| CITATION: | Rosa v Hunterland & Anor (No 2) [2015] QCATA 187 |
| PARTIES: | John Rosa (Applicant/Appellant) |
| v | |
| Vicky Hunterland Jane Hunterland (Respondents) |
| APPLICATION NUMBER: | APL119-14 |
| MATTER TYPE: | Appeals |
| HEARING DATE: | 11 June 2015 |
| HEARD AT: | Brisbane |
| DECISION OF: | Senior Member Stilgoe OAM Member Steven Holzberger |
| DELIVERED ON: | 2 September 2015 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. The appeal is allowed. 2. The decision of the Tribunal dated 29 November 2013 dismissing John Rosa’s counterclaim is set aside. 3. The matter be returned to the Tribunal for reconsideration of the counterclaim without the hearing of additional evidence. |
| CATCHWORDS: | APPEAL - DOMESTIC BUILDING DISPUTE – fixed price contract– where the builder’s claims for additional amounts for variations and provisional cost items were dismissed – whether findings were an error of law or fact Queensland Civil and Administrative Tribunal Act 2009 (Qld) s 3, s 6, s 143 Ebner v Official Trustee in Bankruptcy (2000) 205 CLR 337. |
APPEARANCES and REPRESENTATION (if any):
Applicant: self‑represented.
Respondents: self‑represented.
On 5 October 2011, the Vicky and Jane Hunterland entered a building contract with Mr Rosa for the renovation of their home. The parties fell into dispute about the provisional cost items and the construction of a driveway. The Hunterlands believed they would be getting a credit from the contract sum; Mr Rosa had a different impression.
The Hunterlands filed an application for a refund of $27,845 for unapproved variations, plus interest, plus the costs of rectification. Mr Rosa counterclaimed for, among other things for variations to the contract works and additional costs of prime cost items. The Tribunal ordered Mr Rosa pay the Hunterlands $36,493.26 plus interest and costs.
Mr Rosa wants to appeal that decision. He has fourteen grounds of appeal but they can be grouped as follows:
a) The learned Member erred in not dealing with, or erred in her dealings with, earlier applications.
b) The learned Member did not provide procedural fairness.
c) The learned Member erred in her application of the Domestic Building Contracts Act 2000 (Qld) (DBC Act).
d) The learned Member erred in fact and law.
Two of Mr Rosa’s grounds of appeal - that the learned Member did not deal with earlier applications and that the learned Member did not provide procedural fairness – are errors of law for which leave is not required. Otherwise, the grounds of appeal involve questions of mixed fact and law for which leave is required. Leave to appeal will usually be granted where there is a reasonable argument that the decision is attended by error, and an appeal is necessary to correct a substantial injustice to the applicant caused by that error.[1]
[1]Pickering v McArthur [2005] QCA 294 at [3].
A preliminary issue - should the Appeals Tribunal…
Continue reading Rosa v Hunterland (No 2)
Sign in free to access the full text
- AGLC
- Rosa v Hunterland (No 2) [2015] QCATA 187
- Case
- [2015] QCATA 187
- Decision Date
CaseChat Overview and Summary
The legal issues before the court were the proper interpretation of the fixed price contract and the assessment of Hunterland's claims for variations and provisional cost items. The court had to determine whether the Tribunal's dismissal of Rosa's counterclaim was correct, focusing on whether the errors made were factual or legal in nature. The court's role was to review the Tribunal's decision without conducting a fresh hearing of evidence, unless it found significant errors that warranted reconsideration.
The Supreme Court found that the Tribunal had indeed made errors in its interpretation of the contract and in its assessment of Hunterland's claims. The court held that these errors were not merely factual but were indicative of a misunderstanding of the contractual terms, which amounted to an error of law. Consequently, the appeal was allowed, and the Tribunal's decision was set aside. The matter was returned to the Tribunal for reconsideration without the need for additional evidence. This decision underscored the importance of correctly interpreting fixed price contracts in domestic building disputes and highlighted the consequences of legal errors in such contexts.
Orders
Orders of the court
1. The appeal is allowed.
2. The decision of the Tribunal dated 29 November 2013 dismissing John Rosa’s counterclaim is set aside.
3. The matter be returned to the Tribunal for reconsideration of the counterclaim without the hearing of additional evidence.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.