Rocter Tanks Pty Ltd v Adam and Ors No. Scciv-00-697

Link copied
Case Copied 31 min read

ROCTER TANKS PTY LTD  v  ADAM and ORS
[2001] SASC 285

Full Court:  Doyle CJ, Perry and Bleby JJ

  1. DOYLE CJ.          I agree with the reasons given by Perry J for concluding that the appeal to the Full Court is competent, that were it necessary to grant leave to appeal such leave should be granted, and that the appeal should be allowed.  I also agree that the parties should be allowed an opportunity to consider the position, and then to put further submissions to the Court as to the disposition of the third party proceedings.

  2. Accordingly, I would make the following orders:

    (1)    that the appeal be allowed;

    (2)    that the order of the Supreme Court allowing the appeal to this Court be set aside;

    (3)    that for that order there be substituted an order that the appeal to the Supreme Court be allowed, that the decision of the Magistrates Court be set aside; that for that decision there be substituted an order that the plaintiff in the Magistrates Court have judgment against the defendants for the sum of $13,100 with costs, and that the counterclaim by the defendants in the Magistrates Court against the plaintiff be dismissed; and that the cross-appeal to this Court be dismissed;

    (4)    that the respondents pay to the appellants the costs of the appeal to this Court;

    (5)    that the question of the orders to be made in relation to the order that the third party proceedings be dismissed be adjourned for further consideration.

  3. I would hear the parties on the question of the costs of the appeal to the Full Court.

  4. PERRY J. The appellant, Rocter Tanks Pty Ltd (“Rocter Tanks”) sued the respondents, Jim Adam and Deborah Adam, in the Magistrates Court (Civil Division). In the proceedings it claimed $11,700 which it asserted was the agreed price for the construction by Rocter Tanks of a reinforced concrete tank on Mr and Mrs Adam’s property at Oakbank.

  5. Mr and Mrs Adam denied liability, and counterclaimed $14,621 damages, said to be the cost of rectifying the alleged failure by Rocter Tanks to put the tank underground. At the same time they issued third party proceedings against Simon Foale trading as Oakbank Earthmoving & Bitumen Paving, claiming an indemnity from him with respect to Rocter Tanks’ claim, on the ground that he failed properly to excavate the site for the tank.

  6. The learned special magistrate who heard the trial gave judgment in favour of Rocter Tanks against Mr and Mrs Adam for $6,826.30, and judgment in favour of Mr and Mrs Adam on the third party proceedings against Mr Foale for $4,873.70. In due course I will explain the basis upon which he reached that result.

  7. Rocter Tanks appealed to a single judge of this Court. Mr and Mrs Adam lodged a cross-appeal. Mr Foale did not appeal against the judgment given against him.

  8. The learned judge on appeal allowed the appeal and cross-appeal and quashed the judgments under appeal. He substituted a judgment in…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Rocter Tanks Pty Ltd v Adam and Ors No. Scciv-00-697 and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2001] SASC 285
Decision Date

CaseChat Overview and Summary

Rocter Tanks Pty Ltd initiated legal proceedings against Mr and Mrs Adam, along with third-party proceedings against Mr Foale, seeking the contract price of $11,700 for the installation of a water tank, plus interest. The dispute arose from the inadequacy of the excavation performed by Mr Foale, which Rocter Tanks claimed was insufficient to accommodate the tank. Rocter Tanks argued that Mr and Mrs Adam failed to mitigate their losses by not accepting a settlement offer, which would have involved Rocter Tanks performing the necessary remedial work at their own risk.

The court had to decide whether Rocter Tanks owed a duty to ensure the adequacy of the excavation before installing the tank and if Mr and Mrs Adam failed to mitigate their losses by not accepting the settlement offer. The court also had to determine if Mr and Mrs Adam's counterclaim against Rocter Tanks and their claim against Mr Foale were valid.

The court found that Rocter Tanks was not under a duty to ensure the adequacy of the excavation, as it was not manifestly inadequate. The court further held that Rocter Tanks was entitled to recover the contract price and interest from Mr and Mrs Adam, totalling $13,100. The court also ruled that Mr and Mrs Adam's counterclaim against Rocter Tanks should be dismissed. Regarding the third-party proceedings, the court held that Mr and Mrs Adam could claim damages from Mr Foale for breach of contract, but they had to counter the argument that they failed to mitigate their losses by not accepting Rocter Tanks' settlement offer.

The court ordered judgment to be entered for Rocter Tanks against Mr and Mrs Adam for $13,100, dismissing their counterclaim. The court also ordered the dismissal of Mr and Mrs Adam's claim against Rocter Tanks. As for the third-party proceedings, Mr and Mrs Adam were entitled to damages from Mr Foale for breach of contract, but they must counter the argument that they failed to mitigate their losses by not accepting Rocter Tanks' settlement offer.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

DOYLE CJ PERRY J BLEBY J
This was not a case where the excavation was so manifestly and clearly inadequate that Rocter Tanks owed a duty not to pour the tank until any perceived problem had been raised with the building owner.Conclusions as to the Causes of Action It follows that Rocter Tanks was entitled to recover against Mr and Mrs Adam the contract price for the erection of the tank, that is, $11,700. In the claim in the Magistrates Court, Rocter Tanks also sought interest, and there is no reason why it should not be awarded interest. Assuming that judgment will be entered in the Magistrates Court in accordance with the decision of this Court within a short time from now, the period over which interest falls to be calculated is approximately two years. At, say, 6%, the total for interest would be approximately $1,400. This would bring up a total of $13,100. Putting aside for one moment the question whether Rocter Tanks needs leave to appeal to the Full Court, judgment should be entered for Rocter Tanks against Mr and Mrs Adam for that amount. An order should be made dismissing the counterclaim by Mr and Mrs Adam against Rocter Tanks. As for the third party proceedings, Mr and Mrs Adam’s cause of action against Mr Foale is for damages for breach of the contract pursuant to which he agreed to excavate the site. More particularly, the damages should be such damages as flow from an implied term of the contract that the excavation would be sufficient to accommodate a tank of the dimensions of the tank to be erected by Rocter Tanks. It follows that, strictly, the claim by Mr and Mrs Adam in the third party statement of claim against Mr Foale for an indemnity with respect to any amount which they might be ordered to pay to the plaintiff, Rocter Tanks, was misconceived. However, assuming that the technical deficiency in their pleadings would not preclude the entry of a judgment on the third party proceedings in accordance with their legal entitlement, Mr and Mrs Adam face a more substantial difficulty. This is that they must counter the argument that they failed to mitigate their loss, in that they failed to take reasonable steps to remedy the breach of contract by Mr Foale. More particularly, it was contended on the hearing of the appeal by Mr Kourakis QC of counsel for Rocter Tanks that Mr and Mrs Adam acted unreasonably in refusing to accept the settlement proposal conveyed to their solicitor, Mr White, as recorded in Mr White’s letter to Rocter Tanks dated 22 June 1999. In my opinion, that submission is correct. Whatever misgivings Mr and Mrs Adam might have entertained as to the use of Acrow props in order to elevate the lid of the tank to enable the procedure which was being suggested by Rocter Tanks to be followed, the fact is that the remedial work which Rocter Tanks was offering to perform in conjunction with Mr Foale was entirely at Rocter Tanks’ risk. As recorded in Mr White’s letter, the offer of settlement was on the footing that Rocter Tanks would “stand by” its 25 year guarantee in respect of the tank. In agreeing to reduce the height of the tank by whatever method they chose to adopt, Rocter Tanks was accepting the risk involved in the remedial work.

Ratio Decidendi

Legal Principle Established

Established by: DOYLE CJ, PERRY J, BLEBY J