of the fine to be directed to the prosecutor.
Orders
Orders of the court
1 SLD Projects Pty Ltd is convicted.
2 The appropriate fine is one of $240,000 which will be reduced by 25% to reflect the plea of guilty.
3 I impose a fine of $180,000.
4 The offender is to pay the prosecutor’s costs of the proceedings, as agreed or assessed.
5 I order pursuant to s 122(2) Fines Act 1996 that 50% of the fine is to be paid to the prosecutor.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.